IN THE HIGH COURT OF JHARKHAND AT RANCHI
APARESH KUMAR SINGH, J.
M/s ICON Controls Pvt. Ltd. through its Managing Director Namely S.K. Pasupathy - Petitioner
Versus
MECON Limited - Respondent
Arbitration Application No. 19 of 2017
Decided On : 16-03-2018
Arbitration - Appointment of Arbitrator - Arbitration and Conciliation Act, 1996, Section 12(1)
Fact of the Case:
Dispute arose between the parties regarding the completion of work under a contract, leading to the invocation of the arbitration clause. The petitioner sought the appointment of an independent arbitrator under Section 11(6) of the Arbitration and Conciliation Act, 1996.
Finding of the Court:
The court found that there was an admitted dispute in relation to the execution of the work, and despite statutory notice, no appointment of an arbitrator had been made by the respondent within the prescribed time. The court, therefore, appointed Mr. Sajjan Kumar Dubey as an independent arbitrator to adjudicate the dispute between the parties.
Issues: Dispute over completion of work, invocation of arbitration clause, and appointment of an independent arbitrator.
Ratio Decidendi: The court's decision was influenced by the existence of an arbitration clause in the agreement between the parties, the admitted dispute in relation to the execution of the work, and the failure of the respondent to appoint an arbitrator within the prescribed time.
Final Decision: Mr. Sajjan Kumar Dubey was appointed as an independent arbitrator to adjudicate the dispute between the parties.
By the detailed order dated 02.02.2018, this Court had proposed to appoint Mr. Sajjan Kumar Dubey, Retired Principal District Judge, Deoghar as an Arbitrator to adjudicate the dispute between the parties. He was asked to submit his declaration in terms of section 12(1) of Arbitration and Conciliation Act, 1996, as amended by the Act No. 3 of 2016. The proposed Arbitrator had furnished his declaration through letter dated 12.03.2018. Learned counsel for the parties submit that he may be formally appointed as an Arbitrator to adjudicate the dispute between the parties. For better appreciation, order dated 02.02.2018 is reproduced hereunder:
“Heard learned counsel for the parties.
Applicant has sought appointment of an independent Arbitrator under Clause 36.1 of the agreement being work order dated 25th May, 2010, whereunder the scope of the work to be executed by the applicant was as under:
“Order for design, engineering, manufacture, supply, erection, testing, commissioning of instrumentation & Control equipments including assistance during Performance Guarantee Test of Battery and Post Commissioning Services (Pkg. No. SE-869) required for New 7m tall Coke Oven Battery #6 at Rourkela Steel Plant, Rourkela.”
According to the applicant, the dispute arose as the work could not be completed within the scheduled nine months period due to the reasons beyond control of both the parties as well as non-availability of fronts. As such, time to time extension was granted by the respondents to complete the work. The matter could not be resolved as there were disputes relating to non-availability of fronts and claims of payment by the petitioner-applicant also remained unredressed for the work executed. According to the petitioner, respondents had received the Preliminary Acceptance Certificate and Commissioning Certificate from Rourkella Steel Plant as the petitioner had completed the job. However, despite request for payment, no action was taken by the respondents. Reminder was also sent vide Annexures: 4 & 5.
Petitioner being aggrieved due to non-responsive approach of the respondents invoked the Arbitration Clause, which reads as under:
“36.0 ARBITRATION
Any disputes, differences, whatsoever, arising between the parties out of or relating to the construction, meaning, scope, operation or effect of this Order shall be settled between MECON and the Contractor amicably. If, however, the Purchaser and the Contractor are not able to resolve theirs disputes/differences amicably as aforesaid the said disputes/differences shall be settled by Arbitration in accordance with the Rules of Arbitration and the award made in pursuance thereof shall be binding on the parties.
The arbitration shall be governed and regulated in all respect according to Laws of India.
The Arbitration proceedings in case of other Indian companies shall be regulated and governed by Indian Arbitration and Conciliation Act 1996, or such modification thereof.
36.2. The venue of arbitration proceeding shall be Ranchi
36.3 Work under this Order shall be continued by the Contractor during the arbitration proceedings, unless otherwise directed in writing by MECON or unless matter is such that the work cannot possibly be continued until the decision of the arbitrator is obtained.”
Letter dated 17th May, 2016 (Annexure-6), however, remained un-responded. Neither payments were made nor appointment of any Arbitrator was made. That is why petitioner approached this Court invoking the jurisdiction of Hon'ble the Chief Justice for appointment of an independent Arbitrator under Section 11(6) of the Arbitration and Conciliation Act, 1996.
Respondents have filed their written statements. According to counsel for the respondents, during the period of correspondence and even in course of pendency of this application, efforts were made to settle the matter amicably. However, as appears, parties have not been able to resolve their disputes. The request for appointment on part of the petitioner has ho
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.