HIGH COURT OF JAMMU AND KASHMIR AT JAMMU
Rajesh Bindal and Sanjay Dhar, JJ.
J&K Power Development Department
Versus
M/s KEC International Ltd.
LPA No.50/2019 (O&M), LPA No.51/2019 (O&M) and LPA No.52/2019 (O&M)
(Through Video Conferencing)
Decided on 21-11-2020

Subject

Arbitration Law - Setting Aside Arbitral Award

Act Referred

JAMMU AND KASHMIR ARBITRATION AND CONCILIATION ACT : S.33(1), S.34(3), S.34, S.33, S.5
LIMITATION ACT : S.14, S.15, S.16, S.17, S.18, S.19, S.20, S.21, S.22, S.23, S.24, S.29(2), S.4, S.5, S.6, S.7, S.8, S.9, S.10, S.11, S.12, S.13

Headnote

J&K Arbitration and Conciliation Act 1997 - Section 34 - Limitation Act - Sections 4 to 24 - Claim of petitioner - Payment of interim award - counsel for appellant submitted that no doubt re was a delay in filing application section Act however fact remains that appellant had earlier filed an application section Act for correction of errors in interim award- same was dismissed Immediately application under section Act was filed - Hence same cannot be said to be barred by limitation- Such an application could be filed in terms of section Act as re was error in interim award passed by Arbitral Tribunal for short Tribunal - Against admitted amount appellant had also raised counter claim- In light of that counter claim interim award could not be passed by Tribunal as even admitted amount was subject to final adjudication of counter claim made by appellant –Held Court that hundreds of rupees were drawn from treasury against projects which were never sanctioned- Or funds were diverted from project to without any approval from competent authority- tenders were issued without sanction of projects- It was a case of PWD(R&B) Department Jammu- case in hand is of Power Development Department- This apparently shows that this is standard operating procedure being adopted by officers in different departments Jammu & Kashmir- only reason can be that no action is taken against any of officers who are indulging in se types of corrupt practices and consider law into - y do not follow any established procedure or financial rules- Unless strict disciplinary action is taken against se officers y will not mend ways- It is only because competent authority also keeps its eyes closed to all illegal actions of officers for reasons best known to it that y feel encouraged in repeating se kinds of activities- Even if any enquiry is initiated same remains pending for years together case in which some strict disciplinary action is initiated and taken to logical end without wasting time to be message to all those who are indulging or trying to enter kinds of activities and or usurping tax payer’s money case in hand responsibility of officers concerned be fixed on account of whose commission or omission government will suffer or has been made to suffer loss- amount of loss should also be recovered from m to give a clear message to all concerned of course after following due process of law – Order accordingly

Advocates Appeared:
For the Appellant(s): Ms. Seema Shekher, Sr. AAG
For the Respondent(s):Mr. Pranav Kohli and Mr. Rahul Sharma, Advocates

Order

1. This order will dispose a bunch of three appeals bearing LPA Nos. 50-52 of 2019. The facts are being noticed from LPA No. 50/2019.

2. The present appeal has been filed impugning the judgment dated 06.04.2018, passed by Learned Single Judge whereby application filed by the appellant under section 34 of the J&K Arbitration and Conciliation Act, 1997 (for short ‘the Act’), was dismissed.

3. Impugning the aforesaid judgment, the learned counsel for the appellant submitted that no doubt there was a delay in filing the application under section 34 of the Act, however, the fact remains that the appellant had earlier filed an application under section 33 of the Act for correction of the errors in the interim award. The same was dismissed on 02.10.2017. Immediately thereafter, application under section 34 of the Act was filed on 29.10.2017. Hence, the same cannot be said to be barred by limitation. Such an application could be filed in terms of the section 33 of the Act as there was error in the interim award passed by the Arbitral Tribunal (for short ‘the Tribunal’). Against the admitted amount, the appellant had also raised counter claim. In the light of that counter claim, interim award could not be passed by the Tribunal as even the admitted amount was subject to final adjudication of the counter claim made by the appellant.

4. She further submitted that the delay was also on account of the fact that after the interim award was passed, audit was carried out in the department and it was found that the amount was not due to the respondents.

5. On the other hand, the learned counsel for the respondents submitted that section 34 of the Act under, which the application was filed by the appellant, clearly provides a period of three months for filing such an application. It further provides for a limited condonation up to 30 days. Beyond that, the delay cannot be condoned. In the case in hand, interim award was passed by the Tribunal on 06.03.2016, whereas the application under section 34 of the Act was filed on 29.10.2017. The same was delayed by 572 days. In support of the arguments, reliance was placed upon judgments of Hon’ble the Supreme Court in cases reported as (2010) 12 SCC 210 titled as State of Himachal Pradesh and another Vs M/s Himachal Techno Engineers and others and (2019) 2 SCC 455 titled as Simplex Infrastructure Limited Vs Union of India.

6. It was further submitted that the arguments raised regarding filing of application under section 33 of the Act is totally misplaced for two reasons. Firstly, a perusal of the application shows that the same was not filed under section 33 of the Act. It was for recalling of the interim award. The same is not the scope of the section 33 of the Act. In any case, application was filed on 02.10.2017. It was more than 1½ years after the interim award was passed. Limitation for 30 days has been provided in section 33 of the Act for filing such an application. It is only with the consent of parties, where any clerical, arithmetical error is to be corrected that the period of 30 days can be extended. In the case in hand, there was no consent given by the respondents in filing such an application. Hence, filing or decision of the aforesaid application will not take the case of the appellant any further as it has nothing to do with section 33 of the Act. In support of the arguments, reliance was placed upon a judgment of Hon’ble the Supreme Court in (2007) 10 SCC 742 titled as State of Arunachal Pradesh Vs Damani Construction Co.

7. In response the learned counsel for the appellant submitted that even if the provision of law is not mentioned in the application filed before the Tribunal, however, its sources can be traced to section 33 of the Act, which clearly provides that application for such a prayer could be filed.

8. Heard learned counsel for the parties and perused the paper book.

9. The basic facts which are not in dispute, are that an Arbitral Tribunal was constituted to resolv