Judges : R.RAJENDRA BABU
Bel House Associates (P) Ltd. - Appellant
Versus
General Manager, Southern Railway - Respondent
Case No : A.R.13 & 15 of 1999
Decided On : 01/23/2001
Advocates Appeared :
Meijo Kurian Puvathingal For Petitioner M. C. Cherian For Respondents
Arbitration - Appointment of Arbitrator - S.11 of the Arbitration and Conciliation Act, 1996 - Clause 64 of the General Conditions of Contract - Summary of Acts and Sections: S.11, Clause 64 of the General Conditions of Contract - The court discussed the interpretation and application of S.11 and Clause 64 of the General Conditions of Contract in appointing an arbitrator for resolving disputes between the parties.
Fact of the Case:
M/s. Bel House Associates Pvt. Ltd. under liquidation filed petitions for appointing an arbitrator to adjudicate disputes with the Southern Railway. The Railway contested, arguing that the court cannot appoint an independent arbitrator but enforce the procedure in the agreement for arbitration.
Finding of the Court:
The court found that the agreement between the parties admitted the existence of an arbitration clause and that the disputes between the parties required settlement. It rejected the request for appointing an independent arbitrator but directed the respondent to appoint an arbitrator to resolve the disputes.
Issues: The main issue was whether the court could appoint an independent arbitrator or only enforce the procedure in the agreement for arbitration.
Ratio Decidendi: The court held that when the parties had agreed upon a procedure for appointing an arbitrator, the court could only implement the agreed procedure and could not appoint an independent arbitrator at the first instance.
Final Decision: The court rejected the request for appointing an independent arbitrator but directed the respondent to appoint an arbitrator to resolve the disputes. If the respondent failed to appoint the arbitrator within two months, the petitioner could seek further orders from the court for appointment of an arbitrator.
R. Rajendra Babu, J.
M/s. Bel House Associates Pvt. Ltd. under liquidation through the Official Liquidator filed these petitions under Ss,. 11 (5) and (6) of the Arbitration and Conciliation Act, 1996 for appointing an arbitrator for adjudicating the disputes between the petitioner and the respondents, the Southern Railway. The averments in both these petitions are similar. A.R.13/99 was on the basis of an agreement between the parties No. TCR/GUY/CN/12/90 dated 24.7.90 relating to the construction of the Station Building at Guruvayoor. A.R.No.15/99 was based on the agreement between the parties bearing No. 54/CN 88 dated 18.10.88 relating to the construction of new BG line from Trichur to Guruvayoor and other construction works. The relief prayed for in both these petitions are for appointing a sole arbitrator to adjudicate upon the disputes between the parties. It was alleged in both petitions that the entire work had been executed and completed in all respects and handed over to the Railway and the petitioner had to execute some extra items of work at the instance of the railway officials including minor items as well as the major items of work and before commencement of the execution of these extra items, the petitioner had duly intimated the Railway about the fixation of these extra rates and submitted their rate analysis for the same. But the, Railway had neglected to arrive at a rate by themselves. As there arose disputes, the petitioner issued notice to the General Manager, Southern Railway, Madras to appoint a sole arbitrator in accordance with Clause 63 of the General Conditions of Contract forming part of the agreement. The Railway did not comply with the above terms, a reminder also was sent and even then the Railway had not complied with the above demand. Hence the petitioner was compelled to approach this court for appointing an arbitrator to resolve the disputes between the parties.
2. Counter affidavit was filed by the respondents wherein the agreement between the parties had been admitted and also the existence of the arbitration clause. It was contended that there was no proper notice as the petitioner company was under liquidation and while so notices were issued by incompetent persons. It was further contended that there was no dispute for arbitration and when a procedure for arbitration had been mentioned in the agreement, the court cannot appoint an arbitrator, but it can only enforce the procedure contemplated in the agreement for arbitration.
3. Heard the learned counsel for the applicant and the standing counsel for me respondents.
4. The agreement between the parties was admitted. Existence of arbitration clause also was admitted. The applicant company was under liquidation and the petition was filed by the Official Liquidator. A notice also had been issued at the instance of the arbitrator demanding the initiation of arbitration proceedings- These are disputes between the parties for settlement Hence the contention mat there: was no notice cannot be accepted.
5. The main contention put forward by the respondents the Southern Railway was that when the agreement provides an arbitration clause and the procedure for arbitration, this court cannot appoint an independent arbitrator, but can only direct the implementation of the procedure contemplated in the agreement. Clause & of the General Conditions of Contract speaks about the arbitration clause. It says that disputes and difference of any kind whatsoever arising out of or in connection with the contract shall be decided by arbitration. Clause 64 of the General Conditions of Contract prescribes the procedure for appointing an arbitrator. Clause 64 reads:
(1) In the event of any dispute or difference between the parties hereto as to the construction or operation of this contract, or the respective rights and liabilities of the parties on any matter in question, dispute or difference on any account, or as to the withholding by the Railway of any ce
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.