Judges : J.B.KOSHY,K.P.BALACHANDRAN
Sriram Engineering.Construction Co.Ltd. - Appellant
Versus
Kerala State Industrial Development Corporation - Respondent
Case No : OP No. 20099 of 1999 (P)
Decided On : 01/22/2007
Advocates Appeared :
For the Petitioner : Sabu George, Advocate. For the Respondent: M. Pathrose Mathai, Advocate.

Subject

Contract Disputes - Revenue Recovery Proceedings

Act Referred

CONSTITUTION OF INDIA : Art.226

Headnote

Kerala Revenue Recovery Act 1968 - Section 71 - Constitution of India - Art.226 - Can revenue recovery proceedings be taken by a Government Company for realising damages arising out of alleged breach of contract especially when damages are not quantified through adjudication is the main question to be decided in this Writ Petition. Petitioner is a public limited company registered under the Companies Act. First respondent Kerala State Industrial Development Corporation Ltd. (KSIDC) is a State Government undertaking and is a fully owned Government Company - Held, admittedly, petitioner is not asking for judicial review of terms of the contract. Petitioner is not attacking any of the terms of the contract. Petitioner is only stating that no amounts are due to KSIDC. It has not committed breach and breach, if any, is committed by KSIDC. It has already filed a suit for recovering the damages. KSIDC initiated revenue recovery proceedings stating that 'amounts are due'. It is even without an adjudication by the Managing Director of KSIDC. Disputed amounts not settled or adjudicated cannot be recovered by the proceedings under Revenue Recovery Act. Ext.P2 is not a statutory contract. Respondents can realize - There is no power for the Chief Engineer to determine the amount and demand and recover it from the petitioner. Here, so far the Managing Director has not decided the amount as mentioned in the clause relied on by the respondents disputed amount only by adjudication and in the absence of clause for arbitration the only remedy available is to file a suit or file a counter claim in the pending suit. In this case, the Managing Director did not decide the question of damages payable from KSIDC as mentioned under Clause 34 after notice and adjudication. Ext.P12 is a decision from Chief Engineer. Clause 34 cannot be treated as an arbitration clause. When petitioner's claim for damages to the tune of Rs.43 lakhs was rejected under Clause 34, petitioner, treating it as arbitration award, filed petition to set aside the award and KSIDC itself contended that Clause 34 cannot be equated to arbitration and Ext.P11 decision of Managing Director is not amounting to arbitration award. Here, breach of contract is not admitted and petitioner contended that termination of contract by KSIDC is illegal and suit for recovering damages is pending - Petition allowed to extent.

Judgment :-

Koshy, J.

Can revenue recovery proceedings be taken by a Government Company for realising damages arising out of alleged breach of contract especially when damages are not quantified through adjudication is the main question to be decided in this writ petition. Petitioner is a public limited company registered under the Companies Act. First respondent Kerala State Industrial Development Corporation Ltd. (KSIDC) is a State Government undertaking and is a fully owned Government Company. The petitioner was issued with a letter of indent, Ext.P1 dated 21.2.1998, by the first respondent for erection of Water Treatment Plant with rapid and gravity filter pump house and value of the work was estimated at Rs.1,36,20,295/=. Petitioner has deposited Rs.2,00,000/= and the Indent Document was signed by both parties. Ext.P2 is the agreement executed. By Ext.P3 dated 8.3.1998, the site was handed over and the agreement was that project will be completed within fifteen months. According to the petitioner, only on 5.5.1998 drawings were made available by KSIDC and even those drawings were not complete. On 20.8.98, by Ext.P4, final drawings were supplied to the petitioner. Only on 22.12.1998, by Ext.P5, the respondent forwarded details of Footings to be provided for the stub columns supporting the Filter box, after closing of part of the work. Various correspondence took place between the parties. According to the petitioner, without fulfilling contractual obligations of the respondents, by Ext.P9 dated 13.1.1999, Chief Engineer of first respondent cancelled the contract at the risk and cost of the petitioner. Thereafter, by Ext.P10 dated 10.4.1999 addressed to Managing Director of respondent Corporation, the petitioner made claims for Rs.43 lakhs and requested him for arbitration and settling the issue. The claims were made onsix grounds namely:

1. Return of Security deposit Rs.2/- Lakhs with interest at 18%.

2. Idle Labour charges Rs.0ne lakh with interest.

3. Compensation due towards investment at idling machines (hold up of tools & Tackles Rs.5/- lakhs with interest 18%.

4. Compensation for building materials Rs.5/- lakhs with interest at 18% p.a.

5. Damages and delay caused in releasing due payments Rs.5/- lakhs.

6. Consequential damages due to unlawful termination - loss of reputation, loss of business good will Rs.25/- lakhs.

Managing Director rejected the claims by order dated 7.6.1999 (Ext.P11). It is stated in Ext.P11 as follows:

"Hence the claim petition dated Nil- 3-99 of the claimant contractor is totally and summarily rejected outright."

Thereafter, the petitioner filed an Original Petition before this court treating Ext.P11 order of the Managing Director as arbitral award. That was rejected accepting contentions of the respondents that there was no arbitration clause in the agreement and letter of the Managing Director cannot be treated as an arbitral award. Thereafter, the petitioner filed a suit as O.S.No.115 of 2006 before the Sub Court, Thiruvananthapuram claiming damages from the K.S.I.D.C. and the suit is pending.

2. By Ext.P12 dated 22.7.1999 Chief Engineer of the first respondent (second respondent in this O.P.) made a demand of Rs.12,19,769/= as due from the petitioner for re-arranging the work and also threatened that in the event of failure to pay the above sum, Revenue Recovery Act will be invoked for the recovery. Ext.P12 is reproduced as follows:

"The above work which was awarded on contract to you as per agreement No.IGC/KTP/03 of KSIDC, was terminated as per order second cited. Also, your claims were rejected vide letter third cited.

As already informed and as per conditions of tender and agreement, the loss if any sustained by KSIDC in rearranging the work is to be realized from you.

A statement showing the loss, provisionally assessed, in rearranging the work is enclosed herewith for reference. But you are informed that the final figures at the completion of work shall be assessed as cost of completion of th