IN THE HIGH COURT OF JAMMU AND KASHMIR AND LADAKH AT SRINAGAR
Ali Mohammad Magrey, J.
Firdous Kamran Shora – Petitioner
Versus
Union of India & Ors. - Respondents
WP(C) No. 1330 of 2021 C/w CCP(S) No. 356 of 2021
Decided On : 24-09-2021
Constitution of India, 1950 - Article 12 and 226 - Tender Notice - Agreement - Non-completion of the Contract for NFS project by Department of Telecommunication - Action and inaction on part of Respondents in determining contract between parties and changing site, that too, without negotiating with Petitioner amounts to arbitrary exercise of power, aimed at giving undue benefit to some other blue-eyed contractor(s) - It is submitted that there was no agreement executed between parties, therefore, there was no question of invoking any clause of agreement which was not in existence.
Finding of the court: If decisions have been taken in bonafide manner, although not strictly following norms laid down by the Courts, such decisions are upheld on principle laid down by Justice Holmes that Courts, while judging constitutional validity of executive decisions, must grant certain measure of freedom of ‘play in joints’ to executive - The decision taken by Respondents in putting work in question to fresh tenders was certainly not irrational in any manner whatsoever or intended to favour anyone. This decision, apart from being lawful and sound, appears to have been taken by Respondents in view of non-acceptance of all terms and conditions of contract on part of Petitioner - Petitioner has not been able to establish before Court that decision taken by Respondents putting the works in question to fresh tenders is an arbitrary exercise of power or that same was/ is malafide in nature.
Result : Petition dismissed
JUDGMENT :
1. In the instant Petition, the Petitioner is aggrieved of Notice No. 6 (6) 58 EE/DIV/SGR/350 dated 5th of July, 2021 as well as the impugned tender Notice bearing NIT No.12/EE/DIV/SGR/2021-22 dated 7th of July, 2021 issued by the Respondent No.3.
2. Mr A. H. Naik, the learned Senior Counsel representing the Petitioner, submitted that the action and inaction on the part of the Respondents in determining the contract between the parties and changing the site, that too, without negotiating with the Petitioner amounts to arbitrary exercise of power, aimed at giving undue benefit to some other blue-eyed contractor(s). It is submitted that there was no agreement executed between the parties, therefore, there was no question of invoking any clause of the agreement which was not in existence.
3. Objections stand filed on behalf of Respondents 2 and 3. It is stated that the BSNL, Civil wing, was assigned the responsibility of execution of NFS project by the Department of Telecommunication (Government of India). The Project, as stated, is meant for enhancing the communication system of the Army and is of national importance as the project site is located at a highly sensitive strategic area of LOC. It is pleaded that the Petitioner was awarded the contract for timely execution, but he, despite repeated reminders, did not execute the same on time, constraining the Respondents to take the impugned action against the Petitioner and re-tender the work, therefore, no interference is warranted in the said process from this Court.
4. Heard the learned counsel for the parties, perused the pleadings on record and considered the matter. I have also gone through the relevant records made available by the learned Senior Counsel representing the Respondents 2 and 3.
5. At the very outset, what requires to be stated is that the Courts are expected to exercise judicial restraint in interfering with the administrative action, particularly in the matter of tender or contract. Ordinarily, the soundness of the decision taken by the tender issuing authority ought not to be questioned, but the decision-making process can certainly be subject to judicial review. The soundness of the decision may be questioned, firstly, if the decision made is so arbitrary and irrational that the Court can say that the decision is such that no responsible authority acting reasonably and in accordance with relevant law could have reached or; second, if the process adopted or decision made by the authority is malafide or intended to favour someone or; third, if the public interest is affected. In the case on hand, when the Petitioner-firm did not fulfil all the terms and conditions prescribed by the Respondents with regard to completion of the project on time, despite repeated reminders, in such eventuality, the decision of the Respondents in issuing the impugned communication and putting the work to fresh tender cannot be said to be one where they have acted in a manner in which no responsible authority acting reasonably and in accordance with the relevant law would have acted. Furthermore, a bare perusal of the pleadings on record, does not indicate that the decision made by the authority is malafide or intended to favour someone. In fact, the decision of the Respondents was the result of non-completion of the Contract on time on part of the Petitioner, more so when the entire project was located at a highly sensitive and strategic area of LOC. Likewise, the third ground of public interest is also not affected in the present case because while it may be in public interest to have greater competition, it is also in public interest that all the tender conditions are complied with as prescribed by the tender issuing authority and that there is no uncertainty in that area.
6. Law on the subject of scope of judicial review in the matters of Contract is no more res integra.
7. In case titled ‘Tata Cellular V. Union of India: (1994) 6 Supreme Court Cases 651’, at Paragraph No.9
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.