IN THE HIGH COURT OF RAJASTHAN
Pushpendra Singh Bhati, J.
Lalit Soni S/o Radha Krishna Verma - Appellant
Versus
State Of Rajasthan - Respondent
Criminal Miscellaneous (Petition) No. 1000 of 2013, 1001 of 2013
Decided On : 14-12-2018
PREVENTION OF CORRUPTION ACT - COMMISSIONING CERTIFICATE - QUASHING OF FIR - [SECTION 13(1)(D), 13(2)] - The petitioners, State Officers, were not required to give a commissioning certificate, but were required to give certain information of commissioning of certain component in the Plant. The term 'commissioning' was not defined in the PPA, and thus, the said term was a subjective word, which was utilized by the authorities concerned, while issuing the aforesaid certificate certifying commissioning of the Project on 09.01.2012, which was of course not accepted by the Nodal Agency i.e. NTPC-NVVN. Thereafter, after assessment thereof, the same was implemented finally, while deriving the conclusion to the effect of ascertainment of the date of commissioning of the Power Plant as 28.01.2012. Such derivement of the final assessment was done, after taking into account the definitions issued and clarified by the Ministry of New and Renewable Energy, Government of India, and thus, the said date of commissioning of the Project could be ascertained only on 05.07.2012. The present FIR has been lodged on 26.12.2012, which was much subsequent to the action completed by all the parties, including invocation of the penalty Clause 4.6.1 of the PPA, as indicated hereinabove. The stand of the NTPC has further clarified the whole situation, as the NTPC-NVVN, which was directly the Nodal Agency under the National Solar Mission of the Government of India, and the contractual partner in the matter, has in fact categorically stated that the declaration of commissioning of Solar Power Project on different parameters was a mere irregularity and not an illegality, and the said irregularity has occurred in absence of clear guidelines and definition of the term 'commissioning'. Thus, the clinching effect of the stand so taken by the NTPC in the present case is that the impugned FIR itself, which allegedly was registered so as to constitute a criminal offence, goes away. Held - The present misc. petitions are allowed and the impugned FIR No.532 dated 26.12.2012 pending investigation at Police Station CPS ACB, Jaipur for the offences under Sections 13(1)(d) and 13(2) of the Prevention of Corruption Act, 1988 and Sections 420 and 120B of the Indian Penal Code, 1860 is hereby quashed.
Fact of the Case:
The petitioners, State Officers, were not required to give a commissioning certificate, but were required to give certain information of commissioning of certain component in the Plant. The term 'commissioning' was not defined in the PPA, and thus, the said term was a subjective word, which was utilized by the authorities concerned, while issuing the aforesaid certificate certifying commissioning of the Project on 09.01.2012, which was of course not accepted by the Nodal Agency i.e. NTPC-NVVN. Thereafter, after assessment thereof, the same was implemented finally, while deriving the conclusion to the effect of ascertainment of the date of commissioning of the Power Plant as 28.01.2012. Such derivement of the final assessment was done, after taking into account the definitions issued and clarified by the Ministry of New and Renewable Energy, Government of India, and thus, the said date of commissioning of the Project could be ascertained only on 05.07.2012. The present FIR has been lodged on 26.12.2012, which was much subsequent to the action completed by all the parties, including invocation of the penalty Clause 4.6.1 of the PPA, as indicated hereinabove. The stand of the NTPC has further clarified the whole situation, as the NTPC-NVVN, which was directly the Nodal Agency under the National Solar Mission of the Government of India, and the contractual partner in the matter, has in fact categorically stated that the declaration of commissioning of Solar Power Project on different parameters was a mere irregularity and not an illegality, and the said irregularity has occurred in absence of clear guidelines and definition of the term 'commissioning'. Thus, the clinching effect of the stand so taken by the NTPC in the present case is that the impugned FIR itself, which allegedly was registered so as to constitute a criminal offence, goes away.
Finding of the Court:
The present misc. petitions are allowed and the impugned FIR No.532 dated 26.12.2012 pending investigation at Police Station CPS ACB, Jaipur for the offences under Sections 13(1)(d) and 13(2) of the Prevention of Corruption Act, 1988 and Sections 420 and 120B of the Indian Penal Code, 1860 is hereby quashed.
Issues: None
Ratio Decidendi: The stand of the NTPC has further clarified the whole situation, as the NTPC-NVVN, which was directly the Nodal Agency under the National Solar Mission of the Government of India, and the contractual partner in the matter, has in fact categorically stated that the declaration of commissioning of Solar Power Project on different parameters was a mere irregularity and not an illegality, and the said irregularity has occurred in absence of clear guidelines and definition of the term 'commissioning'. Thus, the clinching effect of the stand so taken by the NTPC in the present case is that the impugned FIR itself, which allegedly was registered so as to constitute a criminal offence, goes away.
