Goa High Court
TITO MENEZES
Manohar Hiru Naik Parulekar - Appellant
Versus
Agrawal Minerals (Goa) - Respondent
Decided On : 02/18/1972
CRIMINAL PROCEDURE CODE, 1973 - SECTION 145 - POSSESSION OF MINE - DISPUTE BETWEEN OWNER AND CONTRACTOR - JURISDICTION OF MAGISTRATE - ORDER UNDER SECTION 145(6) - VALIDITY.
Fact of the Case:
A dispute arose between the petitioner, the owner of a mine, and the respondent, a contractor engaged by the petitioner to extract ore from the mine, regarding the possession of the mine. The petitioner claimed that the respondent was merely a worker and could be dismissed by him, while the respondent claimed that he was in possession of the mine for the purpose of extracting ore under the terms of the contract.
Finding of the Court:
The court found that the evidence on record showed that the respondent was in possession of the mine at the time of the dispute, but that the petitioner also had control and possession of the mine. The court held that the mine was not in the exclusive possession of either party, as required by Section 145(6) of the Criminal Procedure Code, and that the Magistrate therefore acted without jurisdiction in passing an order under that provision.
Issues: 1. Whether the Magistrate had jurisdiction to pass an order under Section 145(6) of the Criminal Procedure Code in a dispute regarding the possession of a mine between the owner and a contractor engaged to extract ore from the mine. 2. Whether the petitioner had the right to stop the respondent from working in the mine.
Ratio Decidendi: The court held that the Magistrate did not have jurisdiction to pass an order under Section 145(6) because the mine was not in the exclusive possession of either party. The court also held that the petitioner did not have the right to stop the respondent from working in the mine because there was a regular contract between the parties for the extraction of ore and the petitioner had placed the respondent in joint possession of the mine for that purpose.
Final Decision: The court allowed the revision application and set aside the order of the Magistrate.
2. The case of the petitioner is that by the said agreement, he engaged the respondent No.1 as an ore raising contractor to extract iron ore from the mine in question; that he had his own manager, two clerks and a watchman to look after the working of the mine; that the mine was in his possession and the respondent No.1 was in the mine only as his worker; and that he was entitled to dismiss the respondent No. 1 from his service and stop his entry into the mine.
3. The case of the respondent No.1, who was the only respondent who contested the petition, is that under the agreement of 29-10-1969, he was put in possession of the mine for the purpose of extracting ore for the period of 3 years ending on 30-10-1972; and that therefore the petitioner could not oust him from that possession unless by due process of law.
4. It is evident from the case of the two parties that both of them claim to be in exclusive possession of the mine.
5. Three points were raised by Shri Dias in the course of his arguments, namely:-
(i) that the dispute was not regarding land, but regarding contract
(ii) that the petitioner and not the respondent was in exclusive possession of the mine; and
(iii) that assuming for argument's sake that the petitioner was not in exclusive possession, the possession of the mine was jointly held by the petitioner and the respondent No.1.
6. The first point need not detain me for long. The jurisdiction of the Magistrate to issue an order under sub-section (1) and sub-section (4) was challenged before the Sessions Court and this Court. It was decided that the Magistrate did have jurisdiction to entertain the matter. Such decision was not possible unless the dispute was in regard to land and not regarding a contract.
7. Regarding the second point, namely, that the petitioner had the exclusive possession of the mine, I find that the evidence on record is sufficient to prove that it was not so. The contract itself affords evidence to show that the possession of the mine was given to the respondent No.1 for the period from 1-11-1969 to 30-10-1972, for the purpose of extracting ore. Clause 5 of the agreement dated 29-10-1969 indicates that the contract could not unilaterally be revoked for the period of 3 years. Under clause 11 the contractor was authorised by the mine owner to use the hutments existing in the mine and also to construct more, at his own cost, in case further accommodation was required for the labourers. There is on record a telegram dated 2-11-1970 sent by the petitioner wherein the petitioner states that the respondent No.1 is not properly working "your (of the respondent No.1) part of the mine" and requesting the respondent No.1 to remove his men and machinery f
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.