2013 Supreme(J&K) 505

MUZAFFAR HUSSAIN ATTAR
Hafiz Construction Co. Pvt. Ltd. – Appellant
Versus
State – Respondent


Advocates Appeared:
G.A. Lone, M.A. Chashoo, M.A. Thakur, S. M. Ayub, R.A. Jan.

   1. Construction of Corporate Office Complex of Jammu & Kashmir State Power Development Corporation Limited (JKSPDC) at Silk Factory, Raj Bagh, Srinagar, became subject matter of dispute between the petitioner and State and its other authorities in OWP 65/2013. Writ petition was disposed of vide order dated 09-04-2013. Mr. Chashoo, learned AAG, had stated at the bar in the said case that the respondents proposed to re-advertise the tender notice and decision in this behalf is expected to get manifest by issuance of formal order shortly. The Court disposed of the writ petition on the expectation that the respondents will issue fresh tender notice after the conditions, set out in the tender notice, which was impugned in the said writ petition, are modified.

2. Government of J&K, on 19-02-2013 issued order No. 47-PW(R&B) of 2013, which is taken note of:

Government of Jammu & Kashmir
Civil Secretariat: Public Works (R&B) Department
   Sub: - Revised financial delegation for works to be allotted to JKPCC.
   Reference: - Cabinet decision No. 25/05/2013 dated 18.08.2013
   Govt. Order No. 47-PW(R&B) of 2013
   Dated: 19.02.2013
  In partial modification of Government Orde



























Click Here to Read the rest of this document

1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon telegram-icon
whatsapp-icon Back to top