High Court of Judicature at Madras
THE HONOURABLE MR. JUSTICE LAKSHMANAN
V.V. Raghavan Petitioner
Versus
M/s. Madras Refineries Ltd., Madras & Another
O.P. No. 383 of 1990
Decided On :Decided on : 26-10-1989
ARBITRATION - AWARD - FILING - DELAY - CONDONATION - INTEREST - AWARDED BY ARBITRATOR - MODIFICATION - POWER OF COURT - SECTION 15 OF THE ARBITRATION ACT, 1940.
Fact of the Case:
The petitioner, Mr. Justice V.V. Raghavan, was appointed as the sole Arbitrator in regard to the disputes between the first respondent, M/s. Madras Refineries Ltd., Madras and the second respondent M/s. Sri Prasad Constructions. The first respondent filed 58 documents in support of their case and the second respondent filed 97 documents. There was no oral evidence. After elaborate enquiry, the Arbitrator made an award on 15.4.1984 directing the first respondent M/s. Madras Refineries Ltd., to pay the second respondent a sum of Rs. 4,32,260/and gave a month's time for payment and further directed payment of interest at 11% per annum, the interest to run on the expiry of the one month period from the date of the award namely, by 15.5.1984. The Original Petition was presented on 29.9.1984. The matter was returned by the High Court office on 1.10.1984 and the papers were again represented on 17.11.1984. On 19.11.1984 again it was returned by the office directing the petitioners counsel Mr. K. Lakshmi Narayanan, to file a petition to condone the delay in re-presenting the petition. Though the petition was returned by the office as early as on 1941.1984, the direction made earlier by the office of the Original Side of this Court, was complied with only on 28.6.1990.
Finding of the Court:
The court held that the delay in filing the award was not attributable solely to the counsel for the arbitrator and the counsel for the second respondent, but also to the office of the Original Side of the Court. The court further held that the interest awarded by the arbitrator was just and reasonable and could not be treated as excessive or on the high side. The court also held that it had the power to grant interest in cases governed by the Interest Act, 1978, as S. 3(1)(A) of the Arbitration Act would enable it to award interest in this proceeding and also by invoking S. 29 of the Arbitration Act. The court also held that it had no power to modify the award under S. 15 of the Arbitration Act, as the first respondent had not pointed out any infirmity in the award which enabled the court to modify it.
Issues: 1. Whether the delay in filing the award was attributable solely to the counsel for the arbitrator and the counsel for the second respondent, or also to the office of the Original Side of the Court? 2. Whether the interest awarded by the arbitrator was just and reasonable? 3. Whether the court had the power to grant interest in cases governed by the Interest Act, 1978? 4. Whether the court had the power to modify the award under S. 15 of the Arbitration Act?
Ratio Decidendi: 1. The delay in filing the award was not attributable solely to the counsel for the arbitrator and the counsel for the second respondent, but also to the office of the Original Side of the Court. 2. The interest awarded by the arbitrator was just and reasonable and could not be treated as excessive or on the high side. 3. The court had the power to grant interest in cases governed by the Interest Act, 1978, as S. 3(1)(A) of the Arbitration Act would enable it to award interest in this proceeding and also by invoking S. 29 of the Arbitration Act. 4. The court had no power to modify the award under S. 15 of the Arbitration Act, as the first respondent had not pointed out any infirmity in the award which enabled the court to modify it.
Final Decision: The court passed a decree in terms of the award in favour of the second respondent.
This petition was filed by Mr. Justice V.V. Raghavan who was appointed as the sole Arbitrator in regard to the disputes between the first respondent, M/s. Madras Refineries Ltd., Madras and the second respondent M/s. Sri Prasad Constructions.
2. The first respondent M/s. Madras Refineries Ltd. is a limited Company having its office at Manali, Madras-68. The second respondent is M/s. Sri Prasad Constructions represented by its sole Proprietor Ch. Baba Prasad, having its office at No. 11, Nawab Habibullah Avenue, Nungambakkam, Madras-34.
3. The first respondent with a view to expand its activities at Manali, called for tenders for site grading work at Manali as a first step in their expansion Scheme. The second respondent was one of the eight tenderers and after negotiations the second respondents tender was accepted on 22.4.1981 and the work was to be completed within one year, i.e, within 12 months. As per the contract the work was to be done at seven places in Manali and time was made the essence of the contract, the outer limit of one year in any event was to be kept up, although for various items of work at the seven places any delay may be excused and time extended, and if not so extended under the terms of the contract, the second respondent agreed to pay compensation up to a maximum of 10% of the contract value.
4. It is stated in the petition that the second respondent committed default in execution of the contract, with a result that they had to pay compensation sought to be recovered at the maximum rate. The second respondent did not complete the work within the one year period resulting in the appointment of a substitute contractor for completing the balance of the work. Thus M/s. Madras Refineries, the first respondent, claimed Rs. 3,46,678 as compensation for delay during the period of the contract and a sum of Rs. 25,13,205/as excess payment by reason of the appointment of the substituted contractor, which was increased to Rs. 32,50,446/- by an amendment of the claim.
5. The second respondent, Sri Prasad Constructions disputed the claim of the first respondent and made a counter claim under various heads like value of, materials at site, compensation for wrongful termination of contract, etc., with the result that the Arbitration clause had to be invoked. Under the Arbitration clause, the Chairman of the first respondent, M/s. Madras Refineries Ltd. or his nominee has to decide the dispute between the parties. The first respondent in deciding the disputes between the parties, named Mr. Justice V.V. Raghavan, (Retired), who is the petitioner herein, as the Sole Arbitrator. Accordingly the petitioner also consented to act as an Arbitrator and convened the first meeting and settled the procedure and proceeded with the enquiry.
6. The first respondent filed 58 documents in support of their case and the second respondent filed
97 documents. There was no oral evidence. After elaborate enquiry, the Arbitrator made an award on 15.4.1984 directing the first respondent M/s. Madras Refineries Ltd., to pay the second respondent a sum of Rs. 4,32,260/and gave a months time for payment and further directed payment of interest at 11% per annum, the interest to run on the expiry of the one month period from the date of the award namely, by 15.5.1984. Along with the original award the petitioner had also enclosed the documents filed by the first respondent (Annexure I), documents filed by the second respondent (Annexure II), the minutes of the 51 meetings (Annexure III), and extension of time for making the award made from time to time on consent of the parties (Annexure IV). The petitioner therefore prayed this Court to receive the Award dated 15.4.1984 and to issue notices to the respondents of filing of the above award.
7. It is seen from the receiving seal of the Original Side of our Court, the Original Petition was presented on 29.9.1984. The matter was returned by the High Court office on 1.10.1984 and the papers w
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.