2019 Supreme(Jhk) 1999

IN THE HIGH COURT OF JHARKHAND AT RANCHI
Sujit Narayan Prasad, J.
M/S Kalawati Builders - Petitioner
Vs.
National Project Construction Corporation Limited - Respondents
W.P. (C) No. 766 of 2016
Decided On : 15-10-2019

Advocates Appeared:
For the Petitioner:Mr. Sunil Kumar Sinha, Advocate
For the Respondents:Mr. Sarvesh Kumar Verma, Advocate

Headnote:

Constitution of India Article 226 - National Project Construction Corporation - Tender - Petitioner participated in tender process for consideration of his candidature for execution of work, in which, he has been found successful and accordingly, work has been allotted in his favour in terms thereof, letter of acceptance has been issued and agreement has been executed in between petitioner and respondents - Thereafter, petitioner has started execution of work but in course of its execution, hindrance has come from anti-social element, terrorist group of P.L.F.I, which resulted even into death of brother of petitioner and one local people, who has been engaged to look after work, which led petitioner to represent before authority vide application stating therein entire fact with a request for closure of contract, disbursement of money to extent as per execution of work as also for refund of earnest money but according to petitioner instead of taking decision thereupon authorities has come out with an order by which, forfeiture of earnest money has been ordered - Apart from that petitioner has been blacklisted for a period of three years vide order – Held, This Court, after having heard learned counsel for parties and considering stand taken by respondents-authorities taken of counter affidavit, is of view that since petitioner has raised issue about hindrance which has occured in execution of work and as such in view of terms of contract, as contained in condition no. 24.1 of terms of contract, it was incumbent upon authority to refer before Dispute Redressal Committee for adjudication of dispute but having not done so authorities have failed to discharge their contractual obligation as has been arrived at between parties and to that effect specific stand has been taken of counter affidavit - In view of such stand having been taken by respondents, this Court is of view that application, which has been submitted by petitioner is required to be referred before competent authority in terms of contract as contained in condition no. 24.1 of terms of contract – Appeal Disposed Of.

ORDER :

This writ petition is under Article 226 of the Constitution of India for quashing of the order as contained in Ref. No. 133017/PMGSY/1593 dated 29.01.2016 passed by Zonal Manager, National Project Construction Corporation Limited-respondent no. 2, whereby and whereunder the Agreement No. NPCC/J20/PMGSY/Agg/146 dated 04.03.2014 executed between the petitioner and NPCC has been terminated and performance security deposited has been forfeited and petitioner has been blacklisted and debarred from further participation in any tender of M/s NPCC Limited for three years from the date of issuance of the letter.

2. It is the case of the petitioner that pursuant to the Notice Inviting Tender, the petitioner participated in the tender process for consideration of his candidature for execution of work, in which, he has been found successful and accordingly, work has been allotted in his favour in terms thereof, letter of acceptance has been issued and agreement has been executed in between the petitioner and the respondents. Thereafter, the petitioner has started execution of the work but in course of its execution, hindrance has come from the anti-social element, the terrorist group of P.L.F.I, which resulted even into death of the brother of the petitioner and one local people, who has been engaged to look after the work, which led the petitioner to represent before the authority vide application dated 22.04.2015 stating therein the entire fact with a request for closure of the contract, disbursement of the money to the extent as per the execution of the work as also for refund of the earnest money but according to the petitioner instead of taking decision thereupon the authorities has come out with an order by which, forfeiture of the earnest money has been ordered. Apart from that the petitioner has been blacklisted for a period of three years vide order dated 29.01.2016 (Annexure 5).

3. Learned counsel for the petitioner by referring to Condition No. 24 of the terms of the contract, which contains a condition about 'Dispute Redressal System' and as such when the petitioner has made a request for closure of the contract showing therein the reason about non-execution of the work, the said grievance has to be referred before the 'Dispute Redressal System' before taking such decision but having not done so, the respondents-authorities have violated the terms of the contract, which equally is binding upon the respondents-authorities.

4. Further submission has been made that the order of blacklisting has been passed without issuance of any notice and even for blacklisting a period three years, issuance of show cause is necessary because blacklisting castes a stigma upon the person against whom the order of blacklisting is being passed.

5. Mr. Sarvesh Kumar Verma, learned counsel for the respondents by putting reliance upon the averments made in the counter affidavit filed on their behalf has raised the issue of maintainability of the writ petition in view of availability of Dispute Redressal System and to that effect specific stand has been taken at paragraph 9 of the counter affidavit, which reads as under:

“9.That in the light of the provision in contract agreement this writ petition is not maintainable before this Hon'ble Court and the writ petition may kindly be dismissed with direction to the petitioner to approach before the empowered standing committee for redressal of his grievance and the Dispute Redressal Committee will consider the matter objectively and the writ petition may kindly be dismissed accordingly because the petitioner has not approached the authority in terms of the agreement.”

6. He further submits that the order of blacklisting since was for a period of three years and the said period of three has already crossed, therefore, the order of blacklisting has lost its force.

7. In response, learned counsel for the petitioner has submitted that so far as the issue of blacklisting is concerned, he has been instructed that

Click Here to Read the rest of this document