RAJASTHAN HIGH COURT BENCH AT JAIPUR
Mahendar Kumar Goyal, J.
Durgalal Meena & Ors. - Appellants
Versus
State of Rajasthan & Ors. - Respondents
S.B. Civil Writ Petition No. 11917 of 2021
Decided On : 22-07-2022
Housing - Writ Petition - Special Registration Scheme - Sections 6, 10, 18(A), 21, 22, 23 - The court interpreted the provisions of the Special Registration Scheme, emphasizing the binding nature of the terms agreed upon by the applicants, leading to the dismissal of the writ petition.
Fact of the Case:
The petitioners challenged the cancellation of their house allotments by the Rajasthan Housing Board due to non-payment of an additional demand, claiming they had already paid the required amounts and attributing delays to the Board's actions.
Finding of the Court:
The court found that the petitioners were aware of the terms of the Special Registration Scheme and were liable for the additional costs as determined by the Board, dismissing their claims regarding delays and cost escalations.
Issues: Whether the petitioners were liable for the additional demand raised by the Housing Board and if the cancellation of their allotment was justified.
Ratio Decidendi: The court held that the terms of the Special Registration Scheme were clear and binding, and the petitioners could not contest the additional costs or the cancellation of their allotments based on delays attributed to the Board.
Result: The writ petition is dismissed.
ORDER
1. Although, the matter comes up on an application (1/2022) filed by the respondents seeking vacation of ex-parte interim order dated 23.10.2021; however, on the request of learned counsels for the respective parties, the writ petition was heard on its merit at this stage.
2. Challenge in the writ petition is to the order dated 02.08.2021 passed by the respondent-Rajasthan Housing Board whereby, the allotment of houses made in favour of the petitioners has been cancelled on account of non-deposition of the requisite amount as per the allotment letter.
3. The relevant facts in brief are that the respondent-Board introduced a housing scheme in town Nainwa, District Bundi floating Special Registration Scheme-2007 (SRS). The houses were categorised in six classes such as economically weaker group, low income group, middle income group and higher income group amongst others. The petitioners are applicants under different categories. In the lottery drawn by the respondents for allotment of houses, all the petitioners stood successful and in terms of demand letter dated 27.07.2011, they deposited the seed money. The petitioners were issued allotment letters dated 29.06.2020 raising an additional demand towards cost of the house. Contending that the petitioners have already deposited the entire amount and on account of delay on the part of the Board in raising construction of the houses, this additional demand has been created, this writ petition has been filed for quashing the additional demand and the letters cancelling the allotment on their failure to meet the same.
4. In their reply, the respondents, disputing and denying the averments made in the writ petition, submitted that as per the scheme, the successful applicants were required to pay cost of the houses as assessed at the time of issuance of allotment letter and vide letter dated 27.07.2011, the petitioners were required to pay seed money only.
5. Learned counsel for the petitioners submitted that they have deposited the entire allotment amount in pursuance of the notice dated 27.07.2011 and had the respondent-Board raised construction of the houses within reasonable time, there would not have been any occasion for demand of additional cost. Referring to the contents of para 12 of the writ petition wherein, it is averred that the respondent-Board informed them that due to its dispute with the contractor, the scheme got delayed resulting into levy of additional charges, the learned counsel submitted that there is no specific rebuttal to these averments by the respondents in their reply and hence, for the fault of the respondents-Board, the petitioners could not have been saddled with the additional demand. Elaborating his submissions, learned counsel submitted that delay also invited application of Goods and Service Tax. He further submitted that the additional demand also reflects enhanced cost of the land, which, in view of the fact that it belonged to the respondents-Board, is illegal. He, therefore, prayed that the writ petition be allowed, the order dated 02.08.2021 as also the additional demand raised vide allotment letter dated 29.06.2020 be quashed and set aside and the respondent-Board be directed to allot them houses treating the seed money deposited by them in pursuance of demand dated 27.07.2011 as complete payment towards cost of the house.
6. Per contra, learned counsel for the respondents, drawing attention of this Court towards the provisions of the SRS, submitted that the demand raised vide letter dated 27.07.2011 represented the seed money only and the petitioners were liable to pay the cost of the house determinable on its completion only. He submitted that the respondent-Board allots houses on the principle of 'No Profit No Loss'. He submits that contention of the learned counsel that delay in construction occurred on account of dispute between the Board and the contractor is misplaced. Learned counsel submitted that the demand raised vide letter of allo
Bareilly Development Authority & Anr. vs. Ajai Pal Singh & Ors.: (1989) 2 SCC 116
The court affirmed that applicants under a housing scheme are bound by the terms they accepted, including payment obligations, and cannot contest cost escalations due to delays not promised by the Bo....
The court ruled that administrative decisions regarding allotment policies operate prospectively, ensuring that applicants who complied with prior requirements are not adversely affected by subsequen....
The Housing Board's cancellation of plot allotment was invalid due to lack of notice and failure to follow due process, violating principles of natural justice.
Petitioners cannot challenge allotment amounts after acquiescing to the allotment orders and making partial payments, as they were unauthorized occupants without valid claims.
Priority in housing allotment must be honored, and delays by authorities should not adversely affect applicants' rights.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.