2006 Supreme(Raj) 1883
High Court Of Rajasthan
Judgename : Shiv Kumar Sharma
In the Matter of TCI Infrastructure Finance Ltd. - Appellant
Versus
. - Respondent
S.B. Stay Application No. 612 of 2006 in S.B. Company Application No. 20 of 2006
Decided On : 07/07/2006
Act Referred
COMPANIES COURT RULES : R.71
Headnote
Stay of Proceedings - Companies Act - The court granted a stay of proceedings against the company pending the final disposal of the application filed under Section 391 of the Companies Act, based on the wide import of the term 'proceeding' in Section 391(6) and the prima facie case in favor of the applicant company.
Fact of the Case:
The applicant company sought a stay of continuation of proceedings pending in Debt Recovery Tribunal and various Courts of Metropolitan Magistrate New Delhi, under Section 391(6) of the Companies Act, due to financial difficulties and the hope of receiving approval for a proposed compromise/arrangement.
Finding of the Court:
The court found a prima facie case in favor of the applicant company and granted a stay of the proceedings pending in Debt Recovery Tribunal and the Courts of Metropolitan Magistrate New Delhi, until the final disposal of the application filed under Section 391 of the Companies Act. Notice was issued to HUDCO for seeking modification/vacation of the stay order.
Issues: The main issue was whether the court should grant a stay of proceedings against the company pending the final disposal of the application filed under Section 391 of the Companies Act.
Ratio Decidendi: The court's decision was based on the wide import of the term 'proceeding' in Section 391(6) of the Companies Act, which includes criminal proceedings, and the prima facie case in favor of the applicant company.
Final Decision: The application for a stay of proceedings was allowed, and the continuation of the cases pending in Debt Recovery Tribunal and the Courts of Metropolitan Magistrate New Delhi was stayed until the final disposal of the application filed under Section 391 of the Companies Act.
Mr. Paras Kuhad and Mr. Sandeep Taneja, for the Applicants.
Shiv Kumar Sharma, J.-The present applicant company has taken out this Judge’s summons under Rule 71 of the Companies (Court) Rules, 1959 praying for an order under Sub-section (6) of Section 391 of the Companies Act, for stay of continuation of proceedings pending in Debt Recovery Tribunal and various Courts of Metropolitan Magistrate New Delhi.
2. Mr. K.D. Garg, the Executive Director of the applicant company in the additional affidavit stated that HUDCO a secured creditor of the applicant company has initiated following proceedings against the applicant company :-
(a) OriginalApplication No. 64 of 2004 pending before Debt Recovery Tribunal (1) Delhi, titled as
HUDCO vs. TCI Finance Infrastructures Ltd. & Ors.
(b) Complaint under Section 138 of Negotiable Instruments Act pending before Ms. Geetanjali Goyal, Metropolitan Magistrate, Patiala House Court New Delhi (CC No. 1028/203, R.No. 30).
(c) Complaint under Section 138 of Negotiable Instruments Act pending before Sh. Gauttam Manan, Metropolitan Magistrate, Patiala House Court New Delhi (CC No. 1917/1, R.No. 5).
(d) Complaint under Section 138 of Negotiable Instruments Act pending before Sh. Pritam Singh, Metropolitan Magistrate, Patiala House Court New Delhi (CC No. 1925/1/04, R.No. 14).
3. It is canvassed that the applicant company has already filed application under Section 391(1) of the Companies Act, 1956 seeking direction for convening the meeting of the secured creditors for considering and approving the proposed scheme of compromise arrangement with or without modification. This Court vide order dated 26.05.2006 appointed Sh. Sudhir Kumar Tewari as Chairman of the meeting of the secured creditors to be held on 05.07.2006.
4. Now the Chairman of the Meeting Shri Sudhir Kumar Tewari has submitted the report to the effect that on 05.07.2006, the date on which the meeting was to be held, he received a call from Mr. Satish Chandra, Dy. General Manager, Stressed Assets Stabilisation Fund (IDBI) that due to cancellation of flight from Delhi to Jaipur he would not be able to reach by 10.00 AM, the time scheduled for the meeting. He requested that since he was reaching Jaipur by road, therefore, the meeting may be adjourned till 1.00 PM. Since there were only three secured creditors of the applicant company, therefore, upon receipt of the information of Dy. General Manager, the Chairman thought it proper to inform the representatives of other two creditors namely, HUDCO and Bhoruka Investment Ltd. about the request of Stressed Assets Stabilisation Fund (IDBI) for deferment of the meeting till 1.00 PM. The representatives of the other two creditors also agreed for the same and accordingly the meeting was postponed till 1.00 PM. Thereafter the representative of HUDCO Mr. R.L. Batta met the Chairman at 11.30 AM in the High Court premises and handed over a written communication for rescheduling the date of meeting. The representatives of other creditors namely Stressed Assets Stabilisation Fund (IDBI) and Bhoruka Investment Ltd. agreed by written consent for rescheduling the meeting to be held on 17.07.2006 at 12.30 PM.
5. The grievance expressed by the applicant company is that for quite some time the company was in financial difficulties and, therefore, it could not repay its debts. Because of non payment of the liabilities in time, one of the creditors of the company namely HUDCO has initiated legal proceedings by filing recovery application before the competent Courts. The applicant company is hopeful that the proposed scheme of compromise/arrangement shall be approved by the requisite number of secured creditors and the same shall be sanctioned by the Court. If the compromise arrived at between the company and secured creditors and sanctioned by the Court the applicant company shall be able to receive its operation. However, if the creditors are allowed to initiate recovery proceedings against the applicant company the entire endeavour to receive the company and to