2020 Supreme(Raj) 58
IN THE HIGH COURT OF RAJASTHAN AT JODHPUR
Sangeet Lodha, Arun Bhansali, JJ.
State of Rajasthan and Ors. – Appellants
Versus
Hari Om Builders and Ors. – Respondents
D.B. Civil Misc. Appeal Nos. 151 and 165 of 2020
Decided On : 24-01-2020
Subject
Contract Law - Interest on Delayed Payments
Act Referred
Headnote
Civil Procedure Code, 1908 - Section 34 - Order VII - Rule 2A - Civil Suit - Suit for Recovery of amount - Where interest is sought in suit - Respondents-plaintiffs, inter alia, for recovery of amount respectively towards the work undertaken by them for constructions of class rooms - It was indicated that as per work order, which was issued pursuant to tender process, time fixed for completion of work was requisite work was completed and physical possession was handed over alongwith final bill - Held, Amount claimed by plaintiffs in the suits has been paid, interest under Section 34 CPC could not be awarded - Said plea raised also has no substance as has been laid down by the Division Bench of this Court in State Bank of Bikaner & Jaipur & Ors. v. Abdul Wahid & Ors. 2003 (1) WLN 69, wherein, it was laid down that even if entire suit amount including the interest, for which, the suits are filed is paid during pendency of suit, interest for period suit remains pending could be awarded and plea raised in this regard also has no substance, inasmuch as, plaintiffs besides claiming outstanding amount have also sought decrees for interest and admittedly the amount of interest as claimed in plaints was not paid by the appellants - Appeals dismissed.
Advocate Appeared:
For the Appellants : Anil Bachhawat, Govt. Counsel
JUDGMENT :
Arun Bhansali, J.
1. These appeals have been filed by the appellants aggrieved against judgments & decrees dated 26.08.2019 passed by Commercial Court, Jodhpur, whereby, the Commercial Court has directed the appellants-defendants to pay interest @ 6% per annum from 01.04.2015 till the outstanding amount was paid by the appellants-defendants to the plaintiffs.
2. The suits were filed by the respondents-plaintiffs, inter alia, for recovery of a sum of Rs.42,23,075/- & Rs.49,40,935/-, respectively towards the work undertaken by them for constructions of class rooms. It was, inter alia, indicated that as per the work order, which was issued pursuant to the tender process, the time fixed for completion of the work was 31.03.2015, the requisite work was completed by 30.03.2015 and the physical possession was handed over alongwith final bill.
3. An amount of Rs.33.65 lakh and Rs.39.37 lakh remained outstanding, for which, the plaintiff-firms repeatedly contacted the appellants, however, the payment was not made and, therefore, the suits were filed in the year 2018 seeking payment of the outstanding sum alongwith interest @ 18% per annum.
4. Written statements were filed, inter alia, admitting the averments made in the plaints pertaining to the grant of contracts and that the work was completed on 30.03.2015. It was claimed that as sufficient budget was not allotted, the amount could not be paid to the plaintiffs and that a sum of Rs.33,64,896/- & Rs.39,37,245/-, respectively was outstanding, the department was trying to make payment and on budget being allotted the amount would be paid. It was denied that the plaintiffs were entitled to interest @ 18%.
5. Based on the pleadings of the parties, the Commercial Court framed five issues. On behalf of the plaintiffs one witness each was examined, however, on behalf of the defendants no evidence was produced.
6. The Commercial Court in the judgment impugned noticed that the outstanding sum of Rs.29,35,594/- and Rs.33,58,577/- was paid to the plaintiffs during pendency of the suits (learned counsel for the appellants submits that the payment was made on 25.01.2018).
7. Based on the above fact of payment, which was admitted by PW-1 in his statements, the issues pertaining to the amount being outstanding were not pressed.
8. While dealing with the issue pertaining to interest, the Commercial Court came to the conclusion that as in the written statements the plea taken is that the amount could not be paid on account of non-grant of budget, there apparently was no mistake on part of the plaintiffs and, therefore, in the interest of justice and in the circumstances of the case, awarded interest @ 6% per annum w.e.f. 01.04.2015 at simple rate and passed decrees in this regard.
9. It is submitted by learned counsel for the appellants that the Commercial Court was not justified in decreeing the suits. Submissions were made that the plaintiffs were required to comply with the requirements of Order VI, Rule 3A and Order VII, Rule 2A CPC, which deal with pleadings in a case where interest is sought in a suit before the Commercial Courts and, therefore, the Commercial Court was not justified in awarding the interest.
10. Further submissions were made that in the contract between the parties there was no provisions for awarding interest on delayed payment and, as such, there was no occasion for the Commercial Court to have awarded interest to the respondents for the delayed payments.
11. Attempts were made to justify the delay on account of lack of budget and it was submitted that during pendency of the suits, the amount due has already been paid and, therefore, there was no occasion for the Commercial Court to have granted decrees for payment of interest.
12. We have considered the submissions made by learned counsel for the appellants and have perused the material available on record.
13. The facts are not in dispute, whereby, the plaintiffs were forced to file the suits for recovery of huge sum from the