2011 Supreme(Mad) 2382

2011 (6) MLJ 21
High Court of Judicature at Madras
K. VENKATARAMAN
M/s. Hindustan Steel Works Construction Limited, rep. by its General Manager V.C.S. Prasad
Versus
Govt. of Tamil Nadu rep. by its Project Director, Tamil Nadu Road Sector Project & Others
Original Petition No.122 of 2010
Decided On: 27-04-2011

Important Points

The main legal point established in the judgment is that the petitioner intentionally waived its right to seek a reference to the Adjudicator and that the claims made by the petitioner were factually incorrect and not entitled to any interference.

Subject

Arbitration Law - Refund of Liquidated Damages

Act Referred

ARBITRATION AND CONCILIATION ACT : S.34
CONSTITUTION OF INDIA : Art.14
CONTRACT ACT : S.23

Headnote

Arbitration - Refund of Liquidated Damages - Clauses 24 and 25 - Summary: The court rejected the claim for refund of liquidated damages as the petitioner intentionally waived its right to seek a reference to the Adjudicator. The court also found that the petitioner's claim for refund of liquidated damages was factually incorrect and not entitled to any interference.

Fact of the Case:

The petitioner entered into an agreement for road maintenance work, but the work was delayed. The petitioner's claims for refund of liquidated damages, compensation for delayed issue of Project Authority Certificate, price variation, loss of profit, and overheads were rejected by the Arbitral Tribunal.

Finding of the Court:

The court found that the petitioner intentionally waived its right to seek a reference to the Adjudicator and that the claims made by the petitioner were factually incorrect and not entitled to any interference.

Issues: The issues involved the petitioner's claims for refund of liquidated damages, compensation for delayed issue of Project Authority Certificate, price variation, and loss of profit and overheads.

Ratio Decidendi: The court held that the petitioner intentionally waived its right to seek a reference to the Adjudicator and that the claims made by the petitioner were factually incorrect and not entitled to any interference.

Final Decision: The court rejected the petitioner's claims and upheld the award passed by the Arbitral Tribunal.

Advocates Appeared:
For the Petitioner:M.D. Subramanian, Advocate.
For the Respondent: R1 - Bhavani Subbarayan, Special Government Pleader.

Judgment :-

1. The present Original Petition is filed seeking to set aside the award passed by the Arbitral Tribunal dated 11.11.2009.

2. The claimant before the learned Arbitrators is the petitioner herein.

3. The facts of the case, in nutshell, are set out hereunder:

The petitioner herein had entered into an agreement with the first respondent on 03.09.2004 for the work of Enhanced Periodical Maintenance of Government Roads in Salem and Karur District. As per the said agreement, the petitioner has to complete the work within 12 months from the date of handing over the sites. The site was handed over on 29.09.2004. The targeted date of completion was on 28.09.2005. However, the work was completed only on 15.09.2007. The reason for the delay in starting the work was, to approve the revised level, the first respondent and his officials have taken time nearly five months. The exorbitant price-hike outside the control of the employer as well as contractor has resulted in frustration of the contract and for other reasons. Without considering the same, the first respondent's Engineer has levied the liquidated damages in two spells. Hence, the petitioner has preferred the claim before the first respondent, which is set out hereunder:

(a) Refund of Rs.32,72,500/- was required, since it was recovered as liquidated damages illegally.

(b) A sum of Rs.86,67,055/- was asked for compensation due to the delay in issue of Project Authority Certificate.

(c) A sum of Rs.6,25,15,934/- for the price variation and difference in cost between the agreement rate and market rate spent by the petitioner during the execution of the work due to price hike.

(d) A sum of Rs.4,72,79,191/- towards loss of profit and overheads due to prolongation of contract.

Before the learned Arbitration Tribunal, the petitioner has raised those claims. However, the claim has been rejected in toto by the learned Arbitrators and hence, the petitioner has come up with the present Original Petition challenging the said award under Section 34 of the Arbitration and Conciliation Act, 1996.

4. The learned counsel appearing for the petitioner fairly submitted that in respect of the work carried out at Karur District, absolutely there is no dispute and there are disputes only with regard to the work carried out in Salem District.

5. The first and foremost submission that was made by the learned counsel appearing for the petitioner is that as per various clauses in the agreement, the petitioner has followed the procedure for referring the matter to the Adjudicator. But, however, there was no response on the side of the first respondent and hence, the petitioner was not in a position to follow the Dispute Resolution Mechanism. However, this vital aspect has been overlooked by the Arbitral Tribunal while passing the award. Keeping in mind the said submission made by the learned counsel appearing for the petitioner, it has to be seen whether the claims made by the petitioner have been considered by the Arbitrators in proper perspective.

6. Claim No.1 – Refund of Liquidated Damages (LD) levied by the first respondent.

(a) Before adverting to the claim made in this regard, the preliminary objections raised by the first respondent have to be considered. According to the first respondent, the contract between the parties envisages a reference to Adjudicator and the petitioner has not followed the adjudication mechanism.

(b) Before adverting to the said contention, it will be useful to extract the relevant clause in the agreement, viz., Clauses 24 and 25, which are reproduced hereunder:

"24. Disputes

24.1. If the Contractor believes that a decision taken by the Engineer was either outside the authority given to the Engineer by the Contract or that the decision was wrongly taken, the decision shall be referred to the Adjudicator within 14 days of the notification of the Engineer's decision.

25. Procedure for Disputes

25.1 The Adjudicator shall give a decision in writing within 28 days of receipt




































1
2
3
4
5
6
7
8
9
10
11