IN THE HIGH COURT OF KERALA AT ERNAKULAM
T.R.RAVI, J.
S.SATHEESH, S/O. LATE K.N. SATHYAPALAN
Versus
THE STATE OF KERALA – Respondent
WP(C) NO. 9932 OF 2015
Decided on : 07-07-2021
SARFAESI Act – Sections 19, 22 – Failure to complete work – Compensation – Whether Smt.P.Shyamala is liable to pay any amount to respondents under "risk and cost" clause, for withdrawing from work undertaken by her, is pending consideration of a civil court – Whether partnership assets can be made liable for a debt allegedly owed by a partner – It is contended that nominee did not complete work in prescribed time owing to failure of respondents to supply materials for work as agreed in agreement – Respondents extended time for completion of work on several occasions but did not supply materials – Validity of original agreement expired on 13.07.2002 – Nominee requested 2nd respondent to foreclose contract and relieve her from obligation of continuing work and she refused to grant revised rates for completing work – Request has been produced as Exhibit P1 – Dispute regarding said work went up to Hon'ble Supreme Court in Civil Appeal Nos.1961–1962 of 2013, which was disposed of by Exhibit P2 judgment with an observation that nominee shall be free to file a civil action for damages/compensation – It is stated that nominee has filed O.S. thereafter, which is pending before Sub Court
Finding of the court:
Respondents and Smt.P.Syamala, respondents cannot contend that she had executed document with any intention to bind firm or in her capacity as a partner of firm – This is all more evident from reading of Ext.R4(a) which had preceded agreement – Even though in Ext.R4(a) legal heirs of Late Sathyapalan had expressed willingness of firm to carry out work, respondents chose to execute agreement with Smt.P.Syamala in her individual capacity – As such, neither Smt.P.Syamala nor respondents have intended agreement to bind firm – It follows therefore that no liability alleged to have been incurred as a result of Ext.P6 agreement can be fastened on petitioner – There can be no doubt that if a partner owes any money, creditor will be entitled to proceed against profits that may be earned by debtor, in his capacity as a partner of a firm or against debtors' interest in partnership firm – In case on hand, Smt.P.Syamala had retired from partnership as can be seen from Ext.P4 deed whereby partnership was reconstituted – There is nothing in pleadings of parties to show that retiring partner had any rights subsisting in partnership, on date of issuance of Ext.P3 letter by Assistant Executing Engineer, proposing to withhold amounts due to firm, towards risk and cost liability of Smt.P.Syamala – Ext.P3 proceeds on basis that Smt.P.Syamala is a partner of firm, which does not appear to be correct on basis of Ext.P4 deed – Since question whether Smt.P.Syamala has any "cost and risk" liability to respondents is admittedly pending consideration of competent civil court, it is not necessary in these proceedings to go into question as to modes of recovery that can be resorted to by respondents, if they are able to succeed in civil court.
Result : Writ Petition Allowed
JUDGMENT :
Pious obligation, a doctrine/principle of pristine Hindu law, which obliged a son to settle the debts incurred by his father, appears to be still haunting the Irrigation Department, in understanding the rights of the parties to a written contract. The petitioner, who is the Managing Partner of a partnership firm, which has executed certain works on the basis of agreements entered into with the respondents, are faced with a situation where the amounts due to them are being withheld for the reason that certain amounts are due from the mother of the Managing partner of the firm to the department, for having abandoned a work which was undertaken by her. One wonders whether the basic principles of the laws relating to partnerships and contracts will not apply when one of the contracting parties is the State.
2. Heard Sri S.Sreekumar, Senior Advocate, instructed by Sri P.Martin Jose, on behalf of the petitioner and Smt.Deepa Narayanan, Senior Government Pleader, on behalf of the respondents.
3. One Sri Sathyapalan had been undertaking civil works entrusted by the State, both in his individual capacity as well as through a partnership firm, which had been reconstituted on several instances from 1979. He had undertaken a work on 16.6.2000, which was designated as "IIP – Constructing Lower-level canal from CH.9000m to 9455m, including Construction of pressure siphon, flume and aqueduct". The work was entrusted to him in his personal capacity as can be seen from Ext.P8 letter dated 13.4.2000. Soon after the execution of the agreement relating to the work, he died on 7.7.2001, leaving behind his wife and two sons. In the agreement executed, Sri Sathyapalan had named his wife Smt.P.Syamala as his nominee, and it can be seen Ext.P8, which contains the nomination, that the nomination is for the purpose of receiving all or any sums due to her husband, under the terms of the agreement dated 16.6.2000. After the death of Sri Sathyapalan, his legal heirs wrote Ext.R4(a) letter to the Superintending Engineer on 10.7.2001, stating that they are the only legal heirs and they are willing to continue the work through a partnership firm, that they acknowledge the nomination of Smt.P.Syamala and further requesting that the nominee may be permitted to complete the balance work. The respondents thereafter executed Exhibit P6 supplementary agreement with the nominee on 03.08.2001, whereby it was agreed that the nominee shall execute the work as per the original schedule of the work, at the rate specified in that schedule and that the nominee shall not claim any enhanced rate of compensation, whatsoever. It can be seen from Exhibit P6 that the respondents in their wisdom thought it fit to entrust the work to the nominee in her personal capacity, without any reference to the partnership firm constituted by the legal heirs, even though at that point of time, Smt.P.Syamala was also a partner of the said firm.
4. It is contended that the nominee did not complete the work in the prescribed time owing to the failure of the respondents to supply materials for the work as agreed in the agreement. The respondents extended the time for completion of the work on several occasions but did not supply materials. The validity of the original agreement expired on 13.07.2002. The nominee requested the 2nd respondent to foreclose the contract and relieve her from the obligation of continuing the work and she refused to grant revised rates for completing the work. The request has been produced as Exhibit P1. The dispute regarding the said work went up to the Hon'ble Supreme Court in Civil Appeal Nos.1961–1962 of 2013, which was disposed of by Exhibit P2 judgment dated 26.2.2013, with an observation that the nominee shall be free to file a civil action for damages/compensation. It is stated that the nominee has filed O.S.No.48 of 2014 thereafter, which is pending before the Sub Court, Muvattupuzha. In short, whether Smt.P.Shyamala is liable to pay any amount to the re
Devji v. Magan Lal R. Atharana reported in (1964) 7 SCR 564 : AIR 1965 SC 139
M.Rajagopal v. K.S.Imam Ali reported in 1980 SCC OnLine Ker 251 : AIR 1981 Ker 36
SupremeToday
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.