2019 Supreme(J&K) 348

IN THE HIGH COURT OF JAMMU AND KASHMIR AT JAMMU
Sanjay Kumar Gupta, J.
Romesh Padha and Ors. - Appellants
Versus
State of J&K c/w connected matter - Respondent
CRMC No.158/2017, IA No.1/2017 c/w
CRMC No.87/2017, IA No.1/2017
Decided On : 29-3-2019

Subject

Criminal Law - PRE-TRIAL

Act Referred

CRIMINAL PROCEDURE CODE : S.154
JAMMU AND KASHMIR CRIMINAL PROCEDURE CODE : S.561(a)
JAMMU AND KASHMIR PREVENTION OF CORRUPTION ACT : S.5(1)(d), S.5(2)
RANBIR PENAL CODE : S.120(b)

Headnote

J&K Prevention of Corruption Act, 2006 - Section 5 – Ranbir Penal Code - Section 154 - FIR - Enquiry - Government service as Executive Engineer and Assistant Executive Engineer in the year respectively from Power Development Department and petitioner continues to be in service even as on today and is presently posted as Junior Engineer that somewhere in the year when the petitioner was posted as Executive Engineer in M&RE Division of Power Development Department certain purchases were made on emergency basis that M&RE Division of the Power Development Department deals with the supply of power to various consumers in area of their jurisdiction – Held Grounds taken that petitioners have retired from services is not tenable because once criminal offences have been committed one has to pay for that no matter accused has been retired - Further petitioners have relied upon certain documents during course of argument this court is neither an investigating agency nor court of appeal so these documents cannot be considered petitioners are at liberty to place these documents before IO who shall consider these documents during course of investigation - Another argument of counsels for petitioners is that one impugned FIR has been lodged for two different Divisions one and another which is not permissible under law - This argument is also not tenable because and falls under District counsel for petitioners have failed to show any law as to how ACB cannot conduct investigation of cases of financial irregularities of one District with regard to same funds when offences have taken place of same nature though in different Division of same department - Further as it is evident from FIR there are serious allegations against the petitioners with regard to purchase of electric items through various supply orders to different firms without following formalities as provided in financial code in this way huge money of State exchequer is involved – petition dismissed

Advocates Appeared:
For the Petitioner(s):Mr. Rahul Pant, Advocate (in CRMC No.158/2017)
For the Petitioner(s):Mr. Parimoksh Seth, Advocate & Mr. Navyug Sethi, Advocate (in CRMC No.87/2017)
For the Respondent(s): Mr. Raman Sharma, Dy AG

JUDGMENT :

1. Both the petitions have arisen out of same FIR No.29/2016 dated 28.12.2016, registered at Police Station, Vigilance Organization, Jammu for commission of offence under Section 5(1)(d) read with Section 5(2) of the J&K Prevention of Corruption Act, 2006 and Section 120-B RPC against the petitioners. Petitioners, who were officers of Electric M&RE Division Rajouri and Kalakote, have challenged the registration of FIR against them on various grounds.

2. In CRMC No.158/2017, it has been stated that petitioner Nos.1 & 2 have been retired from Government service as Executive Engineer and Assistant Executive Engineer in the year 2008 and 2010 respectively from the Power Development Department and petitioner No.3 continues to be in service even as on today and is presently posted as Junior Engineer; that somewhere in the year 2006 when the petitioner No.I was posted as I/C Executive Engineer in the M&RE Division Rajouri of the Power Development Department, certain purchases were made on emergency basis; that M&RE Division of the Power Development Department deals with the supply of power to various consumers in the area of their jurisdiction. Most of the times when electrical material is required on emergency basis, Electric Central Store of the Power Development Department is approached for the supply of said material and in case of non-availability of said material, purchase is made from open market either through government agencies or from registered firms by inviting quotations; that in case the necessary supplies are not received/not available in the Electric Central Store of the Power Development Department, the purchases are made on emergency basis, inasmuch as the failure to have the requisite material purchased on emergency basis can lead to disruption of power supply to the various consumers which at times results into law and order problem. It is commonly faced problem in the Power Development Department more particularly in the M&RE Wing that as and when the power is disrupted during the peak hours in the summer season in Jammu or in winter season in Kashmir, it causes law and order problem and violent mobs of the consumers even attack the power Stations. On many occasions even the officials of the Power Development Department dealing in the M&RE Wing are man handled because of the disruption of power. Otherwise also it is hard to imagine that in case of emergency requirement of electrical material to ensure the uninterrupted power supply to the consumers, the NIT will be issued or bids will be invited; that under similar set of circumstances in the year 2006 when petitioner No.1 was posted as Executive Engineer in Rajouri, certain purchases were made after the information was received from the Electric Central Store of the Power Development Department regarding the non-availability of such material. The material in the form of conductors, lightening arresters, transformers/poles etc. were purchased on emergency basis and the same was the practice throughout the State as it is not practically possible to issue N1T and then to purchase the material in case of emergency. The procedure of issuing NIT and calling for bids can take months together and during the aforesaid process the power supplies cannot remain interrupted to the consumers. During the said period i.e. 2006 petitioner No.2 was posted as Assistant Executive Engineer and Petitioner No.3 was posted as Junior Engineer in M&RE Division, Rajouri; that it is not only the Division Rajouri that such kind of purchases were made but throughout the State same was the practice and same system continues even as on today; that the purchases which were made as per the averments made in the FIR, in the year 2006 by the Division of the petitioners, have been estimated at Rs.98,99,202.00 (rupees ninety eight lac ninety nine thousand two hundred and two only). Similarly in the same FIR purchases in the Kalakote Division have been shown to the tune of Rs.36,69,132.00(