Rajasthan High Court, Jaipur Bench
Honble R.S. CHAUHAN, J.
Rajendra Prasad - Appellant
Versus
Jaipur Vidyut Vitran Nigam Ltd. - Respondents
S.B. Civil Misc. Appeal No. 2266 of 2006
Decided On : February 09, 2007
Key Points: - The Rajasthan General Supply Conditions use "may", making submission to the Settlement Committee optional and not ousting civil court jurisdiction (!) (!) . - The consumer may approach the Settlement Committee "at the initial stage" but is not compelled to do so (!) (!) . - Submission to the Settlement Committee does not prevent the consumer from approaching the civil court if no settlement is reached (!) (!) . - The civil court has the discretion to adjudicate the dispute and can direct restoration of supply subject to payment of current dues (!) (!) . - The respondent must restore the electricity connection and allow usage if the appellant pays ongoing bills, with the trial Court deciding on any outstanding amounts within six months (!) .
(2). In a nutshell the facts of the case are that the appellant has a modest home in Bharatpur. He also has an electricity connection, connection Account No.1512/18100104. The respondent has also installed an electric Meter, bearing No. 559920 at his house. The electrical connection is for `domestic purpose. The appellant had religiously paid his electric bills to the respondent. In February 2003, the meter recorded as 17695. Thus, in one month, the appellant had consumed 700 units. Hence, the respondent sent a electric bill for Rs.2145/- to the appellant. According to the appellant this was the `normal bill that he had been receiving for the last few years. Therefore, the appellant paid the said bill. However, on 19.3.2003, the respondents officer illegally removed the electric meter ostensibly on the ground that the appellant had tampered with the meter. According to them, the body seal and the terminal seal were tempered with. But, the officers assured the appellant that a new meter would be installed immediately. But, the meter was not restored. In May 2003, the appellant received an electric bill based on `minimum charges. He paid the same. To his great shock and dismay, suddenly in September 2003, the appellant received a notice from the respondent, notice dated 29.9.2003, demanding Rs.22,000/- as `settlement amount for the misuse of energy. He also received a supplementary bill for consumption of 1,59,280 units of electricity. The appellant immediately rushed to the District Consumer Forum in order to challenge the said notice and the supplementary bill. According to him, before the notice and the supplementary bill could be issued, the meter had to be tested by an Electrical Inspector. As the Electrical Inspector had not tested the functions of the electric meter, the notice and the supplementary bill could not be issued. Vide Order dated 30.10.2003, the learned Forum stayed the recovery of the amount. On 13.11.2003, the appellant submitted an application for restoration of the electricity supply, which was duly allowed. A new meter was finally installed. The appellant has been paying the electricity bill regularly since then. However, vide order dated 12.1.2006, the learned Forum has dismissed the appellants complaint on the ground of `jurisdiction. Before the learned Forum, the respondent had taken the plea that as the case involved disputed questions of facts, as it required detailed evidence, the summary procedure prevalent in the Forum was unsuitable for the adjudication of the case. According to them, only the civil courts could adjudicate the case. Agreeing with the respondents contention, the learned Forum dismissed the appellants complaint. As soon as the complaint was dismissed, the respondent disconnected the meter. The appellant and his family were left in the dark.
(3). Therefore, immediately the appellant filed a suit for declaration and for permanent injunction. Along with the suit, the appellant also filed an application for temporary injunction under Order 39 Rule 1 & 2 of the Code. The respondent filed its written statement and contended that at the time of checking of the meter the body seal and the terminal were found to be tempered and VCR was made on 19.3.2003. They also contended that no injunction could be issued against them as the demand made against the appellant is of Rs.22,000/-
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.