2007 Supreme(Mad) 3274
Before the Madurai Bench of Madras High Court
THE HONOURABLE MR. JUSTICE V. RAMASUBRAMANIAN
A.Saravanan
Versus
The Executive Engineer cum Administrative Officer, Tamil Nadu Housing Board, Trichy Housing Unit, Kajamalai Colony, Tiruchirapalli & Another
W.P.(MD)Nos.6395 of 2007 to 6397 of 2007 & M.Ps.1/2007 and W.P.Nos.3864 to 3873 of 2006 and W.P.M.Ps.4068 to 4077 of 2006 and W.P.Nos.6169 to 6179 of 2006 and M.Ps.1/2006 and W.P.Nos.11366 to 11375 of 2006 & M.Ps.1 & 2/2006 and W.P.Nos.6213 to 6217 of 2006 and M.Ps.1/2006 and W.P.Nos.7333 to 7338 of 2006 and M.Ps.1/2006 and W.P.Nos.7575 to 7584 of 2006 and M.P.1/2006 W.P.Nos.7704 to 7708 of 2006 and M.P.1 of 2006
Decided On : 11-10-2007
Headnote
Interest Capitalization - Housing Scheme Allotment - Tamil Nadu Housing Board Act, 1961, Section 155 - The court held that the demand made by the respondents for capitalization of interest charges was not in conformity with the orders of allotment and the Lease Cum Sale Agreement, which form a concluded contract between the allottees and the Housing Board and which is binding on both the parties. The court also found that the Allotment Orders and the Lease Cum Sale Agreement do not provide for the allottees to be entitled to any interest for the period from the date of initial payment up to the date of handing over possession.
Fact of the Case:
The petitioners were allotted houses in a housing scheme by the Tamil Nadu Housing Board. The Housing Board demanded payment of interest on the tentative cost from the date of ready for occupation till the date of allotment, together with further interest and penal interest on the interest so capitalized. The petitioners challenged this demand through writ petitions.
Finding of the Court:
The court found that the demand for capitalization of interest charges was not in conformity with the concluded contract between the allottees and the Housing Board. The court also ruled that the allottees were not entitled to any interest for the period from the date of initial payment up to the date of handing over possession.
Issues: The main issue was the legitimacy of the demand made by the respondents for capitalization of interest charges. Additionally, the court addressed the entitlement of the allottees to interest for the period from the date of initial payment up to the date of handing over possession.
Ratio Decidendi: The court held that the demand for capitalization of interest charges was not in conformity with the concluded contract between the allottees and the Housing Board. Additionally, the court ruled that the allottees were not entitled to any interest for the period from the date of initial payment up to the date of handing over possession.
Final Decision: All the writ petitions were allowed, and the proceedings impugned in the writ petitions were set aside. No costs were awarded, and the connected miscellaneous petitions were closed.
For the Petitioner:S.K. Mani, Advocate.
For the Respondents:A. Kannan for TNHB, Advocate.
The petitioners in all these writ petitions were allotted houses in the Navalpattu Housing Scheme Phase-III, Trichy on various dates ranging from 14.10.1991 to 15.05.1998, by the Executive Engineer cum Administrative Officer, Trichy Housing Unit, Tamil Nadu Housing Board. The said scheme was part of a larger scheme promoted in three different phases by the Housing Board and there were three categories of houses namely, High Income Group (HIG), Middle Income Group (MIG) and Low Income Group (LIG), which were promoted in the said scheme. Even among those three categories, there were different types of houses, depending upon the size of the plot and the total constructed area of the building. Since these details are not relevant for the determination of the issue on hand, I do not propose to advert to them.
2. Some of the allotments which were originally under hire purchase agreements, later got converted into out-right purchases. In any case, most of the petitioners are either State Government employees or Central Government employees and there are no complaints of default in payments.
3. The possession of the individual houses were handed over to the petitioners in 1993, 1994, 1995, 1996, 1997 and 1998, depending upon the dates of allotment and the petitioners are in possession of these houses.
4. During the period from July 2005 to March 2006, the Executive Engineer cum Administrative Officer, Trichy Housing Unit issued individual communications to the petitioners calling upon the petitioners to pay different amounts of money. Aggrieved by the said demand, all these petitioners have come up with the present writ petitions. While the petitioners in 16 cases have merely sought to quash the demand made by the respondents, the petitioners in the remaining 44 cases have not only prayed for quashing the demand made, but also sought a direction to the respondents to pay interest at 8% per annum on the initial deposit made by them, from the date of the initial payment till the date of handing over possession.
5. Heard Mr.S.K.Mani, learned counsel for the petitioners and Mr.A.Kannan, learned Standing Counsel for the Tamil Nadu Housing Board.
6. It is seenfrom the counter affidavit filed by the respondents that under Phase III of the Navalpattu Neighborhood Scheme, a total of 325 houses were built by the Housing Board, out of which 63 were under the category HIG, 104 were under the category MIG and 158 under the category LIG. The size of the plots under these categories were 222.96 sq.mts., 195.05 sq.mts., 162.58 sq.mts. and 74.32 sq.mts. The built up area of the houses were 51.52 sq.mts., 73.72 sq.mts., 35.82 sq.mts., 31.08 sq.mts., 21.10 sq.mts. and 20.00 sq.mts. Therefore, the tentative cost fixed by the Housing Board was different from one category to another, depending both upon the extent of land and upon the built up area. To be specific the cost of a HIG house was Rs.1,52,800/- for one type of design, Rs.1,56,100/- for a second type of design, Rs.1,78,700 for a third type of design and Rs.1,81,900/-for the fourth type of design. The cost of a MIG house was Rs.79,600/-for one type of design, Rs.90,800/- for a second type of design and Rs.97,900/-for a third type of design. Similarly the cost of a LIG house for one type of design was Rs.45,100/- and it was Rs.46,900/- for another type of design. These statistics are furnished only for the purpose of completion of narration and they have no bearing on the issue raised in the writ petitions.
7. It is stated by the respondents in the counter affidavits that the construction of the houses were completed in 1991-92 and the tentative cost, referred to above, was fixed up to 30.06.1991. But all the houses could not be sold before 30.06.1991, as there were no takers. Therefore, the respondents were forced to issue extensive advertisements in Newspapers and ultimately the allotments came to be made in favour of persons like the petitioners herein, who applied in response to