SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

1990 Supreme(Mad) 890

High Court of Judicature at Madras
THE HONOURABLE MR. JUSTICE A. R. LAKSHMANAN
P. Shanmugha Sundaram, Proprietor, K. Paramasiva Mudaliar
Versus
Bharat Petroleum Corporation Limited & Another
O.P. No. 15 of 1984 and O.P. No. 307 of 1984
Decided On :Decided on : 15-10-1990

Advocates Appeared:
For the Petitioner:K. Bijai Sundar, Advocate.
For the Respondent:V. Aravamudhan, Advocate.

Headnote:

ARBITRATION - EXTENSION OF TIME - JURISDICTION - ESCALATION COSTS - INTEREST - CONTRACT - FULL AND FINAL SETTLEMENT - ARBITRATION CLAUSE - AWARD - DISPUTE - CONTRACTOR - CORPORATION - ARBITRATOR - SECTION 28(1), 14(2), 17, 30 OF ARBITRATION ACT 1940 - SECTION 3(1)(A) OF INTEREST ACT 1978 - SECTION 29 OF ARBITRATION ACT 1940 - SECTION 34 OF CIVIL PROCEDURE CODE - O.P. NO. 15 OF 1984 - O.P. NO. 307 OF 1984 - CLAUSE 16 OF THE AGREEMENT - SECTION 9(B) OF THE INDIAN ARBITRATION ACT 1940 - SECTION 5 OF HUDSONS BUILDING AND ENGINEERING CONTRACTS - SECTION 33 OF THE ARBITRATION ACT - CLAUSE 8(C) OF THE CONTRACT - CENTRAL WAREHOUSING CORPORATION V. P. GUNASEKARAN AND OTHERS - EXECUTIVE ENGINEER, IRRIGATION, (GALIMALA V. ABNADUTA JENA) - HYDERABAD MUNICIPAL CORPORATION V. N. KRISHNASWAMI - P.M. PAUL V. UNION OF INDIA - METRO ELECTRIC COMPANY V. DELHI DEVELOPMENT AUTHORITY, NEW DELHI - DAMODAR VALLEY CORPORATION V. K.K. KAR - ASIA ENGINEERING COMPANY, MADURAI V. LIFE INSURANCE CORPORATION OF INDIA, BOMBAY - UNION OF INDIA V. M/S. AJIT MEHTA AND ASSOCIATES, PUNE AND OTHERS - M/S. AMAR NATH CHAND PRAKASH V. M/S. BHARAT HEAVY ELECTRICALS LIMITATED -

Fact of the Case:

Bharat Petroleum Corporation Limited (Corporation) called for tenders for the fabrication and erection of storage tanks and fabrication, welding, and laying pipelines at Warangal in Andhra Pradesh. P. Shanmugha Sundaram (Contractor) was granted the contract. The Corporation made a payment of Rs. 24,400/- on 26.2.1982 purely on sympathetic grounds. The Contractor started to raise further claims which were not covered by the agreement. The Corporation appointed an Arbitrator and sought to have the question of escalation costs referred to the decision of an Arbitrator. The Contractor appointed an Arbitrator and sought to have the question of escalation costs referred to the decision of an Arbitrator. The Arbitrator passed an Award against the Corporation for the payment of a sum of Rs. 2,28,203/- together with costs. The Corporation filed O.P. No. 307 of 1984 under Section 30 of the Indian Arbitration Act to set aside the award dated 1.11.1983 passed by the Arbitrator and for costs. The Contractor filed O.P. No. 15 of 1984 under Sections 28(1), 14(2), and 17 of the Arbitration Act of 1940 to grant extension of time with retrospective effect so as to validate the award, to direct the second respondent Arbitrator to file the award dated 1.11.1983, and to pass a decree in terms of the award together with further interest on the award amount.

Finding of the Court:

The Arbitrator had jurisdiction to entertain the reference after the payment of the final bill and the dispute was referable to arbitration. The Contractor was entitled to escalation costs. The Corporation was liable for the consequences of the delay, namely, increase in prices. The Arbitrator had jurisdiction to go into this question and in fact, the arbitrator in the said case gone into that question and has awarded as he did. The Arbitration Clause survives and even though it was brought to the notice of the Corporation, the Corporation has only sent a cryptic reply informing that the Arbitration Clause cannot be invoked. The Contractor is entitled to the interest awarded by the Arbitrator. Prior to the commencement of the Arbitration proceedings and from the date of the award to the date of the decree, interest at 16 1/2% on the amount awarded by the Arbitrator. The principal amount awarded by the Arbitrator is confirmed. But, however, the Court deleted the interest awarded by the Arbitrator for the period pendente lite and confined the interest on the principal sum awarded by the Arbitrator at 16% per annum for the period prior to the commencement of the Arbitration proceedings and from the date of the award to the date of decree and from the date of decree till realization.

