SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2015 Supreme(Ker) 1380

IN THE HIGH COURT OF KERALA
P.N. Ravindran, Anil K. Narendran, JJ.
State of Kerala - Appellant
Vs.
Edward John - Respondent
Regular First Appeal No. 703 of 2014
Decided On : 20-05-2015

Advocate Appeared:
For the Appellant : A. Mohammed Savad, Government Header
For the Respondent:K.L. Varghese, Santha Varghese, Rahul Varghese and Ranjith Varghese, Advocates

The main legal point established in the judgment is that the appellants wrongfully deprived the respondent of the beneficial use of the money payable for the work undertaken, entitling the respondent to interest on delayed payment, as per the provisions of the Kerala Financial Code, PWD Manual, and the Interest Act, 1978.

Headnote:

Interest on Delayed Payment - PWD Contract - Kerala Financial Code, PWD Manual, and Contractual Obligations - [INTEREST] - [PWD Contract] - [Kerala Financial Code, PWD Manual, Interest Act, 1978] - The court discussed the provisions of the Kerala Financial Code, PWD Manual, and the contract for execution of the work, and concluded that the appellants wrongfully deprived the respondent of the beneficial use of the money payable for the work undertaken, and hence, the respondent is entitled to interest on delayed payment. The court also referred to the Interest Act, 1978 and allowed interest at a just and reasonable rate.

Fact of the Case:

The respondent, a PWD contractor, filed a suit for realisation of a sum due to him as per the statement of accounts furnished, along with interest, from the appellants. The appellants admitted the contract work but contended that payment was made based on strict seniority and availability of funds.

Finding of the Court:

The court found that there was delay on the part of the appellants in making payment to the respondent and held that the respondent is entitled to interest on the amount covered by the part bill and final bill from a certain date at a specified rate till realisation, together with costs.

Issues: The main issue was whether the respondent is entitled to interest on delayed payment of the amount covered by the part bill and final bill.

Ratio Decidendi: The court relied on the provisions of the Kerala Financial Code, PWD Manual, and the contract for execution of the work to establish the appellants' wrongful deprivation of the respondent's beneficial use of the money payable for the work undertaken, leading to the conclusion that the respondent is legitimately entitled to interest during the period of delayed payment.

Final Decision: The appeal was dismissed, and the court upheld the judgment and decree passed by the lower court, allowing the respondent's claim for interest on delayed payment.

JUDGMENT :

Anil K. Narendran, J.

The appellants are the defendants in O.S. No. 313 of 2006 on the file of the Court of the Principal Subordinate Judge of Thiruvananthapuram. The said suit was filed by the respondent herein for realisation of the sum of Rs. 4,27,276/- due to him as per the statement of accounts furnished, from the appellants and their assets and for allowing him to realise future interest at the rate of 18% per annum on the aforesaid sum from the date of suit till realisation together with costs of the suit. The court below by judgment delivered on 30.9.2010 decreed the suit and allowed the respondent to realise the sum of Rs. 4,27,276/- together with interest at the rate of 12% per annum from the date of suit till realisation and costs of the suit from the appellants and their assets. Aggrieved by the said judgment and decree, the appellants are before this Court in this appeal. We heard the arguments of the learned Government Pleader appearing for the appellants/defendants and also the learned counsel appearing for the respondent/plaintiff.

2. Going by the plaint averments, the plaintiff is a registered PWD contractor, who had undertaken the contract work of "Improvements to Thirupurathoor-Pulluvila Road between Ch. 2/600 to Ch. 5/600" in pursuance of Ext. B1 agreement dated 14.12.2002 executed between the plaintiff and the second defendant (second appellant herein) acting for and on behalf of the Government of Kerala. The plaintiff had completed the entire work to the satisfaction of the defendants in September, 2003. During the execution of work, in terms of the provisions in the contract, a part bill for work amounting to Rs. 5,73,007/- was drawn up during March, 2003. While the part bill was pending payment, the plaintiff proceeded with the work and completed the same on the belief that the defendants would honour their contractual obligations. But, the defendants did not release the payment due under the part bill even after completion of the work. After completion of the work, final measurement of the work carried out by the plaintiff was recorded in the measurement books and a final bill in terms of such measurements was drawn up for a sum of Rs. 14,67,988/-, excluding a sum of Rs. 5,73,007/- covered by the part bill and passed for payment on 29.9.2003. The plaintiff contended that, as per the terms of contract, the defendants were liable to pay the final bill immediately on completion of the work. However, they released Rs. 5,73,007/- covered by the part bill only on 23.2.2005 and Rs. 14,67,988/- covered by the final bill only on 12.8.2005, nearly two years after the completion of work. Therefore, the plaintiff filed the suit to realise the sum of Rs. 4,27,276/- due as per the statement of accounts furnished together with interest at the rate of 12% per annum from the date of suit till realisation, with costs from the defendants and their assets.

3. The defendants (appellants herein) filed a written statement admitting the award of the contract work of "Improvements to Thirupurathoor-Pulluvila Road between Ch. 2/600 to Ch. 5/600" to the plaintiff vide Agreement No. 78/SESC/2002-03 dated 14.12.2002 and also the fact that, the first and part bill (CC 1st) amounting to a gross amount of Rs. 5,92,194/- was received in the office of the Executive Engineer on 5.3.2003 and CC 2nd and final bill for a gross amount of Rs. 19,09,733/- was received in that office on 27.9.2003. Though the Department is liable to make payment as per agreement conditions as and when work bills are received, payment of the work bills can be effected only based on strict seniority and availability of funds and letter of credit and that the plaintiff was fully aware of this fact when he entered into the agreement for the execution of work. According to the defendants, there was no willful delay in entertaining the request made by the plaintiff as payment can be released only by observing strict seniority, in accordance with the orders of





















Click Here to Read the rest of this document

1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top