SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

1999 Supreme(Raj) 116

Rajasthan High Court, Jaipur Bench
Honble P.P. NAOLEKAR & MOHD. YAMIN, JJ.
Jaipur Development Authority - Appellant
Versus
The State of Rajasthan & Two Others - Respondents
D.B. Civil Special Appeal (Writ) No. 27 of 1998
Decided On : February 15, 1999

Advocates Appeared:
Bharat Vyas, for Appellant J.D.A. Ajay Rastogi, for Respondent No.2 R.S.E.B. Narendra Jain, for Respondent No.3

Headnote:Indian Electricity Rules, 1956, Rule 82 read with Rules 77, 79 or 80 – High Tension Line of Electricity passing over the plot of respondent No.3 – Petition filed for removal of H.T.L. – Single Bench directed U.I.T. to deposite cost with R.S.E.B. for moving such H.T.L. – Held – When the plot was purchased, overhead high tension line was already led across the plot – Respondent No.3 had made construction of a building without following the due process of law – It is for Respondent No.3 to deposite the cost of removal or shifting of the H.T.L. and not the responsibility of the J.D.A. (Para 6)

       

Honble NAOLEKAR, J.–Respondent No.3 Smt. Shashi Jain, writ petitioner, is owner of plot No. 595 measuring 272 square yards situated in Mahaveer Nagar, Tonk Road, Jaipur. Mahaveer Nagar, Tonk Road Jaipur where the plot of respondent No.3 is situated, is an approved colony. She had deposited development charges at the rate of twenty five rupees per square yards. The construction plan submitted by the respondent No.3 was duly approved by the Jaipur Development Authority, the appellant, on 2.4.1985. When the plot was purchased and the permission was sought for for construction, a High Tension Line (HTL) of electricity was passing over the plot of the respondent No.3. On an enquiry, she was informed by the Jaipur Development Authority that the HTL will be shifted along the road side. On 15th December, 1995 one Shri Sarvesh Jain received serious burn injuries on account of the HTL passing over the plot and the constructed building of the respondent No.3 and thus a writ petition was filed by the respondent No.3 seeking relief that HTL passing over her plot be removed immediately. The respondent No.3 sought further appropriate writ, order or direction directing the respondents (in the writ petition) to shift the entire electricity line and poles from the residential colony of Mahaveer Nagar, Tonk Road, Jaipur which falls over the residential plots of the residents of the Colony. The learned Single Judge vide its order dated 15.10.1997 has allowed the writ petition in part and directions were given as under:-

``......and direct the respondents No. 2 and 3 to negotiate among them- selves and to come to proper conclusion within a period of three months from today and if any amount is to be spent, the same shall be negotiated between the parties themselves and whatever the figures are agreed, would be deposited by the respondent No.3 to respondent No.2 within one month thereafter and the line shall be re- moved or diverted within one month from the depositing of such amount by the respondent No.3 to the respondent No.2....

(2). Thus the learned Single Judge has granted relief to the respondent No.3 (writ petitioner) as regards to prayer made for removal of HTL from her plot on deposit of the cost by the Jaipur Development Authority with the Rajasthan State Electricity Board. So far the general relief claimed in the writ petition for removal of entire electricity line and poles from the residential colony of Mahaveer Nagar, Tonk Road, Jaipur which falls over the residential plots of residents of Mahaveer Nagar, no writ, order or direction was passed. Aggrieved by the directions issued by the learned Single Judge, the Jaipur Development Authority has come in the appeal.

(3). It is submitted by the counsel for the Jaipur Development Authority that directions to deposit the amount for removal of the HTL by the J.D.A. is contrary to law particularly so when the plot was purchased by the respondent No.3 the HTL of electricity was in existence over her plot and brought to our notice Rule 82 of the Indian Electricity Rules, 1956.

(4). On the other hand it is submitted by the learned counsel for the respondent No.3 (writ petitioner) that it is the duty of the instrumentality of the State to secure the safety of the citizens and therefore the J.D.A. who has approved the con- struction is duty bound to remove the HTL which causes danger to the persons residing there.

(5). There cannot be any doubt that the personal security and safety is to be looked after and endeavour should be made to safeguard the persons from the danger of injury being caused by the HTL of electricity led by the RSEB, but the que- stion is what methods and means are to be adopted for the said purpose and by whom. Rule 82 of the Indian Electricity Rules, 1956 is specific in that direction. Rule 82 lays down that when there is a proposal for erection of or alteration to buildings, structures, flood banks and elevation of roads subsequent to the erection of an overhead line (whether co




Click Here to Read the rest of this document

1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top