1980 Supreme(Ker) 331

High Court of Kerala
P.S. Poti, P.J. Amma, JJ.
Food Corpn Of India - Appellant
Versus
Yousuff Co - Respondent
A.S. No. 31 of 1976
Decided On : 17-11-1980

Important Points

The main legal point established is that in contracts involving independent work under the same contract, each non-performance gives rise to a separate cause of action with a 3-year limitation period.

Subject

Contract Law - Breach of Contract

Act Referred

LIMITATION ACT : Art.55

Headnote

Breach of Contract - Food Corporation of India - Clause IX(i) of the annexure to the tender form - S.39 of the Contract Act - Severable performance - Cause of action for each breach - Limitation Act, 1963 - Art.55 - Independent work under the same contract - Suit dismissed

Fact of the Case:

The Food Corporation of India filed a suit against a contractor for damages due to breach of contract. The defendant had refused to perform the work for an extended period as per the contract. The defendant argued that the suit was barred by limitation.

Finding of the Court:

The court found that the suit was barred by limitation as there were no breaches within the 3-year limitation period prior to the date of the suit. The suit was dismissed on this ground.

Issues: The main issue was whether the suit was barred by limitation due to the absence of breaches within the 3-year limitation period.

Ratio Decidendi: The court held that in a contract where parties envisage that one party is obliged to perform work from time to time, each non-performance gives rise to a separate cause of action. The period of limitation for each breach is 3 years from the date of such breach.

Final Decision: The court dismissed the suit as there were no breaches within the 3-year limitation period prior to the date of the suit.

JUDGMENT

P. Subramonian Poti, J.

1. The judgment of the Court was delivered by Subramonian Poti J.- The Food Corporation of India, the plaintiff in the suit, has filed this appeal against the decision of the Additional Sub Judge of Tellicherry dismissing the suit. In response to the invitation for tenders issued by the Regional Manager of the plaintiff Corporation the defendant submitted a tender quoting 70 per cent above the schedule rates. The tender was accepted by the plaintiff and the contract was concluded. The plaintiff, the Food Corporation of India, is engaged in the work of undertaking the wholesale purchase of foodgrains and distribution of the same by sale at various places in India. The invitation by tender by the Regional Manager was for appointment of contractors for loading / unloading and transport of foodgrains etc. in and around Muzhappilangad and Cannanore for a period of two years from 11th September 1968 or such later date as may be decided. The period of two years was to commence on 11th October 1968 and that would expire on 10th October 1970. There was an option reserved in the plaintiff corporation under Clause.9(1) of the agreement to extend the period of contract by one more year and if such option was exercised by the plaintiff the defendant would be liable to carry out the work tendered for such extended period under the terms and conditions of the agreement. Evidently circumstances had changed by about the period of expiry of two years contemplated under the contract and in view of escalation in prices and rates a fresh tender was felt to he disadvantageous to the plaintiff corporation. By Ext. A3 letter, dated 31st July 1970 the Corporation exercised option to extend the term by one year by intimation to the defendant its intention to extend such term. Despite the attitude of the defendant who indicated that he was not willing to agree to it the Corporation by its letter, dated 29th September 1970 Ext. A5 insisted upon performance by the defendant of his obligation under the terms of the contract to work for one more year. In the meanwhile arrangements were simultaneously made by the Corporation ad hoc to see that the business of loading / unloading and transport did not come to a stand still if, on the expiry of the period of two years, the defendant did not choose to work further. But it was made expressly plain that this was being done because such arrangement was necessary. In other words the very issue of Exts. A3 and A5 by the plain tiff indicated that despite the ad hoc arrangements the plaintiff corporation was exercising its option to insist upon the performance by the defendant of its obligation to undertake the work for one more year. One Khalid Hajee was appointed to carry on the work evidently with a view to avoid the breakdown of the work of transport and supply of food articles. But the plaintiff had to pay higher rate to such contractor and that was so for the period from 11th October 1970 to 10th October 1971. The total amount that had to be paid to the new contractor was Rs. 5,58,852.91 in place of Rs. 4,22,244.39 which alone need have been paid to the defendant had he performed the same work under the terms of the contract. The excess amount thus paid Rs. 1,36,608.52 is claimed in the suit by the Corporation against the defendant as damages.

2. In this context we may mention that prior to the institution of this suit the contractor had filed a suit O.S. 82 of 1970 for declaration that the clause in the agreement entered into between the contractor and the Food Corporation concerning the option to extend for one more year was null and void and unenforceable and also seeking an injunction restraining the operation of certain clauses thereof. That suit O.S. 82 of 1970 was tried and dismissed and that decision has become final.

3. The present suit O.S. 136 of 1974 was resisted by the defendant on several grounds. He of course raised the plea of unenforceability of the clause of the