2026 Supreme(Gau) 1770

THE GAUHATI HIGH COURT (HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH)
Devashis Baruah, J.
Deben Thaosen, S/O Sri Mojen Thaosen - Petitioner 
Versus
The State Of Assam Rep. By The Commissioner And Special Secretary To The Govt. Of Assam, Public Works Department - Respondent 
WP(C) 5943 of 2016, WP(C) 2515 of 2013
Decided On : 26-08-2026

Act Referred

CONSTITUTION OF INDIA : Art.14
CONTRACT ACT : S.74

Advocates Appeared:
For the Petitioner:Mr. A. K. Baruah, Advocate
For the Respondent: Mr. B. Gogoi, SC, PWD

JUDGMENT :

Devashis Baruah, J.

Heard Mr. A. K. Baruah, the learned counsel appearing on behalf of the Petitioner. Mr. B. Gogoi, the learned counsel appears on behalf of the PWD.

2. Both the writ petitions are taken up together for disposal by this common Judgment.

3. In WP(C) No.2515/2013, the Petitioner is aggrieved by the action on the part of the Respondent Authorities in issuance of a letter of cancellation of the work order dated 03.12.2012 and the consequential actions taken for issuance of the Short Tender Notice and the Letter of Acceptance issued to the private Respondents.

The Petitioner has further sought for appropriate directions upon the Respondents not to proceed further for withdrawing the performance security money of the Petitioner from the bank of the Petitioner.

4. It is relevant to take note of that the Petitioner was granted a contract for Construction of rural roads, culverts, minor bridges and further for routine maintenance of work for five years under PMGSY (Regular) PH-VII, 2007-08 vide the communication dated 30.09.2008. In terms with the said communication, the Petitioner was required to carry out Construction of Road from 1) Mouzadar Gaon No. 1 to Sarkebasti; 2) Tini Ali Bazar to Bordoloi Pathar; 3) 4th KM of Bhalukmari Kaki Raod to Jaysagar; 4) Road from 4th KM of Kaki Marketing Road to Ramnagar 2 and 5) 17th KM of NH- 54 to Khiring Khiring Bazar including Cross drainage works and routine maintenance of the works for five years under PMGSY (Regular) Ph-VII, Package No. AS-19-102.

5. The period of completion of the Construction work was 18 months, and thereafter, for routine maintenance for 5 years thereafter. The date of completion of the construction work was on 15.04.2010. The Petitioner was granted extension up to 30.09.2011.

6. The materials on record show that in accordance with Clause 45 of the General Conditions of Contract (GCC), the Petitioner was paid an amount of Rs.46,55,970/- as Mobilization Advance and on account of equipment advance an amount of Rs.80,24,170/- was paid, totaling to Rs.1,26,79,960/-. Subsequent thereto, in terms with Clause 45.3 of the GCC, against the 7 (seven) running Account Bills, certain amounts were recovered. The details are given in the chart herein under:-

7. The materials on record further transpire that the Petitioner claims that on account of security problem as well as breach of the reciprocal obligations by the Respondents, the Petitioner could not carry out the work. The Petitioner had written various letters in that regard. The records also show that on various occasions, the Executive Engineer, had issued notices to the Petitioner to complete the work.

8. On 03.12.2012, the contract with the Petitioner was terminated on the ground of fundamental breach of the terms of the contract. It is relevant to observe the following details:

(A) The period of the contract stipulated that the period within which the construction work would be completed was 15.04.2010.

(B) Extension was granted for completion of the construction work upto 30.09.2011.

(C) At the time of termination of the contract, the Petitioner against the five construction works could achieve progress of 34%, 65%, 100%, 72% and 42%.

9. The contract was terminated by the Executive Engineer, PWD on 03.12.2012. The Petitioner requested the Executive Engineer vide a communication dated 10.12.2012 to recall the termination and grant extension up to 31.03.2013. The Petitioner thereupon requested various other authorities of the PWD including the Chief Engineer, PWD to revoke the termination order. However, instead of revoking, the Performance Security so submitted by the Petitioner in the form of TDR Receipt was invoked.

10. The Petitioner thereupon filed the writ petition being WP(C) No. 377/2013 challenging the termination order. This Court vide an order dated 01.02.2013 taking into account that the Petitioner filed an Appeal before the Chief Engineer, PWD (Roads) on 17.12.2012, disposed of the writ petition wit