SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

1977 Supreme(Ker) 292

Judges : P.SUBRAMONIAN POTI
CHELLAPPAN - Appellant
Versus
EXECUTIVE ENGINEER - Respondent
Case No : O.P. No. 2634 of 1977
Decided On : 12/21/1977
Advocates Appeared :
K.G. Devarajan; C.N. Sasidharan; For Petitioner Govt. Pleader; For Respondents

The determination of the quantum of damages on breach of the contract was not within the purview of the Executive Engineer, and the proceedings under the Revenue Recovery Act for recovery of the sum claimed due as damages for breach of contract would be incompetent until determination of the quantum of such amount.

Headnote:

Revenue Recovery Proceedings - Validity of Revenue Recovery Proceedings - Sections 68(1), Clause 2 of the conditions of the contract - The court discussed the validity of revenue recovery proceedings taken against the petitioner by the Revenue authorities to recover damages for breach of contract. The court examined the rights of the parties to the contract, the propriety of termination of the contract by the respondent, and the proceedings for recovery under the Revenue Recovery Act. The court held that the determination of the quantum of damages on breach of the contract was not within the purview of the Executive Engineer and that the proceedings under the Revenue Recovery Act for recovery of the sum claimed due as damages for breach of contract would be incompetent until determination of the quantum of such amount.

Fact of the Case:

The petitioner tendered for the construction work of certain structures in the State Guest House premises, which was accepted by the Executive Engineer. The work was not completed within the specified period, and the contract was terminated. The petitioner complained about the recovery sought to be made from him as damages for breach of contract.

Finding of the Court:

The court held that the determination of the quantum of damages on breach of the contract was not within the purview of the Executive Engineer and that the proceedings under the Revenue Recovery Act for recovery of the sum claimed due as damages for breach of contract would be incompetent until determination of the quantum of such amount.

Issues: The issues involved were the validity of the termination of the contract by the respondent and the propriety of the revenue recovery proceedings to recover damages for breach of contract.

Ratio Decidendi: The court emphasized that the determination of the quantum of damages on breach of the contract was not within the purview of the Executive Engineer and that the proceedings under the Revenue Recovery Act for recovery of the sum claimed due as damages for breach of contract would be incompetent until determination of the quantum of such amount.

Final Decision: The Original Petition was allowed, and no costs were awarded in the circumstances of the case.

Judgment :-

1. A difficult but interesting question the decision of which may be of considerable consequence arises in this case. The question relates to the validity of the revenue recovery proceedings taken against the petitioner by the Revenue authorities to recover what is claimed as due from him as damages for breach of the contract he had entered into with the Executive Engineer, PWD. (B&R) Division, Trivandrum. That the petitioner tendered for the work of construction of certain structures in the State Guest House premises at Trivandrum on 21-6-1975, that the Executive Engineer concerned accepted bis tender, that the petitioner executed an agreement on 17-7-1975 for completion of the work before the end of December, 1975 and the work was not completed within the period specified in the agreement are admitted facts. The petitioner has some explanation to offer for the delay in the completion of the work. According to him necessary materials which the PWD. had to supply him in accordance with the terms of the agreement were not supplied in time. By the time they were supplied the petitioner is said to have fallen ill consequent upon which he is said to have sought for extension of time for completion of the work. But then even before the period agreed upon for completing the work had expired the contract was terminated. That it was so terminated is not disputed. It was terminated on 13-11-1975 and the security deposit was forfeited. It was stated in Ext. P3 letter issued by the first respondent that the petitioner is seen to have abandoned the work after completing the foundation masonry for a portion of the compound wall at the entrance, that repeated requests were made to the petitioner to complete the work with the least delay, that he had been told repeatedly that the progress was very slow, that therefore the work could not be completed within the specified period and that there was no progress as required by the terms of the contract which enabled the first respondent to cancel the contract. I am not called upon in this case to decide whether there was sufficient excuse for the petitioner for defaulting to carry out the work according to the time schedule contemplated by the parties or whether there were circumstances which may justify the termination of the contract. That would be beyond the province of this Court as I will presently indicate. But the further contention of the petitioner is that recovery sought to be made from him of an amount of Bs. 31843/-as intimated by Ext. P4 ought not to be permitted. The petitioner complains that he was never given an opportunity to show how this amount could be claimed as damages and that he was never given an opportunity to show that the case that loss was caused by re-arrangement of work had no basis. The complaint is that the unilateral determination by the Executive Engineer of the quantum of damages and proceedings for recovering such quantum were not warranted by law.

2. The two questions which therefore arise in this case are: (1) Whether this Court should go into the question as to the propriety of the termination of the contract by the first respondent and (2) Whether revenue recovery proceedings can be resorted to recover what is claimed as damages due as a result of breach of contract.

3. When the State enters into a contract with the citizen the rights of the parties to the contract are determined solely on the terms of the contract and the remedies available for breach of contract to either of the parties would be in terms of the contract, in the matter of entering into contractual relations the State is exercising its executive power and the provisions of Part III of the Constitution impose certain restrictions in the matter. It is not open to the State to pick and choose the persons with whom it proposes to enter into a contract. In other words, the exercise of such executive power at the stage prior to the entering into a contract is liable to be examined by a

















Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
Judicial Analysis

AI

SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top