2009 Supreme(Ker) 942
High Court of Kerala
THE HONOURABLE MR. JUSTICE S.S. SATHEESACHANDRAN
Salu Varghese
Versus
P.P. Prabhakaran & Others
CRP.No. 613 of 2009
Decided on : 19-11-2009
Subject
Civil Law - Execution of Decrees
Act Referred
LIMITATION ACT : S.125, S.3
Headnote
Civil Procedure Code, 1908 - Section 47, Order XXI Rule 2 & Order XXI Rule 2A - Limitation Act, 1963 - Article 125 - Revision is directed against the order - Petitioner is the judgment debtor in the execution petition - Execution proceedings relate to the decree passed in O.S., a suit for money, and the respondents are the decree holders - Petitioner/judgment debtor had moved an application under O.XXI Rr.1 and 2 of Code of Civil Procedure to certify the payment purported to have been made to one of the decree holders, the 1st respondent by way of a cheque to satisfy the decree - That application, after enquiry, was dismissed by Additional Sub Judge, under the impugned order - Propriety and correctness of that order is challenged in the revision - Held, Court may also refer to some of the observations made in the previous order while disposing of the earlier revision, which no doubt, cause serious doubt and generate considerable suspicion regarding the payment under the cheque though a different view had been taken by the Execution Court - Court has observed that there are suspicious circumstances in the case with regard to the issuance of the cheque taking note the cheque was not given as an account payee, that it could be encashed with a forged signature by any one and that the issuance of the cheque was not brought to the notice of the court earlier - Court do not find any reason to doubt the submissions made by the counsel that the conviction entered against him in the criminal case referred to above by virtue of a remand in the revision, is pending consideration before the appellate forum - Such questions as to the validity of the cheque, payment to one of the decree holders etc. have got no significance at all as the application for certification of payment had been filed much after the time prescribed and it was hopelessly barred by limitation - Revision lacks merit - Revision Dismissed
For the Petitioner:Pirappancode V.S. Sudhir, Advocate. --
The revision is directed against the order dated 9.10.2009 in E.A.No.402 of 2000 in E.P.No.557 of 1996 in O.S.No.529 of 1994 on the file of the Additional Sub Court, North Paravur. Petitioner is the judgment debtor in the above execution petition. The execution proceedings relate to the decree passed in O.S.No.529 of 1994, a suit for money, and the respondents are the decree holders. Petitioner/judgment debtor had moved an application under Order XXI Rule 1 and 2 of the Code of Civil Procedure to certify the payment purported to have been made to one of the decree holders, the 1st respondent by way of a cheque to satisfy the decree. That application, after enquiry, was dismissed by the learned Additional Sub Judge, under the impugned order. Propriety and correctness of that order is challenged in the revision.
2. I heard the counsel on both sides. Previously, there was a revision before this Court as CRP.No.629 of 2001 at the instance of the decree holders when the execution court had passed an order on the application of the judgment debtor that there was payment of the decree debt by way of cheque as contended by him in his application and also to record full satisfaction of the decree debt. That revision was disposed by this Court by order dated 17.8.2005 setting aside the order of the execution court and remitting the case for fresh consideration subject to the observations made. Pursuant to such remission, the disputed cheque was sent over to a forensic expert for scientific examination and the report collected is Ext.X3. Petitioner/judgment debtor, on his side, had examined three witnesses including himself as PWs.1 to 3, and exhibited A1 and A2. On the side of the decree holders, the 1st respondent was examined as RW1. Towards court exhibits, two documents were exhibited as X1 and X2 apart from X3 report. On the basis of the materials produced, the execution court arrived at the conclusion that the payment claimed by the judgment debtor by way of cheque is acceptable, but it is not sufficient under the rule for certification of the payment. Since there are several decree holders, payment to one of them was not sufficient in the absence of consent and concurrence by the other decree holders for certification of the payment of the decree debt, was the view taken by the execution court to conclude that the request made under the application by the judgment debtor cannot be allowed. The application was therefore dismissed. Petitioner/judgment debtor challenge the above order contending that once payment to one of the decree holders has been established by the materials produced in the case, that has to be treated as sufficient for certification of the payment as covered by the rule to satisfy the decree debt.
3. In the given facts of the case, it has become essential to advert to the backdrop of the case and most particularly what transpired earlier in the execution proceedings. In the previous order dated 17.8.2005 disposing C.R.P.No.629 of 2001, proceedings in execution had been adverted to with reference to the dates of enquiry on the execution application moved by the judgment debtor and what transpired in the enquiry. It would be profitable to reproduce what has been stated with respect to the above aspect in that order, which reads thus:
"The execution petition was filed for realisation of an amount of Rs.1,68,529/-. The suit was decreed on 22.12.1995 and the E.P. was filed on 17.9.1996. The alleged handing over of the cheque was on 30.7.1997. The proceedings paper in the execution petition shows that the judgment debtor was praying for time for filing objections on 2.6.1997. The case was posted for filing objections to 14.8.1997. On that day also, the judgment debtor prayed for time for filing objections and the case was adjourned to 12.12.1997. Again the judgment debtor prayed for time for filing objections and the case was adjourned to 30.3.1998. On 30.3.1998, the counsel for the judgment debtor represe