IN THE HIGH COURT OF JHARKHAND AT RANCHI
SANJAYA KUMAR MISHRA, ANANDA SEN, JJ.
Amalgam Steel and Power Limited – Petitioner
Versus
Central Coalfields Limited (CCL) – Respondent
W.P. (C) No. 410 of 2022
Decided On : 20-12-2023
Forfeiture - Bid Security - IBC, 2016 - Section 7 - Fuel Supply Agreement - Clause 5.2.1(d) - Scheme - Auction - Resolution Plan - Change of Name/Control - Loss - Forfeiture of Bid Security - Refund
Fact of the Case:
The petitioner sought to quash the forfeiture of bid security and refund the deposit. The respondent forfeited the bid security deposited by the company under insolvency resolution, citing change of name/control and outstanding dues. The petitioner argued that no claim survived after the resolution plan approval and challenged the forfeiture. The respondent contended that the forfeiture was as per the scheme and the petitioner was allowed to participate in future auctions.
Finding of the Court:
The court found that the change of name/control was not intimated to the respondent, leading to the forfeiture as per the scheme. The court noted that the bid security was forfeited at the pre-contract stage and the petitioner did not contest the forfeiture. The court also observed that the bid security amount was not included in the approved Resolution Plan, thus the petitioner cannot claim a refund.
Issues: The issues involved the validity of bid security forfeiture, the impact of insolvency resolution on outstanding dues, and the applicability of the scheme's clause on change of name/control.
Ratio Decidendi: The court relied on the IBC provisions and relevant case law to establish that once a resolution plan is approved, claims not part of the plan stand extinguished. The court also emphasized that the bid security forfeiture was a consequence of default as per the bid document and did not require proof of loss.
Final Decision: The court dismissed the writ petition, finding no merit in the challenge to the forfeiture and refund of bid security, with no orders as to costs.
JUDGMENT :
1. In this writ petition, the petitioner has prayed to quash the part of letter as contained in Ref. CCL/HQ/C-4/FSA/2021-22/1628 dated 23.8.2021, whereby the bid security deposited by the then Adhunik Alloys and Power Limited was forfeited after cancelling the linkage. A further prayer has been made to refund the deposit of Rs. 59,50,000/-.
2. Learned counsel appearing on behalf of the petitioner submitted that on the facts of this case, the respondents could not have forfeited the bid security. He further submitted that the bid security was deposited with the respondent-M/s Central Coalfields Limited (hereinafter to be referred as ‘CCL’) through the auction provider namely, MSTC by the Adhunik Alloys and Power Limited (hereinafter to be referred as ‘AAPL’) through the Resolution Professional as the said company AAPL was under the Insolvency Resolution Process. When admittedly the respondent CCL did not raise any claim with the Resolution Professional in regard to any outstanding demand which they could not have made in relation with M/s AAPL, now they could not forfeit the security nor could adjust any dues. He further submitted that since none of the dues of AAPL payable to CCL was not a part of the resolution plan on the date of approval of such plan, no claim would survive, thus the forfeiture of security is absolutely bad. Learned counsel argued that the respondents have in fact not suffered any loss in the entire transaction as admittedly the letter of intent was not also issued in favour of M/s AAPL, thus in absence of any loss, the bid security could not have been forfeited. As per the petitioner, the change of name/control was not voluntary or unilateral action of M/s AAPL rather the same happened after conclusion of the process of resolution under IBC, thus the respondent could not have invoked the clause under the Fuel Supply Agreement and the scheme framed for that purpose to forfeit the security deposit.
3. Learned counsel appearing on behalf of the respondent-CCL submitted that as per the auction notice and the scheme, in the event of change of name/control of the successful bidder, the rights and relation to the allocated quantity of coal was permissible with the prior approval of the subsidiary coal company i.e. Central Coalfields Limited. Later the same was modified and it was made mandatory to give intimation to the coal company about the change of control/name. He submitted that admittedly in the instant case, no intimation was given to M/s CCL about the change of name/control of the Company. He further argues that due to misrepresentation made by M/s Adhunik Alloys and Power Limited (AAPL) huge amount of Rs.13.46 fell due and became recoverable from the said company under the Coal Supply Agreement but the said company M/s AAPL did not turn up for payment of such dues, thus supply of coal was discontinued and the existing Bank Guarantee of M/s AAPL towards security deposit stood revoked. The demand which was made by M/s CCL, was challenged by the said Company in writ petition being W.P. (L) No. 4178 of 2016 which was ultimately withdrawn on 23.12.2021. The pendency of the proceeding under the Insolvency and Bankruptcy Code, 2016 was not initially known to the respondent. When the respondent came to know about the matter, they approached the Resolution Professional, who expressed his inability to entertain such claim. In fact, only on 24.10.2018, the respondent came to know about the said insolvency proceeding. On 27.9.2019, when the respondent enquired about the status of the proceeding, the petitioner, herein, informed that they had taken over the Company and the name and control of the Company has changed as M/s Amalgam Steel and Private Limited with effect from 16.8.2019. He also submitted that as per Clause 5.2 of the Scheme, the change of name/control of the successful bidder and/or any transfer of the specified End Use Plant along with a right in relation to allocated quantity was permissible o
Ghanshyam Mishra and Sons (P) Ltd. vs. Edelweiss Asset Reconstruction Co. Ltd. (2021) 9 SCC 657
National Thermal Power Corporation Limited vs. Ashok Kumar Singh and Others
Forfeiture of bid security must be explicitly stipulated in the contract terms, and failure to bid higher does not equate to withdrawal from the bidding process.
The action of forfeiture was clearly ultra vires, manifestly arbitrary and thus cannot be sustained.
Forfeiture of earnest money must be reasonable, just, and based on actual loss suffered. The manner of cancellation and forfeiture should be fair and equitable.
The forfeiture of the deposit by the Committee of Creditors was lawful and justified under the provisions of the Insolvency and Bankruptcy Code, 2016, due to the appellant's failure to comply with th....
The specific clauses of the contract and the completion certificate played a pivotal role in determining the appellant's right to refund the security deposit, while highlighting the Corporation's fai....
A successful bidder cannot be penalized for inadvertent documentation errors, and forfeiture of earnest money requires proof of intent to mislead, reflecting principles of natural justice.
The main legal point established in the judgment is that the arbitrator's decision must be in accordance with the terms of the agreement, and failure to do so can result in the decision being set asi....
The failure of a successful bidder to pay the balance auction price in a timely manner allows the Liquidator to forfeit the Earnest Money Deposit as per the terms of the auction process.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.