2017 Supreme(Ker) 535
IN THE HIGH COURT OF KERALA AT ERNAKULAM
DAMA SESHADRI NAIDU, J.
K.RAVINDRAN – PETITIONER
Versus
THE SECRETARY, PUBLIC WORKS DEPARTMENT AND ORS. – RESPONDENTS
W.P. (C) No. 23149 of 2012 (P)
Decided On : 10-04-2017
Subject
Contract Disputes - PAYMENT DISPUTE
Act Referred
CIVIL PROCEDURE CODE : O.2 R.2
INTEREST ACT : S.3, S.3(1)(a), S.3(3)(d)
Headnote
For the Petitioner: SRI. BABU KARUKAPADATH, SMT. M.A. VAHEEDA BABU, SRI. JAGAN GEORGE, SRI. K.A. NOUSHAD, SRI. P.G. PRAMOD, SRI. KANDAMPULLY RAHUL
For the Respondent: SMT. A.C. VIDHYA
Facts:
To the petitioner, a contractor, the Government has allotted a civil work--the improvement of a road. On 11.03.2005, he contracted with the Government. Later, the Government expanded the scope of the work and gave a revised estimate, as approved by the Superintending Engineer, Roads and Bridges, PWD, North Circle, Kozhikode-the third respondent. Eventually, the contractor completed the work on 13.03.2007 and obtained the work- completion certificate on 15.10.2007. Throughout or even thereafter, the Department did not complain against the contractor or the manner of his completing the work.
2. On 01.08.2007, the contractor raised a bill for the completed work. But he was paid only in part on 18.10.2007. The balance remained to be paid was Rs.42,48,665/-.
3. Failed to realize the balance amount, the contractor filed W.P.(C) No. 911 of 2009 before this Court and invited a judgment. This Court, overruling the Department's objections, fixed three-months' time, through Ext.P1 judgment, for the Government to pay the amount. That three months' time came to an end on 14.01.2010. Later, the contractor sent Ext.P2 reminder to the Superintending Engineer, who informed the contractor, through Ext.R4, that suitable directions were given to the Executive Engineer, the 4th respondent, to settle the bills.
4. So on 07.04.2012, the contractor requested the Executive Engineer to pay. Eventually, on 25.08.2012, the contractor, perhaps informed by the Executive Engineer, went to his office to receive the amount. He, however, wanted to receive the amount under protest. On the other hand, the Executive Engineer insisted that the contractor should receive the amount without protest. When the contractor refused to receive the amount without protest, the Executive Engineer, too, declined to settle the bills.
5. As seen from the record, on 27.08.2010, the Executive Engineer issued Ext.P5 communication reiterating his stand that the contractor should receive the amount without protest. Eventually, on 07.09.2012, the contractor received the amount and submitted Ext.P6 letter dated 07.05.2012, thereby recording his protest, anyway. Thereafter, the contractor filed this writ petition demanding interest on the entire period from the day the bill was due or, at least, from the day the Court fixed a time-frame for the Government to pay the bills.
Submissions:
The Petitioner's:
6. Smt. M.A. Vaheeda Babu, the learned counsel for the petitioner, strenuously contends that the Government had no tenable objection why it did not settle the bills, despite the contractor's completing the work to the Department's satisfaction. She has, on this count, reminded the Court that at no point in time did the Government object to or complain about the quality of the work or the time frame. She has straight away drawn my attention to Section 3 of the Interest Act, 1978, to hammer home her contention that under clause (a) of sub-Section (1) of Section 3, the contractor is entitled to interest.
Respondents':
7. On the other hand, the learned Government Pleader has submitted that though the Department was willing to settle the bills, it is the contractor who insisted--unreasonably, at that--on his receiving the amount only under protest. According to her, clause 56 as extracted in Ext. R4(a) would mandate that the contractor is not entitled to any interest. She contends that the contractor undertook to claim no interest, as has been specified under Ext.R4(a).
8. Head Smt. M.A. Vaheeda Babu, the learned counsel for the contractor and the learned Government Pleader, besides perusing the record.
Issue:
9. Section 3 (1) (a) of the Interest Act provides for payment of interest on delayed payments. Section 3 (3) (d) exempts the interest if there is an "express agreement," which the contractor has with the Department. That express agreement does not affect a "judgment debt", though. Here, the Court directed the Department to pay the amounts due to the contractor within a time frame. T