2013 Supreme(Ker) 1104

IN THE HIGH COURT OF KERALA
P.N. Ravindran, J.
Valsamma Thomas - Appellant
Vs.
Abdul Rahiman - Respondent
O.P.(C) No.3442 of 2013
Decided On : 21-10-2013

Subject

Civil Law - Attachment Before Judgment

Act Referred

CIVIL PROCEDURE CODE : O.21 R.32(5), O.38 R.5
SPECIFIC RELIEF ACT : S.39

Headnote

Specific Relief Act, 1963 - Section 39 - Code of Civil Procedure, 1908 - Order XXI Rule 32(5) and Order XXXVIII Rule 5 - Claim - Defendant has not denied the averment in paragraph 7 of the affidavit filed in support of the application for attachment - He is making hasty preparations to alienate his tangible assets - To obstruct and delay the execution of the decree that may be passed in the suit - Held, Notwithstanding the fact that the expenses incurred on that account can be recovered under Order XXI R.32(5) of the Code of Civil Procedure is in my opinion plainly untenable and cannot be sustained - Dismissed.

Advocates Appeared:
For the Appellant :K. Jayakumar (Sr. Advocate), John Joseph Vettikad, Joseph Abraham (Kottayam) & C. Joseph Johny.
For the Respondent: Biju Abraham.

JUDGMENT :

The petitioners are the plaintiffs in O.S.No.147 of 2013 on the file of the Court of the Subordinate Judge of Ottappalam. The respondent is the sole defendant therein. The petitioners have in O.S.No.147 of 2013 prayed for the following reliefs:-

"A. Direct the defendant by an order of Mandatory Injunction to give adequate and sufficient lateral support to the Plaint schedule item no.1 & 2 properties on its north and from where earth has been excavated and removed by the Defendant, by constructing necessary concrete retainer wall as may be indicated by a qualified competent engineer deputed by this Hon'ble Court, and also to restore the original condition of the Plaint schedule property and in case the Defendant fails to do so allow the Plaintiffs to do the said work under the supervision of this Hon'ble Court and to realize the cost thereof from the Defendant and his assets.

B. Restrain the Defendant or anybody under him from further digging or excavating the earth from the subjacent and adjacent land that lies to the north of the Plaint schedule property and belonging to the Defendant.

C. Allow the plaintiffs to realize damages of Rs.2,01,000/- as per the statement furnished below from the Defendant and his assets."

2. The petitioners have in the plaint averred that the defendant who owns properties lying to the north of the plaint schedule properties, has illegally excavated his land adjacent to the northern boundary of the plaint schedule property to a depth of about 15 meters and for a length of about 56 meters, that as a result thereof the north eastern portion of plaint schedule item No.1 has subsided for a length of about 6 meters and a width of about 3 meters. They have also averred that the soil thus removed was illegally appropriated and removed by the defendant to obtain unlawful gain. The plaintiffs have in the plaint estimated the damage caused on account of the illegal and negligent conduct of the defendant in digging and excavating the earth at Rs.2,00,000/- and have paid the court fee for that relief in terms of section 22 of the Kerala Court Fees and Suits Valuation Act, 1959. They have also averred that the defendant who has removed the natural support that was being rendered by the sub-adjacent and adjacent soil which is very much essential and necessary for the safe and convenient enjoyment of the plaint schedule properties is liable to give adequate lateral support to the plaint schedule properties and that he is also liable to be restrained by a permanent prohibitory injunction from further excavating his land lying adjacent to the plaint schedule property.

3. Along with the plaint, the petitioners filed I.A.No.972 of 2013 under Order XXXVIII rule 5 read with section 151 of the Code of Civil Procedure for a conditional order of attachment. Paragraphs 6, 7, 8 and 9 of the affidavit filed in support of the said application are extracted below for easy reference:-

"6. Due to the illegal, negligent, unthoughtful and unscrupulous conduct of the Defendant, the north eastern portion of Plaint schedule item no.1 property got subsided to a length of about 6 mt. and to a width of about 3 mt. and to a depth of about 6 mts. Even that soil was illegally appropriated and removed by the Defendant to obtain unlawful gain. Because of the illegal conduct the surface of the Plaint schedule properties became unstable and unsafe and we are not in a position to use or enjoy the said land and this position is continuing. The damage caused due to the illegal and negligent conduct of the Defendant in digging and excavating the earth is estimated at Rs.2 lakhs. Apart from that the cost for restoring the lateral support of the Plaint schedule properties may approximately come to more than Rs.15 lakhs.

7. The defendant on getting information about the legal proceedings that may be initiated against him is making hasty preparations to alienate his tangible assets with the intent to obstruct and delay the execution of the d


















1
2
3
4
5
6
7
8
9
10
11