SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2004 Supreme(J&K) 353

IN THE HIGH COURT OF JAMMU AND KASHMIR AT JAMMU
S.K. Gupta, J.
Ranvijay Chand & Anr. - Appellant
Versus
State Of J&K & 4 Ors. - Respondent
LPA (W) No. 131/2001
Decided On : 16 December, 2004

Advocates Appeared:
Advocate For Appellant: Sindhu Sharma
Advocate For Respondent: A.H. Naik
Advocate For Respondent: Shaishta Hakim

The main legal point established in the judgment is that the Power Development Department had the absolute power to lay transmission lines for public interest and was only required to provide compensation for any damage caused to the landowners.

Headnote:

Electricity Act - Power Development Department - Section 18 of the Jammu and Kashmir Electricity Act, 1997 - The court held that the Power Development Department had the absolute power to lay transmission lines for public interest and was only required to provide compensation for any damage caused to the landowners. The court emphasized that the department's actions were within the framework of statutory powers and could not be interfered with by the court.

Fact of the Case:

The Power Development Department of Jammu and Kashmir Government formulated a project report for laying transmission lines over the land of the petitioners for public purpose. The petitioners sought re-alignment of the transmission lines to minimize damage to their land, but the respondents argued that they had the right to install the lines as per the original project report.

Finding of the Court:

The court found that the Power Development Department had the statutory power to lay transmission lines and that the petitioners were only entitled to compensation for any damage caused to their land. The court held that the department's actions were in the larger interest of the public and could not be interfered with by the court.

Issues: The main issue was whether the Power Development Department could be prevented from laying transmission lines over the land of the petitioners and whether the court could interfere with the department's actions.

Ratio Decidendi: The court relied on Section 18 of the Jammu and Kashmir Electricity Act, 1997, which recognized the department's absolute powers and the requirement to provide compensation for any damage caused. The court emphasized that the department's actions were within the framework of statutory powers and could not be interfered with by the court.

Final Decision: The court dismissed the appeal, affirming the judgment of the learned Single Judge and holding that the Power Development Department had the statutory power to lay transmission lines and that the petitioners were only entitled to compensation for any damage caused to their land.

Petitioner under Article 226 of the Constitution of India read with Section 103 of the Constitution of Jammu and Kashmir had been commenced by the petitioners, who happened to be the owners in respect of the land aggregating 18 kanals 18 marlas across which the Power Development Department of the State, respondent-2, is said to be laying overhead lines for transmission of electrical energy and putting up towers for support of those lines. By the writ petition, the petitioners have sought a writ of prohibition restraining the respondents from spreading the 220 KV transmission lines including construction of any steel tower over and in the land of the petitioners situated in village Omara, Tehsil and District Udhampur, and further directing the respondents to align the transmission lines in such a manner that the same are laid over the adjacent available Government land without involving the land of the petitioners. The writ petition, however, came to be dismissed by the learned Single Judge vide his judgment and order dated 04-09-2001 and its correctness came to be impugned in LPA (W) No. 131/2001 by the appellants/petitioners. Honble Judges composing the Bench differed in their view and the Lord Chief Justice under Rule 36 of the Jammu and Kashmir High Court Rules, 1997 designated another Judge to hear on the point on which the Judges differed in their view. This is how the matter came to be heard by this Court. The facts of the case, in brief, may be stated as follows.

2. In pursuance of a Scheme, respondent-2, Power Development Department of Jammu and Kashmir Government formulated a project report for laying transmission lines 220 KV S/C Gladni, Udhampur and after securing an administrative approval to the project subsequent to its clearance by the Techno-Economic Committee vide order No. 27-PDD of 1996 dated 19-01-1996, a survey was conducted for the execution of the Scheme to be purely for public purpose. On the approval of the plan, the land of the petitioners was to be utilized for the laying of the transmission lines. After crossing the Army area, transmission lines had to cross over the land of the petitioners/appellants for completing the connection with Tower No. 113 of the transmission lines. That in between Tower No. 112 and Tower No. 113 was located the land in occupation of the appellants/petitioners. Transmission lines were to cross through the land of the appellants/petitioners for completion, which, according to them, was likely to reduce its utility and could not be used for agriculture purposes as it had been used earlier, besides its availability for residential use. According to the appellants/petitioners, the proposed spreading/laying of the transmission lines is passing through the middle of their land and will render the entire piece of land unusable being reduced in its utility either for agriculture purpose or for residential use. The appellants/petitioners approached the respondents with a representation in urging for re-alignment, as the Department has already done in deviating from the original alignment and the overhead transmission lines be laid on one side of the land so that minimum land of the appellants is utilized and minimum damage is caused while installing the proposed Tower in re-alignment.

3. The stand taken by the respondents in their return is that respondents are within their rights to install the Towers in accordance with the original project report based on a sanctioned Scheme and the petitioners/appellants are only entitled to compensation as per the Electricity Act for the land, which is likely to be used for erecting Transmission Towers. That the respondents cannot be prevented from doing an act, which is recognized by a statute. The act of the respondents in laying the transmission lines to provide electricity and undisturbed power supply is in the larger interest of the public. Further plea of the respondents is that so long as the work is done by the respondents, viz., Power De














Click Here to Read the rest of this document

1
2
3
4
5
6
7
8
9
10
11
Judicial Analysis

AI

SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top