Final Decision: The present misc. petitions are allowed and the impugned FIR No.532 dated 26.12.2012 pending investigation at Police Station CPS ACB, Jaipur for the offences under Sections 13(1)(d) and 13(2) of the Prevention of Corruption Act, 1988 and Sections 420 and 120B of the Indian Penal Code, 1860 is hereby quashed.
JUDGMENT
Pushpendra Singh Bhati, J. - Since the issue involved in both the present misc. petitions is identical, therefore, with the consent of learned counsel for the parties, both the present petitions have been heard analogously and are being decided by this common judgment.
2. These criminal misc. petitions under Section 482 Cr.P.C. have been preferred claiming the following reliefs:
"(i) The FIR No.532/12 dated 26.12.2012 Police Station CPS, ACB, Jaipur and its further proceedings may kindly be quashed and set aside.
(ii) Any other appropriate order or direction which may be deemed just and proper in the facts and circumstances of the case may kindly be passed in favour of the petitioner."
3. The aforequoted prayer clause indicates that the present FIR bearing No.532/12 dated 26.12.2012 is pending investigation against the petitioners at Police Station CPS ACB, Jaipur for the offences under Sections 13(1)(D) and 13(2) of the Prevention of Corruption Act, 1988 read with Sections 420 and 120-B of the Indian Penal Code, 1860.
4. The said FIR No.532/12 dated 26.12.2012 has already been quashed by this Court vide judgment dated 13.12.2018 passed in Sanjay Varghese Vs. State of Rajasthan & Anr. (S.B. Criminal Misc(Pet.) No. 98/2013).
5. Mr.Mahesh Bora, learned Senior Counsel assisted by Mr.Nishant Bora representing the petitioners submits that the basic arguments and facts of the earlier case of Sanjay Varghese Vs. State of Rajasthan & Anr. (supra) remains the same, but he has certain additional submissions regarding the present petitioners, who are the State Officers.
6. Learned Senior Counsel for the petitioners has drawn the attention of this Court towards the circular dated 06.10.2008 issued by the Chairman & Managing Director, Jaipur Vidyut Vitran Nigam Limited, in which the role was attributed to the petitioners, and as per the said circular, a Committee was authorized to witness the commissioning of generator only, and not the overall commissioning of the Plant.
7. The relevant Clause 7 of the aforementioned circular dated 06.10.2008 reads as under:-
"7. Superintending Engineer (RPPC) will authorize a committee of the following officers for witnessing the commissioning of generator.
i) Xen/Aen (O&M) of the Discom where generating plaint is located.
ii) Xen/Aen (GSS) of RVPN of the area where generating plant is located.
iii) Xen/Aen (M&P) nominated by the SE (M&P) of the concerned Discom to whom the generator is allotted.
iv) The Representative of the Developer/Generator.
The above Committee shall visit the site and prepare the joint meter reading of the Energy meters installed at newly connected generator panel and the 33 KV side and on EHV sided meter installed at the concerned pooling/receiving 220 or 132 KV GSS and prepare the commissioning report giving all the details of the system."
8. Learned Senior Counsel for the petitioners has also drawn the attention of this Court towards the Office Order dated 06.01.2012 issued by the Office of the Superintending Engineer (RDPPC), Jodhpur Discom, 400 KV GSS Control Room, Heerapura, Jaipur, reflecting that the commissioning was again in respect of generator only and for a particular reading of the energy meters to be installed at the delivery point.
9. The relevant portion of the aforesaid office order dated 06.01.2012 reads as under:
"A committee of the following officers is hereby constituted to witness the commissioning of the above generator:
1. The X.En (M&P)/A.En (M&P), to be nominated by the SE (M&P) JDVVNL, Jodhpur.
2. The Executive Engineer / Assistant Engineer (132KV GSS), Pokran.
3. Representative of RREC.
4. Representative of DDE Renewables Pvt. Ltd. (Developer).
The above committee shall visit the site and prepare the joint meter reading of the Energy meters to be installed at the delivery point and prepare the commissioning report giving all the details of the system. The above committee shall also ensure that the main meters and back up meters and metering equi
Binod Kumar and Ors. vs. State of Bihar and Anr.
Parbatbhai Aahir Alias Parbatbhai Bhimsinhbhai Karmur and Ors. vs. State of Gujarat and Anr.
AI
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.