2011 Supreme(Mad) 3867

High Court of Judicature at Madras
K. CHANDRU
Ramakrishna Engineering Company rep. by Managing Partner Dhinoo Gopalakrishnan
Versus
The State Industries Promotion Corporation of Tamil Nadu, rep. by Chairman and Managing
W.P.No.2022 of 2009
Decided on : 08-09-2011

Important Points

Disputes arising from contractual terms and breaches should be settled by the principles of contract law and not through writ petitions under Article 226 of the Constitution of India.

Subject

Civil Law - Contract Law

Headnote

Land Allotment - Lease Conditions - [Kerala State Electricity Board v. Kurien E.Kalathil, AIR 2000 SC 2573 : [2000] 6 SCC 293, State of Bihar v. Jain Plastics and Chemicals Ltd., AIR 2002 SC 206 : [2002] 1 SCC 216, U.P. Financial Corporation v. Gem Cap (India) Private Limited and others, [1993] 2 SCC 299] - The court dismissed the writ petition challenging the order to resume unutilized land, emphasizing that the transaction was purely contractual and the contractual conditions had been violated. The court cited precedents to establish that disputes arising from contractual terms and breaches should be settled by the principles of contract law and not through writ petitions under Article 226 of the Constitution of India.

Fact of the Case:

The petitioner, an allottee of a plot in an industrial park, challenged an order to resume unutilized land. The petitioner failed to comply with the conditions of lease, leading to the order for resumption of the unutilized portion of the land.

Finding of the Court:

The court found that the transaction between the petitioner and the respondent was purely contractual and the contractual conditions had been violated. The court declined to entertain the writ petition to extend or modify the lease conditions based on the difficulties pleaded by the petitioner.

Issues: Violation of lease conditions, challenge to the order to resume unutilized land, and the applicability of contractual principles in resolving disputes.

Ratio Decidendi: The court emphasized that disputes arising from contractual terms and breaches should be settled by the principles of contract law and not through writ petitions under Article 226 of the Constitution of India.

Final Decision: The court dismissed the writ petition and extended the time for the petitioner to file an explanation.

Advocates appeared:
For the Petitioner:Srinath Sridevan, Advocate.
For the Respondent:Narmadha Sampath, Advocate.

Judgment :-

1. The petitioner was an allottee of a developed plot in the SIPCOT Industrial Park at Irungattukottai. The petitioner was allotted Plot No.A1 (Part) to the extent of 4 Acres. In this writ petition, the petitioner has challenged an order dated 13.1.2009 issued by the respondent/SIPCOT, wherein they have indicated their intention to resume the unutilised portion of the land to the extent of 2 Acres. It was stated that under the conditions of allotment and in paragraph 14(1) of the Lease Deed it was stipulated that if the plot allotted to the allottee is not fully utilised, then there is no impediment for the respondent/SIPCOT to resume the land and it was found that the petitioner had not constructed in the area which is allotted to it as per the conditions of lease.

2. As per the conditions of lease which is appended in the typed set, it is stipulated that non compliance of the terms and conditions of the allotment will result in cancellation of the lease, including claiming of amount paid towards plot and interest already paid. One of the conditions that is set out is that the allottee should put to use the land for the purpose for which it was allotted and if it is in excess of the actual requirement than the purpose for which it is allotted, the respondent/ SIPCOT can, at any time, cancel the allotment. It is also stated that the construction of the building will have to be commenced within six months from the date of the allotment order and should be completed within 24 months from the date of the allotment.

3. The lease was executed in favour of the petitioner on 5.12.2003, pursuant to the allotment order made on 26.8.2003. Thereafter, after waiting for five years, a notice dated 31.1.2008 was issued to the petitioner and in that notice the petitioner was informed that the petitioner has violated condition No.6(a) of the allotment order and condition No.14(1) of the lease deed and since the land was not put to use for the purpose for which it was allotted and it was also found to be excess of the actual requirement, they have right to cancel the allotment in respect of the land which was not utilized. The petitioner was asked to show cause on the same.

4. The petitioner sent a reply dated 15.5.2008 stating that they need the entire land and they have also finalized their expansion plan for the next two/three years and they also require six to eight months for completing the work. They also sent further representation dated 11.6.2008 indicating that they have further period of two years for completing the construction process.

5. In the meanwhile, the respondent/SIPCOT, by communication dated 12.6.2008, found that since the original condition was not complied with, they propose to resume the unutilised portion of land allotted to them. It is pursuant to the said warning the impugned order came to be passed on 13.1.2009. In the impugned order, it is stated that even after ninety days time was given for compliance of defects by the proceedings of the respondent dated 28.3.2008, the petitioner had not complied with the same and it is also stated that on inspection made by the respondent, it was found that they have not even commenced civil works in the site and therefore, they were directed to show cause as to why allotment should not be cancelled. Challenging the said show cause notice, the writ petition came to be filed.

6. The writ petition was admitted on 2.2.2009. Pending the writ petition, interim stay was granted. On notice from this Court, the respondent/SIPCOT is represented by Ms.Narmada Sampath, learned counsel. Today when the matter came up, the learned counsel for the petitioner produced further documents showing that they had made application for building approval on 21.5.2008 and they have also paid the infrastructure and amenities charges and official plan approval was also obtained. But these conditions will not improve the case of the petitioner. In any event, if the petitioner has a good case, they