2008 Supreme(Mad) 3548

High Court of Judicature at Madras
THE HONOURABLE MR. JUSTICE F.M. IBRAHIM KALIFULLA
The Chairman, Chennai Port Trust, Chennai
Versus
The Presiding Officer, Central Government Industrial Tribunal cum Labour Court & Others
W.P.No.32755 of 2005
Decided on: 25-09-2008

Important Points

The judgment establishes the importance of documentary evidence, emphasizes the limitations of tribunals in re-writing scheme provisions, and highlights the need for adherence to the eligibility criteria outlined in relevant acts and schemes.

Subject

Industrial Dispute Resolution - Employment Dispute

Act Referred

INDUSTRIAL DISPUTES ACT : .
UNREGISTERED DOCK GENERAL POOL WORKERS REGULATION OF EMPLOYMENT SCHEME : .

Headnote

Chennai Port Trust - Industrial Dispute - Dock Workers (Regulation of Employment) Act, 1948, Industrial Disputes Act, 1947, Dock Workers (Regulation of Employment) (Inapplicability to Major Ports) Act, 1997 - 1956, 1957, 1988, 1997 - The judgment discusses the application of various schemes and acts including the Dock Workers (Regulation of Employment) Act, 1948, Industrial Disputes Act, 1947, and Dock Workers (Regulation of Employment) (Inapplicability to Major Ports) Act, 1997 in the context of an industrial dispute between Chennai Port Trust and an ex-employee of a Stevedoring Company. The court analyzes the eligibility criteria, transfer provisions, and the interpretation of relevant clauses in the 1988 Scheme, and the subsequent settlement dated 25.05.2001. The judgment emphasizes the importance of documentary evidence and the limitations of the tribunal in re-writing scheme provisions.

Fact of the Case:

The case involves an industrial dispute between Chennai Port Trust and an ex-employee of a Stevedoring Company. The employee claimed that he should have been absorbed by the Port Trust under a settlement, while the Port Trust contended that he was not eligible based on the relevant schemes and acts.

Finding of the Court:

The court found that the employee failed to establish his eligibility as a List A employee under the 1988 Scheme and that the tribunal's decision to include his name in List A was not permissible. The court emphasized the importance of documentary evidence and held that the tribunal's reliance on oral evidence was unfounded.

Issues: The issues revolved around the eligibility of the employee for inclusion in List A under the 1988 Scheme, the interpretation of relevant clauses, and the permissibility of the tribunal's decision.

Ratio Decidendi: The court emphasized the importance of documentary evidence, highlighted the limitations of the tribunal in re-writing scheme provisions, and held that the tribunal's reliance on oral evidence was unfounded.

Final Decision: The court set aside the tribunal's decision and allowed the writ petition filed by Chennai Port Trust.

Advocates Appeared:
For the Petitioner:G. Venkatraman, Advocate.
For the Respondents:R2, M. Sriram, R3, V. Sudhakar, Advocates.

Judgment :-

1. The Chennai Port Trust is the petitioner. The challenge is to the award of the Central Government Industrial Tribunal-cum-Labour Court, Chennai dated 22.05.2005 passed in I.D.No.35 of 2003. The issue which came up for consideration before the first respondent-Tribunal by way of the order of the Central Government, Ministry of Labour dated 24.02.2003 reads as under:

"Whether the non-employment of Shri V.Durai, an ex-employee of M/s. K.P.V. Shaik Mohammed Rowthar Co. Ltd., Steverdoring Agent by the Chennai Port Trust is justified and if not, to what relief the workman is entitled to?"

2. The brief facts which are required to be set out are that originally the operation in the dock of Chennai Port Trust was said to have been handled by the Dock Labour Board. The Dock Labour Board in turn was recognizing such labour through Stevedores and Clearing and Forwarding Agents. The operation and handling of such labour were originally covered by two schemes, known as Madras Dock Workers (Regulation of Employment) Scheme, 1956, otherwise called as "Registered Scheme" and the Madras Unregistered Dock Workers (Regulation of Employment) Scheme, 1957. Both the Schemes were framed under the purview of Dock Workers (Regulation of Employment) Act, 1948. By virtue of the operation of the Schemes, there were two systems of workers, one by way of General Pool workers maintained by the Dock Labour Board itself and the other called privately maintained pool workers under settlement reached under section 12(3) of the Industrial Disputes Act. Since the workers of the Stevedores Association and Clearing and Forwarding Agents were clamouring for employment by the Dock Labour Board, such a demand was considered by the Central Government and a Scheme came into effect in the year 1988 known as Madras Unregistered Dock General Pool Workers (Regulation of Employment) Scheme, 1988. Under Clauses 16 to 22 of the said 1988 Scheme, the manner in which such general pool workers maintained by the Dock Labour Board and the pool of workers privately maintained by the Stevedores and Clearing and Forwarding Agents was elaborately set out. Under the said 1988 scheme, 2 lists namely List A and List B came to be prepared and the benefit of the Scheme was made applicable only to such of those persons whose names find a place in either List A or List B and none else. Subsequent to coming into force of 1988 Scheme, there was yet another development, by which, the Dock Workers (Regulation of Employment) (Inapplicability to Major Ports) Act, 1997 (Act 31 of 1997), came into being and by virtue of the said 1997 Act, the system of Dock Labour Board itself was abolished. Subsequently, there was a settlement dated 25.05.2001, reached between various Unions representing the employees of Madras Dock Labour Board with Chennai Port Trust under section 12(3) of the Industrial Disputes Act, 1947. Under Clause 28 of the said settlement, the Management of Chennai Port Trust agreed to take nine left out employees of List A and five other left out employees of List B as the employees of Chennai Port Trust.

3. It is in the above stated background, the second respondent herein raised the present Industrial Dispute, which went before the first respondent-Tribunal for adjudication as I.D.No.35 of 2003, wherein the terms of reference as extracted earlier came to be referred for consideration.

4. The second respondent in his claim statement before the first respondent-Tribunal contended that he was employed in the third respondent-Stevedoring Company as Supervisor, that, his name was omitted to be included in List A like that of nine other left out employees of List A, who came to be absorbed by the Chennai Port Trust under the settlement dated 25.05.2001, that the second respondent herein ought to have been absorbed in the petitioner-Port Trust, and therefore necessary direction should be issued by the first respondent-Tribunal to the petitioner-Port Trust to that effect. While cla




































1
2
3
4
5
6
7
8
9
10