High Court of Judicature at Madras
THE HONOURABLE MRS. JUSTICE CHITRA VENKATARAMAN
The Superintending Engineer Dharmapuri Electricity Distribution Circle Dharmapuri
Versus
Meenakshmi Udyog India (P) Ltd & Another
W.P.No.6199 of 2007 and MP.Nos.1 and 2 of 2007
Decided On : 14-08-2007
Electricity Tariff Dispute - Electricity Act 2003 - Section 82, Section 42(5), Section 42(6), Section 42(7), Regulation 16, Regulation 17, Regulation 18, Regulation 20, Regulation 21, Regulation 22 - The court discussed the dispute regarding the application of electricity tariff and the jurisdiction of the Ombudsman under the Electricity Act 2003 and the Regulations for Consumer Grievance Redressal Forum and Electricity Ombudsman, 2004. The court upheld the jurisdiction of the Ombudsman to pass an award as an arbitrator and dismissed the writ petition.
Fact of the Case:
The petitioner, a Superintending Engineer, challenged the order passed by the Tamilnadu Electricity Ombudsman, regarding the application of electricity tariff and the Ombudsman's jurisdiction under the Electricity Act 2003.
Finding of the Court:
The court upheld the jurisdiction of the Ombudsman under the Electricity Act 2003 and the Regulations for Consumer Grievance Redressal Forum and Electricity Ombudsman, 2004, to pass an award as an arbitrator.
Issues: The issues involved the application of electricity tariff and the Ombudsman's authority to settle disputes and pass awards.
Ratio Decidendi: The court held that the Ombudsman has the authority to pass an award as an arbitrator under the Regulations for Consumer Grievance Redressal Forum and Electricity Ombudsman, 2004.
Final Decision: The writ petition was dismissed, and the court upheld the jurisdiction of the Ombudsman to pass an award as an arbitrator.
This writ petition is filed by the Superintending Engineer, Dharmapuri Electricity Distribution Circle, Dharmapuri challenging the order passed by the second respondent viz., Tamilnadu Electricity Ombudsman, Chennai dated 11. 2006 in O.P.No.13 of 2006, quash the same and direct the first respondent to levy consumption charges under Tariff III from the date of service connection till the date of first meter reading.
2. The first respondent herein is having a mini-steel plant having two electric induction furnaces involved in the manufacture of steel ingots and applied for a service connection. The service connection with a sanctioned load of 5500 KVA at 33 KV was established and the supply was availed on 6. 2006 for industrial purpose. It is stated by the first respondent herein that it is a high-tension consumption service connection under the petitioner. The first respondent started the industrial activity by using electric furnace for the production of steel ingots on the same day. On 26. 2005 the petitioner issued bill for consumption of electricity charges for the month of June 2005 under HT Tariff-III cover instead of HT Tariff-I. The first respondent represented to the petitioner to charge them under HT tariff-I as specified under tariff order dated 13. 2003 by the Tamil Nadu Electricity Regulatory Commission constituted under Section 82 of the Electricity Act 2003. After considering the request, the petitioner revised the first bill for the month of June 2005 to HT tariff I and adjusted the excess amount collected in July 2005 consumption bill. However, the Superintending Engineer reversed his decision by letter dated 12. 2005 demanding the first respondent to pay June 2005 consumption charges being first bill under HT tariff III, that the initial bill has to be billed only under tariff III, even though the industrial activities started well before the first reading was recorded. The first respondent appealed to the Superintending Engineer on 112. 2005, he being the Chairman of the Consumer Grievance Redressal Forum constituted under Section 42(5) of the Electricity Act, 2003. The first respondent contended that the revision of the bill from HT tariff I to HT tariff III was against tariff notification issued by the Regulatory Commission. Further the demand made after a lapse of six months was in violation of principle of natural justice. The first respondent alleged that it was not given an opportunity to lodge their objections. Considering the fact that no relief was granted, on 16. 2006, the first respondent was directed to pay the amount refunded on the ground that the first respondent did not attend the enquiry on 16. 2006, but the notice of which according to the respondent was received only on 16. 2006.
.3. Aggrieved by the orders of the petitioner herein, the first respondent filed an appeal before the second respondent Ombudsman created under Section 42(6) of the Electricity Act 2003. The petitioner also filed its written statement stating that HT tariff I is applicable only from the date of first meter reading after commencement of the industrial activities and not from the date of service connection. The petitioner also submitted that the first respondent was charged under HT tariff III from the date of service connection and change of tariff from HT III to I was done only from the date of first meter reading since commencement of the industrial activity could be verified physically only by the Field Officers. It was also stated that in the tariff order of TNERC/Supply Code and tariff G.Os issued by the Government of Tamil Nadu there was no specific direction with regard to the date from which corresponding HT-I tariff is to be adopted for HT service connections. Defending the action to charge HT tariff-III, the petitioner prayed for rejection of the complaint.
4. By order dated 11. 2006, the Ombudsman constituted under the Act passed orders restoring the earlier decision dated 17. 2005 wherei
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.