2000 Supreme(J&K) 51
IN THE HIGH COURT OF JAMMU AND KASHMIR AT Jammu
A.K. Goel, J.
Union Of India & Ors. - Appellant
Versus
D. Khosla & Co. - Respondent
CIMA No. 157 And 158/1996
Decided On : 29 February, 2000
Important Points
Subject
Arbitration Law - Appointment of Arbitrator
Act Referred
Headnote
Arbitration - Appointment of Arbitrator - A.A.F.W. No. 2249 - Section 8 of the Arbitration Act - Court's Power to Appoint Arbitrator
Fact of the Case:
The appeals arose from disputes over the appointment of an arbitrator in two separate cases related to construction contracts. The designated authority failed to appoint an arbitrator within the stipulated time, leading to a court application for appointment of an arbitrator. The court revoked the authority of the initially appointed arbitrator and appointed a new arbitrator. The appellants contested the court's authority to make the appointment.
Finding of the Court:
The court found that the failure of the designated authority to appoint an arbitrator within the specified time allowed the court to appoint an arbitrator under Section 8 of the Arbitration Act. The court held that the designated authority's delay amounted to overreaching and circumventing the judicial process. The court also cited precedents where courts had appointed arbitrators in similar circumstances.
Issues: The main issue was whether the appellants had forfeited their right to appoint an arbitrator after the designated authority failed to do so within the specified time.
Ratio Decidendi: The court's power to appoint an arbitrator under Section 8 of the Arbitration Act is triggered when the designated authority fails to appoint an arbitrator within the stipulated time. The court can intervene to ensure that the arbitration process is not unduly delayed or circumvented.
Final Decision: The court dismissed the appeals, upholding the appointment of the new arbitrator by the court and ordering the appellants to pay costs to the respondent.
Advocate For Appellant: Subash Bhat
Advocate For Respondent: K.L. Pandita
CIMA No. 157/96 and CIMA No. 158/96.
2. Brief facts giving rise to these appeals need to be tested. CIMANo. 157/96
3. This appeal has arisen from the order passed by the learned Sessions Judge, Jammu in CID No. 17/Arbitration dated 27-4-1996, whereby petition for appointment of an arbitrator has been alleged and as a consequence of this authority of arbitrator who was appointed by respondent during the pendency of the said petition before trial court was revoked and in his place another arbitrator viz. R. V. Ahuja (AVSM) Retd. Chief Engineer, A-2/53, Azad Apartment, Opp. IIT Gate, Hauz Khas, New Delhi was appointed an arbitrator and matter in dispute was further referred to him for adjudication. Parties had entered into an agreement No. CE (P) Samparak/MD-4/86-87 for the construction of permanent bridge over River Tain at KN 80.50 on Akhnoor-Poonch Road. This work was allotted to the respondent. This work was undertaken by respondent, however, numerous difficulties on account of non-payment as well as lack of decision on the part of department. This resulted in work being not completed even within the extended period of contract. Though fault was on the part of Chief Engineer, Samparak, who instead of admitting the name chose to cancel the contract vide its communication dated 14-6-1993.
4. Since dispute had arisen between the parties to the agreement, therefore, respondents admittedly approach and requested designated authority for the appointment of the arbitrator in terms of clause 70 of the contract agreement for referring the dispute for determination. The contract period in the instant case has already expired on 31-3-1993
5. The designated authority i.e Director General Border Roads Organisations, Army Headquarter, Kashmir House. New Delhi was under obligation to have appointed an arbitrator within a period of 15 days on receipt of communication in that behalf from the respondent. Since it failed to appoint an arbitrator and thus neglected in his duty, therefore, respondent filed an application for appointment of an arbitrator. The claim of the respondent was contested on behalf of the appellants. According to them whatever amount was due stands already paid. The contract had to be cancelled because of failure on the part of the respondent and alternate arrangement for its completion was undertaken by them. It was admitted that arbitrator is to be appointed to adjudicate the disputes. He is to be appointed by the authority named in the agreement. It is specific case of the appellants that it is respondent who owes money to them and not other way around as claimed by latter. It is also case of the respondent that arbitrator if at all could be appointed was only after the arrangement to carry out the balance work at the risk and cost of the respondent was completed.
6. Another fact that needs to be noted is that respondents approached the competent authority in terms of the agreement to appoint an arbitrator on 16-2-1994. Till 11th July, 1995 no action had been taken by the appellants. Even in the objections filed by the appellants to the application for appointment of an arbitrator by the Court, it is nowhere stated that arbitrator has been appointed on 11th July, 1995, i.e. during the pendency of the application for appointment of an arbitrator. It appears that when Brig. Sudhir Kumar was appointed as an arbitrator, an application was filed for quashing the said order. This application has also been disposed of by means of impugned order by the learned Court below.
CIMA No. 158/96
7. In this case vide Agreement No. CE(P) Samparak/Mn-1 / 89-89 parties entered into an agreement for construction of permanent bridge over Nisra Tawi at KN 65.50 on Akhnoor-Poonch Road. Other facts are almost identical as are of CIMA No. 157/96. In this case also Brig. Sudhir Kumar was appointed an arbitrator on 11-7-1