IN THE HIGH COURT OF MARAS
Spencer
Edmund Bendit
Versus
Edgar Raphael Prudhomme
Decided On : 2 November, 1924
Force Majeure - Contractual Dispute - Indian Contract Act, Section 56 and 65
Fact of the Case:
The respondent, a merchant, contracted with the appellants to ship groundnut kernels. The vessel was commandeered by the Government, and the respondent was unable to find alternative accommodation for the cargo. The respondent pleaded force majeure, but the appellants refused to consider the contracts as cancelled. The trial court found force majeure would discharge the respondent from the contract due to inability to obtain tonnage.
Finding of the Court:
The court found that the commandeering of the vessel was the real cause of the respondent's inability to perform the contract, and the force majeure clause applied. The respondent's inability to procure tonnage was not force majeure, but a contributing cause to make the commandeering the effective cause of non-performance.
Issues: The main issue was whether the commandeering of the vessel constituted force majeure and the respondent's inability to obtain tonnage was a contributing cause to the non-performance of the contract.
Ratio Decidendi: The court held that the force majeure clause applied as the commandeering of the vessel was the real cause of non-performance. The respondent's inability to procure tonnage was not force majeure, but a contributing cause to make the commandeering the effective cause of non-performance.
Final Decision: The judgment appealed against was upheld, and the appeal was dismissed with costs.
Spencer, J.
1. The respondent, a merchant of Madras, contracted on 10th November, 1916, with the appellants, who are a firm in Marseilles, to ship 400 tons of groundnut kernels of Marseilles in the December January 1916-1917 season on a C.I.F. contract, the goods to be of H. P. Brand. Ha booked the necessary tonnaga on the S.S. Seapool, a vessel chartered by Messrs. Gordon Woodroffe & Co., but it was commandeered by the Government on 14th November for purposes connected with the War. In spite of his best endeavours, the respondent was unable to obtain accommodation for this cargo on any other steamer leaving the "kernel" ports, that is, ports on the Coromandel Coast from which kernels are usually shipped, viz., Madras, Pondicherry, Cuddalore, Negapatam and Porto Novo. Ha therefore wrote on 22nd December, 1916, and 11th January, 1917, to the appellants pleading force majeure and asking them to consider the contracts as cancelled. The appellants refused to do so, rejecting the plea that this was a case of force majeure and suggested trying other lines and other ports. The respondent tried all the shipping agents in vain. He then made a proposal that he should endeavour to work off old contracts by shipping a portion of the goods contracted for under old contracts along with the portions of the goods to be supplied under new contracts, but the appellants only treated this as a virtual admission of his liability and an attempt to diminish his debt. They were unwilling to accept the proposal exactly as it was offered and it fell through. There was no extension of the time for performance for an indefinite period by mutual agreement. In the end they put the respondent into Court in March, 1921, and lost their case in the Trial Court, on the findings of the Judge, (1) that force majeure would discharge the defendant from the performance of his original contract, and (2) that inability to obtain tonnage is force majeure within the meaning of that expression as construed in English Courts.
2. It may be noted in this connection that both the standard contract forms in use by the parties (Exhibits A and I) contain force majeure clauses. Exhibit I which is respondents version is the less definite of the two. It mentions two kinds of force majeure which would render the contract null and void except so far as it had already been partly performed. One is prohibition of export of the article from the country, a second is blockade, and there are others not mentioned. Such are cases of force majeure preventing the execution of the contract. Exhibit A is more explicit, as it enumerates war, revolution, strikes, epidemics as well as other unforeseen circumstances which might prevent the goods from reaching the port of embarkation or from being shipped or despatched and so would render the contract void. Section 56 of the Indian Contract Act simply says that a contract to do an act which, after the contract is made, becomes impossible, or by reason of some event which the promisor could not prevent, unlawful, becomes void when the act becomes impossible or unlawful; and Section 65 provides that in such event any person who has received any advantage under the contract is bound to compensate the person from whom he received it.
3. The term force majeure which is borrowed from the Code Napoleon has received interpretation in several decisions of the English Courts in recent years. In Matsoukis v. Priestman and Co. (1915) 1 K.B. 681 Mr. Justice Bailhache after considering the definition given by an eminent Belgian lawyer of force majeure as meaning "causes you cannot prevent and for which you are not responsible" a definition which would certainly include inability to obtain tonnage owing to war conditions prevailing in the port or ports from which the goods were to be despatched-himself gave it a more restricted meaning. In his opinion force majeure would include strikes and break-down of machinery but not bad weather, or football matches, or
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.