SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

1992 Supreme(Raj) 841

RAJASTHAN HIGH COURT AT JAIPUR BENCH
G.S.Singhvi, J.
Mangalam Cement Ltd. - Appellant
Versus
The Goods Superviser, Western Railway, Kota and Others - Respondent
S.B. Civil Revision Petition No. 672 of 1992 (Against the order dated, 18.7.1992, passed by the Addl. District Judge No. 3, Kota, camp Ramganjmandi, in Civil Appeal No. 42 of 1992).
Decided On : 25-08-1992

The General Manager of a zonal railway is authorised to act on behalf of the railway administration.

Headnote:

RAILWAYS ACT - SECTION 3(6) - INDIAN RAILWAYS ACT, 1890 - GENERAL MANAGER OF A ZONAL RAILWAY IS AUTHORISED TO ACT ON BEHALF OF THE RAILWAY ADMINISTRATION.

Fact of the Case:

The petitioner, a public limited company, had a cement factory at Aditya Nagar, Morak, Tehsil Ramganj Mandi, district Kota, where cement was manufactured. The petitioner entered into an agreement with the Railway Administration on 2.3.81 regarding the terms and conditions of use and working of railway siding. The agreement provided for free time and demurrage charges. In 1982, the Railway Administration introduced the schema of loading full Jumbo rake which consisted of 100 wagons and a total loading capacity of 22 M.T. The petitioner found the system to be highly unworkable and arbitrary and made a representation to the Railway Administration. On the basis of the representation, the Railway Board directed the petitioner to approach the General Manager, Western Railway. It was thereafter agreed that joint trial be conducted to verify and determine the actual time required for loading the Jumbo Rake. The Joint Trial Team came to the conclusion that 411/2 hours was the minimum time required for loading Jumbo rake at the site. The General Manager accepted these recommendations and the authorities of the Western Railway acted upon those recommendations till 1986. In 1986, the Goods Supervisor, Western Railway, orally informed the petitioner that the existing facilities of providing 411 hours as free loading time stands withdrawn and henceforth the company will be liable to pay demurrage in case of its failure to load the Jumbo rake within 13 hours. The petitioner filed a suit for permanent injunction against the non-petitioners in the court of Munsiff and Judicial Magistrate, First Class, Ramganj Mandi and claimed that the action of the non-petitioners was highly arbitrary, unreasonable and discriminatory as also contrary to clause 17 (c) of the agreement. The trial court granted an ad interim injunction, which was confirmed by the trial court on 20.3.87 after hearing the parties. The non-petitioners filed appeal before the District Judge, Kota, who remanded the matter to the trial court for fresh decision after proper service on the Divisional Railway Manager. The trial court again heard the parties and passed the order of injunction dated, 25.9.90. The non-petitioners appealed before the Additional District Judge No.3 and the learned Additional District Judge has passed the order dated, 18.7.92. He has set aside the order of the trial court and dismissed the application of injunction filed by the petitioner.

Finding of the Court:

The court held that the General Manager of a zonal railway is authorised to act on behalf of the railway administration. The court also held that the petitioner was not entitled to the facility of 411/2 hours free time as the Railway Board had not approved the recommendations of the Joint Trial Team and the General Manager, Western Railway. The court further held that the petitioner was not entitled to specific performance of the contract for 411/2 hours free time as there was no concluded contract between the parties.

Issues: 1. Whether the General Manager of a zonal railway is authorised to act on behalf of the railway administration? 2. Whether the petitioner was entitled to the facility of 411/2 hours free time? 3. Whether the petitioner was entitled to specific performance of the contract for 411/2 hours free time?

