IN THE GAUHATI HIGH COURT (HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH)
MICHAEL ZOTHANKHUMA, J.
Ms ATW (India) Pvt. Ltd. – Appellant
Versus
Union Of India And Anr – Respondents
Arb.P. 36 of 2023
Decided on : 20-02-2024
Arbitration - Dispute Resolution - Arbitration and Conciliation Act, 1996, Section 11(6) - Clause 63 & 64 of General Conditions of Contract (GCC)
Fact of the Case:
The petitioner entered into a contract agreement for construction work, completed the work, and raised a dispute regarding non-payment. The petitioner sought appointment of an Arbitrator under Section 11(6) of the Arbitration and Conciliation Act, 1996.
Finding of the Court:
The Court found that the dispute resolution clause in the contract agreement limited arbitration to claims below 20% of the contract value. The Court dismissed the petition, stating that the dispute was not arbitrable due to exceeding the 20% threshold.
Issues: Validity of the arbitration clause, applicability of the 20% threshold, and the Court's jurisdiction under Section 11(6) of the 1996 Act.
Ratio Decidendi: The Court's jurisdiction under Section 11(6) is limited to examining the existence of an arbitration agreement. The Court may reject claims that are manifestly non-arbitrable.
Final Decision: The petition for appointment of an Arbitrator was dismissed, and the parties were advised to seek other jurisdictional remedies for adjudication of their dispute.
JUDGMENT :
1. Heard Mr. R. Hussain, learned counsel for the petitioner. Also heard Mr. H. Gupta, learned CGC appearing for all the respondents.
2. The present application under Section 11(6) of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as “the 1996 Act”), is for a reference of the dispute between the parties before a sole Arbitrator to be appointed by this Court. The petitioner’s case is that the respondent no.4 had floated Tender No.CE/CON/S-L/EMB/2005/64 for “Construction of Br. O.99 (New) span (1x4.0m RCC Arch Box) at Chainage 49.335 km and earthwork in filling in layers to form embankment at the approaches of the bridge including other ancillary work between station Dihakho-Mupa on permanent diversion in connection with Lumding-Silchar Gauge conversion project.”
3. The petitioner was selected for the contract work and accordingly, a contract agreement dated 02.03.2007 was executed between the parties at a total cost of Rs.4,30,95,325/-. The time for completion of the contract work was 18 months, i.e., on or before 21.09.2007. The petitioner’s further case is that he successfully completed the contract work on 27.03.2012, after being granted various extensions by the respondents. The dispute arose between the parties, as settlement and finalisation of the Final Bill of the petitioner was not being made by the respondents. The petitioner thereafter lodged his final claim dated 09.05.2022, claiming Rs.3,25,79,502/-. However, the same has not been paid to the petitioner.
4. The petitioner’s counsel submits that as per the contract agreement dated 02.03.2007 executed between the parties, an Arbitration Clause for settlement of disputes through arbitration is present in Clause No. 10.0 of the agreement, which incorporates the relevant Clause 63 & 64 of the General Conditions of Contract (GCC). Clause 63 & 64 of the GCC provides that the disputes between the parties, arising out of the contract, should be decided by way of Arbitration. The petitioner’s counsel submits that though the petitioner has invoked the Arbitration Clause by issuing notice dated 22.11.2022, the respondents have failed to act on the application made by the petitioner, while disputing the claim of the petitioner. The petitioner has thus approached this Court for appointment of an Arbitrator.
5. The petitioner’s counsel submits that Clause 10.1 of the contract agreement, which provides that claims or disputes beyond 20% of the contract value will not attract Clause 63 & 64 of the GCC, is a void clause. He submits that Sub-Section 6A of Section 11 of the 1996 Act provides that the Supreme Court or the High Court, while considering any application under Section 11(6A) of the 1996 Act, would have to confine it’s examination with regard to whether an Arbitrator is to be appointed, only by considering whether an Arbitration Clause existed in the contract agreement. He submits that the issue whether the Arbitrator could or could not decide the claims made by the petitioner in terms of Clause 10.1 of the contract agreement, including the validity of Clause 10.1 of the contract agreement, would have to be decided by the Arbitrator, so appointed by the Court, in terms of Section 16 of the 1996 Act. In this regard he has relied upon the Constitution Bench judgment of the Supreme Court in the case of Re-Interplay between Arbitration Agreements under the Arbitration and Conciliation Act, 1996 and the Indian Stamp Act, 1899 (supra). The petitioner’s counsel thus submits that this Court should appoint an Arbitrator in terms of Section 11(6A) of the 1996 Act.
6. Mr. H. Gupta, learned CGC for the respondents submits that in terms of Clause 10.1 of the contract agreement, which has to be read along with Clause 10.0, which incorporates Clause 63 & 64 of the General Conditions of Contract (GCC), shows that the provisions of Clause 63 & 64 of the GCC would be applicable only for settlement of claims/disputes between the parties, for a value less than or equal
The Court emphasized the importance of examining the existence and validity of an arbitration agreement at the referral stage and the rejection of manifestly non-arbitrable claims.
The main legal point established in the judgment is that all disputes capable of resolution by arbitration should be referred to the Arbitral Tribunal, and the scope of examination by the Court exerc....
Scope of judicial review by court while deciding an application under Sections 8 or 11 of Arbitration Act, post amendments by Act 3 of 2016 (with retrospective effect from 23-10-2015) and even post a....
The claims were notified within the stipulated period and submitted along with the final bill in accordance with Clause 6.6.3.0 of the GCC, making the disputes arbitrable under Clause 9.1.0.0.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.