2026 Supreme(Ker) 1211
IN THE HIGH COURT OF KERALA AT ERNAKULAM
SOUMEN SEN, C.J., SYAM KUMAR V.M., J.
M/S. Sree Saravana Engineering Bhavani Pvt. Ltd., Represented By Its Managing Director, Dr. P. Venkatachalam – Appellant
Versus
State Of Kerala, Represented By Its Secretary, Department Of Electricity, Government Secretariat – Respondent
WA No. 2108 of 2025
Decided On : 10-08-2026
Important Points
Subject
Commercial Law - Bank Guarantee
Headnote
(B) Bank Guarantee - The court will not ordinarily interfere with invocation or encashment once demand is made in compliance with the terms; the bank cannot go beyond compliance and determine justification. (Para 6)
(C) The exceptions are illustrative, not exhaustive; no absolute rule bars injunction in exceptional cases. (Para 5) Facts: The appellant, as lead member of a joint venture, was awarded a contract for electro-mechanical works of a hydroelectric project by a state electricity board. The project remained incomplete for nearly ten years. The board terminated the contract and invoked unconditional bank guarantees furnished by the appellant. The learned single judge refused to restrain encashment. In the appeal, it was noted that a dispute existed between the Indian and foreign partners of the joint venture, and the appellant sought one year to complete the contract, while the board claimed substantial public funds were blocked and termination and invocation were valid.
Findings of Court:
The court found no infirmity in the invocation, which was in terms of the guarantee. The appellant failed to establish any exception such as egregious fraud, irretrievable injustice, or special equities. The dispute between joint venture partners and delay in performance did not justify judicial restraint. Leave was granted to pursue remedies for recovery of amounts covered by the guarantee and for works already completed.
Issues: (1) Whether an unconditional bank guarantee can be injuncted from encashment in the absence of fraud, irretrievable injustice or special equities; (2) whether disputes between joint venture partners and project delay constitute such exceptional circumstances.
Ratio Decidendi: An unconditional and irrevocable bank guarantee is akin to cash and must be honoured on demand; underlying contractual disputes are immaterial. Injunction is permissible only in narrow categories of egregious fraud, irretrievable injury/irreparable damage, special equities, or non-compliant invocation. Since none existed, the invocation was valid and the writ appeal failed.
Result: Writ appeal dismissed; no order as to costs; liberty granted to pursue legal remedies regarding amounts covered by the bank guarantee and retention for completed works.
For the Appellant : Shri. Deepu Thankan
For the Respondents: Sri. C. Joseph Antony, Shri. Raju Joseph (SR.), Shri. Joseph Jose
JUDGMENT :
SOUMEN SEN, C.J.
Heard Mr. Deepu Thankan, learned counsel for the appellant, Sr. Adv. Raju Joseph instructed by Mr. C. Joseph Antony, learned counsel for respondent Nos. 2 to 6 and Ms.O.A. Nuriya, learned Senior Government Pleader.
2. We have considered the minutes of the meeting dated 1st August, 2026 and also the letter dated 1st August, 2026, from which it appears that there is a dispute between the Indian partner and the Chinese partner with regard to the implementation of the contract awarded by the Kerala State Electricity Board Limited (KSEB). Hence, it is not possible for the Indian partner alone to execute the work. The Indian partner has sought a period of one year to fulfill the obligations under the said agreement. The KSEB, however, is of the view that, despite repeated opportunities extended to the appellant, including facilitative measures, the project has remained incomplete even after a period of ten years, owing to the alleged failure to fulfill the contractual obligations, thereby causing substantial financial loss to the KSEB. It is further stated that approximately Rs.169 Crores of public funds invested in the project remain dead without serving the intended purpose, apart from the continuing loss of generation on account of the delay in commissioning the project. On that basis, the KSEB has reiterated the decision to proceed with termination of the contract for the Electro- Mechanical Works of the Bhoothathankettu SHEP at the risk and cost of the Consortium, in accordance with the contractual provisions and the termination proceedings already issued. The KSEB has already rejected the request for release of the Civil and Electro-Mechanical Bank Guarantees, as the conditions governing their release have not been fulfilled and the KSEB is entitled to retain the same in accordance with the Agreement and the Conditions of the Contract.
3. In the present proceedings, we are concerned only with the Bank Guarantee, which is unconditional in nature. A bank guarantee, unconditional in nature, does not admit of any requirement to be fulfilled except a simple demand for the money covered under the guarantee. We are, therefore, examining whether any ground exists for interfering with the exercise of power by the KSEB in invoking an unconditional Bank Guarantee. It appears that the project has remained pending for almost ten years.
4. Lord Denning once has said that bank guarantee is as good as cash. It is life blood of commerce. The law relating to invocation of bank guarantee is now well-settled. When in the course of commercial dealings and unconditional bank guarantee is given the beneficiary is entitled to realize the amounts covered under the bank guarantee in terms thereof irrespective of any pending dispute. The bank giving such guarantee is bound to honour it as per its terms irrespective of any dispute raised by its customer. The very purpose of giving such a bank guarantee would otherwise be defeated. The only two exceptions when the bank may refuse encashment of the said bank guarantee are fraud and irretrievable injury. The fraud must be of an egregious nature such has to vitiate the entire underlying transactions. The exceptional circumstances would include a case where it is proved to the satisfaction of the court that the bank knows that any demand for payment already made or which thereafter be made would be clearly fraudulent. However, in such an event, the evidence must be clear both as to the fact of fraud and as to the bank's knowledge. (See Adani Agri Fresh Limited v. Mahaboob Sharif ) reported at (2016) 14 SCC 517). The third exception which is of recent origin is special circumstances or special equity which may at times overlap with the irretrievable harm or injustice on which encashment may be refused. The limited categories on which the Court may refuse encashment of a bank guarantee or a performance guarantee are summarized below:-
(i) If there is a fraud in connection with the bank gua