SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2006 Supreme(Jhk) 549

High Court Of Jharkhand
Judgename : S. J. MUKHOPADHAYA
NRIPENDRA NARAYAN SINHA - Appellant
Versus
JHARKHAND STATE ELECTRICITY BOARD, RANCHI - Respondents
W. P. 7200 Of 2005
Decided On : 05/05/2006

Advocates Appeared:
I.Sen Choudhary, R.Krishna

The central legal point established in the judgment is the entitlement of workers to payment for actual hours of overtime work performed, as per the provisions of the Factories Act 1948 and the circulars issued by the Bihar State Electricity Board.

Headnote:

Overtime Work - Payment Dispute - Factories Act 1948, Section 59 - The court discussed the provisions of Section 59 of the Factories Act 1948, which entitles workers to overtime wages at twice the ordinary rate of wages for working beyond prescribed hours. The court also considered the circulars issued by the Bihar State Electricity Board, which restricted overtime work beyond 50 hours per quarter and outlined penalties for violations.

Fact of the Case:

The petitioner sought payment for overtime work performed as an assistant Controller at the State Electricity Board. The Board rejected part of the claim based on limitations for overtime work. The petitioner challenged the decision, seeking payment for the actual hours worked.

Finding of the Court:

The court held that the petitioner was entitled to payment for the actual hours of overtime work performed, as the respondents did not dispute the hours claimed. The impugned order rejecting part of the claim was set aside, and the case was remitted to the respondents with directions for payment and disciplinary action against officers deviating from the Board's instructions.

Issues: The issues involved the rejection of part of the petitioner's claim for overtime payment, the limitations on overtime work imposed by the Bihar State Electricity Board, and the violation of provisions of the Factories Act 1948.

Ratio Decidendi: The court determined that the petitioner was entitled to payment for actual hours of overtime work and directed the respondents to pay the remaining dues. It also emphasized the need for disciplinary action against officers deviating from the Board's instructions and highlighted the recoverability of irregular overtime payments from the erring officers.

Final Decision: The writ petition was allowed, setting aside the impugned order and remitting the case to the respondents with directions for payment and disciplinary action. The petitioner was awarded costs of Rs. 5,000.

Judgment :

S. J. MUKHOPADHAYA, J.

( 1 ) THE petitioner has preferred this writ petition against the order, contained in Memo no, 2673 dated December 2, 2004, issued by the 5th respondent, General Manager-cum-Chief engineer, Transmission Zone-1, Ranchi, whereby and whereunder, claim of the petitioner for payment of dues for performing overtime work has been partly rejected on the ground that there is a limitation to take overtime work for more than 50 hours in a quarter of a particular year or maximum 150 hours in the concerned financial year, as per the Boards circular.

( 2 ) FURTHER prayer has been made by the petitioner for a direction on the respondents to prosecute the concerned 2nd to 5th respondents for violating the provisions of Factories Act 1948, in terms with the provisions of Sections 92 and 105 of the Factories Act, 1948.

( 3 ) THE petitioner, who was posted as assistant Controller, Transmission Sub-Division, Jadugora, while performing the duties as such, the State Electricity Board took overtime work on different dates in between january, 1994 and December, 2001 but did not pay him the overtime dues. Being aggrieved, the petitioner had to move before this Court in wp (S) No. 127 of 2002 for a direction on the electricity Board to pay him the amount for taking overtime work. A Bench of this Court vide order dated January 7, 2002 remitted the case to the General Manager-cum-Chief engineer, Area Electricity Board, to determine the claim but decision having not been communicated, the petitioner had to prefer a contempt petition. In the contempt case being contempt Case (C) No. 382 of 2002, the opposite parties brought to the notice of the court a decision communicated vide Impugned memo No. 2673 dated December 2, 2004 and having noticed the same, this Court dropped the proceeding on December 3, 2004. In the aforesaid background, the petitioner had to challenge the impugned order No. 2673 dated december 2, 2004, whereby, part prayer for payment of overtime dues has been rejected and the respondents have allowed and paid the overtime only to the extent of 50 hours per quarter.

( 4 ) THE petitioner claims the following hours of overtime work beyond the normal working hours, as was taken by the respondents for managing the control room where the petitioner was posted;

Year

Month

Sanctioned over time hours


1994

January

160


1994

August

192


1994

October

224


1994

April

48


1994

May

192


1994

June

176


1995

July

48


1995

September

72


1995

October

112


1995

December

112


1995

January

104

1995

February

88


1995

March

72


1996

June

88


1996

July

152


1996

August

152


1996

September

152


1996

October

160


1996

November

96


1996

December

176


1996

January

88


1996

February

112


1996

March

128


1996

April

240


1996

May

248


1997

June

168


1997

July

200


1997

August

200


1997

September

200


1997

October

232


1997

November

216


1997

December

160


1997

January

240

1997

February

232


1997

March

168


1997

April

200


1997

May

200


1997

June

144


1998

July

40


1998

August

200


1998

September

240


1998

October

264


1998

November

248


1998

December

160


1999

January

176


1999

February

176


1999

March

184


1999

April

40


1999

October

40


1999

November

40


1999

December

12


1999

January

40


1999

February

32


1999

March

8


1999

April

24


2000

May

8


2000

July

16


2000

August

16


2000

October

16


2000

November

40


2000

December

40


2000

January

32


2000

February

32


2000

April

248


2000

May

8


2000

June

8

2001

July

32


2001

August

32


2001

September

16


2001

October

48


2001

November

56



( 5 ) THE respondents, have not disputed the aforesaid fact that the overtime work to the extent of 8 to 224 hours in a month was also taken from the petitioner In fact, the overtime work for different months, as given by the petitioner, has not been disputed and from the impugned order, it appears that the then general Manager-cum- Chief Engineer, Area electric Supply, also accepted the same and has ordered to make payment, which is evident from the impugned order No. 2673 dated december 2, 2004, as quoted hereunder:"it appe













Click Here to Read the rest of this document

1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top