Issues: 1. Whether the Contractor is entitled to escalation costs? 2. Whether the Arbitrator has jurisdiction to entertain the reference after the payment of the final bill and whether the dispute is not referable to arbitration as contended by the Corporation.

Ratio Decidendi: 1. The Arbitration Clause survives as rightly contended by the learned counsel for the contractor. As per Clause-16 of the Agreement, it contemplates the appointment of two arbitrators, one to be appointed by each party. In spite of repeated requests, the Corporation had not appointed its own arbitrator. Hence, invoking the provisions of the Indian Arbitration Act, the second respondent was declared to be the sole arbitrator after complying with the formalities as required under the Law. 2. The Arbitrator has passed the reasoned award. It is seen from the award that the Arbitrator has given ample opportunity to both parties, viz., the Contractor and the Corporation. The Arbitrator has also referred to the various claims made by the Contractor and also referred to the various letters and correspondence exchanged between the parties. In considering the question of escalation of costs, the Arbitrator has considered the justification and the reasonableness of the claims made by the Contractor and has passed the reasoned award.

Final Decision: O.P. No. 15 of 1984 is disposed of on the above terms and O.P. No. 307 of 1984 is dismissed. The matter was argued by the respective counsel in an able and effective manner. The Court placed on record its appreciation for the manner in which both the counsel have argued this case. The O.Ps. are disposed of with the cost of the Contractor/Claimant in these two O.Ps. The Court fixed the Counsel Fee for Mr. Bijai Sundar, learned Counsel for the Contractor at Rs. 2,500/-, payable by the Bharat Petroleum Corporation Limited.

Judgment :-

O.P. 15 of 1984 was filed under Sections 28(1), 14(2) and 17 of the Arbitration Act of 1940 by one P. Shanmugha Sundaram against Bharat Petroleum Corporation (a) to grant extension of time with retrospective effect so as to validate the award, (b) to direct the second respondent Arbitrator to file the award dated 1.11.1983 and (c) to pass a decree in terms of the award together with further interest on the award amount.


2. O.P. No. 307 of 1984 was filed by M/s. Bharat Petroleum Corporation Limited, Madras against the petitioner in O.P. 15 of 1984 under Section 30 of the Indian Arbitra tion Act to set aside the award dated 1.11.1983 passed by the Arbitrator and for costs.

3. The facts in brief are as follows:— Bharat Petroleum Corporation Limited, which is a Government of India Corporation is engaged in distributing Petrol and Petroleum products. For the carrying out of its function, the Bharat Petroleum Corporation Limited (in short Corporation) called for tenders for the fabrication and erection of storage tanks and fabrication, welding and laying* pipelines at Warangal in Andhra Pradesh. The petitioner in O.P. No. 15 of 1984, Mr. P. Shanmugha Sundaram was one of the ten derers and was granted the contract as outlined in an agreement entered into between the Corporation and the petitioner in O.P. 15 of 1984 (hereinafter called as Contractor) on 15th December 1979. Accord ing to the Corporation, the consideration for the work and the time to be taken for completing the same were indicated in the agreement itself and that the contractor after completing the work received his full and final payment as per the agreement and that the payment was accepted without demur by the contractor. After sometime, for reasons best known to him, the contractor raised certain demands, which according to the Corporation were not at all within the ambit of the agreement. For the claim made by the contractor, the Corporation made a payment of Rs. 24,400/on 26.2.1982 purely on sympathetic grounds. It was made clear that such payment could not be regarded as a precedents at any time in the future and that no further claim could be entertained. Despite this, the Contractor started to raise fu rther claims which according to the Corporation were not at all either considered nor covered by the agreement entered into between the parties. The Corporation was unable to accede to the request since the agreed amount had already been paid to the Contractor and paying of any further amount would only result in an unjust enrichment of the Contractor. At this juncture, the Contractor has sought to invoke the Arbitration Clause in the agreement which inter-alia covers, “any dispute or differences at any time arising between the company and the contractor touching the construction, meaning or effect of these presents or any clause or thing hereunder contained or the rights or liabilities of the company or the contractor under the presents or otherwise however in relation to the presents”. According to the Corporation, it was clearly pointed out to, the Contractor that the question of escalation costs was not in any manner referred to in the agreement and hence was totally outside the contract. Such being the case, the question of referring for Arbitration would be totally outside the purview of the agreement entered into between the parties and hence Clause-16 of the agreement, viz., the Arbitration Clause w ould have no relevance whatsoever. However, the Contractor appointed an Arbitrator and sought to have the question of escalation costs referred to the decision of an Arbitrator. However, the Corporation clearly pointed out that the work itself had been completed and the remittance under the agreement had been accepted and received by the Contractor as full and final settlement thereof. It was only after the receipt of the final settlement and after the passage of sometime and as an afterthought, the Con tractor sought to raise the question of an enh





















































Click Here to Read the rest of this document

1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top