Ratio Decidendi: 1. The court held that the General Manager of a zonal railway is authorised to act on behalf of the railway administration, relying on the definition of Railway Administration used in Section-3 (6) of the Indian Railways Act, which states that the General Manager will be deemed to be the Railway Administration. 2. The court held that the petitioner was not entitled to the facility of 411/2 hours free time as the Railway Board had not approved the recommendations of the Joint Trial Team and the General Manager, Western Railway. The court noted that the General Manager had recorded a note on 20/30.3.83, in which he stated that the decision to allow 411/2 hours free time was subject to the approval of the Railway Board. The court also noted that the Railway Board had issued a letter dated 12-12-83, which contained a specific guideline regarding free time for loadings and un-loading of Jumbo Rakes. The decision of the Railway Board became effective from 1-1-84. Therefore, the General Manager, western Railway, Had no authority to allow free time facility of 411/2 hours to the petitioner after 1-1-84. 3. The court held that the petitioner was not entitled to specific performance of the contract for 411/2 hours free time as there was no concluded contract between the parties. The court noted that the petitioner had not produced any document before the Court showing that the Railway Board had approved the recommendations made by the Joint Trial Team and the General Manager, Western Railway.

Final Decision: The court dismissed the revision petition filed by the petitioner.

JUDGMENT

1. - This revision petition is directed against the order dated, 18.7.92, passed by the Additional District Judge No. 3. Kota, Camp Ramganj Mandi, whereby he has allowed the appeal filed by the defendants-non-petitioners and set aside the order of injunction passed in favour of the plaintiff-petitioner on 29.5.90 but the Munsif and Judicial Magistrate, First Class, Ramganj Mandi.

2. For the purpose of decision of this revision petition, it is necessary to refer to some facts.

3. The plaintiff-petitioner is a Public Limited Company. It is having a factory at Aditya Nagar, Morak, Tehsil Ramganj Mandi. district Kota, where the cement is manufactured. The construction of the Cement Factory started in 1978. According to the petitioner, the Railway Administration approved the cement loading complex plan and exchange yard for the purpose of loading and unloading the cement. The Compay spent a sum of Rs. 3 50 crores for the purpose of constructing the above complex and exchange yard. An agreement was entered into between the petitioner company and the Railway Admin station in the name of President of India on 2.3.81 regarding the terms and conditions of use and working of railway siding. This was done in term, of the Indian Railway Commercial Mannual As per Clause 17(c) of the agreement, free time and demurrage charges were calculated in accordance with the pilot to pilot schedule Daily loading quota of 35 wagons was fixed for loading cement. These 35 wagons were to be loaded within 8 hours and in case of failure, demurrage charges were payable. Each of these wagons was of 22 tonnes capacity. This total loading capacity of the wagons allotted to the petitioner came to be 770 M T. of cement. In the year 1982, Railway Administration introduced the schema of loading full Jumbo rake which consisted of 100 wagons and a total loading capacity of 22 M.T. The company was required to undertake the loading within 131/2 hours including shunting hours. Since the company found the system to be highly unworkable and arbitrary, it made a representation to the Railway Administration. On the basis of the representation of the Company the Railway Board vide its letter dated, 17.5.82 directed the Company to approach the General Manager, Western Railway. It was thereafter, agreed that joint trial be conducted to verify and determine the actual time required for loading the Jumbo Rake. Such joint trials were conducted between 23rd to 25th October, 1982. According to the plaintiff-petitioner, the Joint Trial Team came to the conclusion that 411/2 hours was the minimum time required for loading Jumbo rake at the site. The Joint Trial Team therefore, made recommendation to the General Manager, Western Railway, Bombay. The claim of the plaintiff is that the General Manager accepted these recommendations and the authorities of the Western Railway acted upon those recommendations till 1986. In the result, the petitioner was allowed free loading time 41-112 hours for one Jumbo rake with a provision of Rs. 3,000/- as penalty as and when 411/2 hours time schedule was exceeded. The petitioner company made a representation dated, 29.3.84 against the penalty of Rs. 3,000/- per rake. In response to this, the railway authorities at Bombay vide their letter dated, 14.11.84 expressed their inability to waive the penalty of Raj. 3,000/-.

4. Some times in the year 1986, the Goods Supervisor, Western Railway, orally informed the petitioner that the existing facilities of providing 411/2 hours as free loading time stands withdrawn and henceforth the company will be liable to pay demurrage in case of its failure to load the Jumbo rake within 13 hours. The petitioner then filed a suit for permanent injunction against the non-petitioners in the court of Munsiff and Judicial Magistrate, First Class, Ramganj Mandi and claimed that the action of the non-petitioners was highly arbitrary, unreasonable and discriminatory as also contrary to clause 17 (c) of the agreement. By an


























Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top