SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2006 Supreme(Raj) 2374

Rajasthan High Court, Jaipur Bench
Honble SHIV KUMAR SHARMA, J.
Damani Construction Company Pvt. Ltd. (M/s.) - Appellant
Versus
Municipal Corporation, Jaipur - Respondents
S.B. Civil Writ Petition No. 3105 of 1998
Decided On : October 03, 2006

Advocates Appeared:
R.S. Mehta, for Petitioner P.C. Jain, for Respondent

Headnote:Jaipur Development Authority Act, 1958, Sec. 65; Jaipur Development Authority (Jaipur Region Building) Regulation, 1996, Rajasthan Municipalities Act, 1959, Sec. 170(12) – Imposition of levy of additional floor charges – Held – Charges of additional floor area are not permissible u/S. 65 of the JDA Act – Petitioner had not constructed any building as per old regulations, how difference could be charged particularly when the plan had been approved as per new Regulations, the provisions of Sec. 170(12) of 1959 Act are not applicable – Order set aside. (Paras 6 & 7)

       

Honble SHARMA, J.–The prayer of the petitioner in this writ petition is to declare the clause 5 of order dated September 9, 1996 ultra vires and quash the imposition of levy of additional floor area charges. Direction has also been sought to restrain the respondent from withholding complete building plans after one installment of conversion charges was deposited.

(2). The petitioner company has been carrying on construction work and owned a plot bearing No.E-5 at New Colony Jaipur. Earlier the Jaipur Development Authority approved the plan of construction of residential building on October 16, 1996 but no construction could be started. Subsequently the petitioner submitted application to Municipal Corporation Jaipur on November 4, 1989 for change of use of land from residential to commercial purpose along with the fresh building plan. The petitioner also deposited processing fee Rs.666/- vide challan dated November 12, 1997. The Building Plan Committee approved the plan and the change of plot from residential to commercial purpose on payment of conversion charges. Jaipur Development Authority (Jaipur Region Building) Regulation,1996 (for short `1996 Regulations) came into force w.e.f. June 25, 1996 according to which earlier building regulations of 1989 were repealed and only building regulations of 1986 were held applicable. Therefore the petitioner filed application to use the plot for commercial purposes in accordance with 1996 Regulations. Regarding conversion charges the State Government issued circular dated November 9, 1989 for depositing the charges in four annual equal installments on payment of 15% annual interest. The plan was approved on March 4, 1998 and the petitioner was informed that since it had opted for installment of conversion charges, only proportionate plan in relation with conversion charges will be issued. The petitioner submitted that payment of interest on the deferred installments of conversion charges would tantamount to payment of complete conversion charges and therefore the petitioner was entitled for release of complete building plan which had been approved on March 4, 1998.

After the approval of complete plan the respondent issued demand of Rs.6,58,283.50 vide challan No.100B, wherein at Sr.No.5 the demand of Rs.4,35,045 has been made in respect of difference of additional floor area as per new and old rules. The petitioner submitted that the plans were to be considered in respect of new 1996 regulations. The clause 5 of the order could be applicable if the owner was getting additional floor area as per new Regulations and in the case of petitioner since there was no existing building, clause 5 was not applicable. Further the petitioner applied plan within permissible parameters of 1996 Regulations. The respondent was competent to grant permission on vacant land, therefore the clause 5 is illegal. The petitioner also submitted that charges of additional floor area was not permissible under section 65 of the JDA Act. When the petitioner has not constructed any building as per old Regulations no difference could be charged from the petitioner when the plan was approved as per new Regulations.

(3). The respondent filed reply raising preliminary objections in regard to maintainability of writ petition on the ground that the petitioner had alternative remedy of appeal under Section 170 (12) of Rajasthan Municipalities Act,1959. The respondent pleaded that the maps were not submitted and released by the erstwhile Jaipur Development Authority. The plot did not fall in commercial area and it could not be allowed to use the same as commercial plot. The first installment only was deposited after filing the writ petition on July 4, 1998 therefore the petitioner was guilty of misstating the facts. The petitioner deposited conversion charges in respect of premises already constructed that was residential in nature but since the building was being used for commercial purpose levy of difference of charges was p







Click Here to Read the rest of this document

1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top