SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2012 Supreme(Mad) 2085

2012 (2) CWC 62, 2012 (3) LW 625
High Court of Judicature at Madras
R. SUDHAKAR
Shri Sathya Sai Warehousing & Logistics Park (SSS ) Pvt.Ltd., rep.by its Director C. Nagalakshmi
Versus
The Chairman Tamil Nadu Electricity Board & Others
Writ Petition No. 11898 of 2010 & M.P.No.1 of 2010
Decided On : 26-04-2012

Advocates Appeared:
For the Petitioner:V. Parthiban for M/s. Paul & Paul, Advocates.
For the Respondents:Navaaneethakrishnan, Advocate General assisted by G. Vasudevan, Advocate.

The objection of the landowner regarding alignment is not relevant for the purpose of alignment but can only be considered with regard to compensation under Section 16 of the Telegraph Act.

Headnote:

Electricity Act - Erection of Tower Lines - Sections 164, 185(2)(b) of Electricity Act, 2003, Sections 10, 12, 16 of Indian Telegraph Act, 1885 - The court discussed the provisions of the Electricity Act, 2003 and the Indian Telegraph Act, 1885 in relation to the erection of tower lines and the power of the appropriate Government to implement the scheme for placing electrical lines for the transmission of electricity. The court emphasized that the objection of the landowner regarding alignment is not relevant for the purpose of alignment but can only be considered with regard to compensation under Section 16 of the Telegraph Act.

Fact of the Case:

The petitioner sought to quash the letter rejecting their objection to realign the transmission line and to prevent the erection of electrical towers on their lands without consent. The petitioner argued that the authorities should follow the Electricity Act, 2003 and the rules made thereunder, while the respondents contended that the Government Order granted approval for the transmission lines under Sections 68 and 164 of the Electricity Act, 2003.

Finding of the Court:

The court found that the objection of the landowner regarding alignment is not relevant for the purpose of alignment but can only be considered with regard to compensation under Section 16 of the Telegraph Act. The court held that the impugned letter, declining the request for re-alignment, was in accordance with the Government Order and scheme, and did not give cause for the writ petition.

Issues: The issues revolved around the authority's power to implement the scheme for placing electrical lines for the transmission of electricity, the relevance of the landowner's objection to alignment, and the compliance with the provisions of the Electricity Act, 2003 and the Indian Telegraph Act, 1885.

Ratio Decidendi: The court emphasized that the objection of the landowner regarding alignment is not relevant for the purpose of alignment but can only be considered with regard to compensation under Section 16 of the Telegraph Act. The court also highlighted that the impugned letter, declining the request for re-alignment, was in accordance with the Government Order and scheme, and did not give cause for the writ petition.

Final Decision: The writ petition was dismissed, and the court held that the Division Bench decision in C.RamPrakash and another vs. Power Grid Corporation of India Ltd., and another reported in (2011)8 MLJ 593 applied to the present scheme for evacuation of power by laying transmission lines in terms of Section 164 of the Electricity Act, 2003.

Judgment :-

1. The petitioner filed the present writ petition seeking for a Certiorarified Mandamus calling for the records of 2nd respondent leading to the issue of the impugned order No.SE/GCC/CNI/AEE/MM/F.LRT/D 379/10 dated 25.5.2010 and quash the same as illegal and void and consequently direct the respondents to forbear from erecting electrical towers on the petitioner's lands in Survey Numbers 292/2, 293/5, 290/1, 293/7 & 289/3B without their consent and without following the due process of law.

2. The petitioner, a private limited company, has filed this writ petition to quash the letter of the second respondent Superintending Engineer dated 25.05.2010 whereby the objection of the petitioner to realign the transmission line has been rejected by the Superintending Engineer stating that the erection of the tower lines was commenced based on the Government approval granted in G.O.Ms.No.102 Energy (C3) Department, dated 10.12.2009 as provided under Sections 68 and 164 of the Electricity Act, 2003. The Superintending Engineer also stated that the technical feasibility was considered at the time of drawing the proposal and approval of the project and therefore, deviation is not possible. It is also stated in the impugned proceedings that since the erection of the tower lines is as per approved scheme under Section 164 of the Electricity Act 2003, the petitioner should co-operate in its implementation. Challenging the said reply Mr.V.Parthiban, learned counsel appearing for the petitioner submits as follows:

For the purpose of erection of tower lines, the respondent authorities will have to follow Section 67 of the Electricity Act, 2003 and the rules made thereunder. Section 185(2)(b) of the Electricity Act, 2003 states that the provisions contained in Sections 12 and 18 of Indian Electricity Act, 1910 and the rules made thereunder shall have effect until the rules under Sections 67 to 69 of this Act are made. He also pointed out Section 12 of the Indian Electricity Act, 1910 to plead that objection has not been considered as per law. Sub-sections 1 and 2 of Section 12 of the Indian Electricity Act, 1910 reads as follows:

"12.) Provisions as to the opening and breaking up of streets, railways and tramways -

(1) Any licensee may, from time to time but subject always to the terms and conditions of his licence, within the area of supply, or, when permitted by the terms of his licence, to lay down or place electric supply-lines without the area of supply, without that area-

(a) open and break up the soil and pavement of any street, railway or tramway;

(b) open and break up any sewer, drain or tunnel in or under any street, or tramway;

(c) lay down and place electric supply-lines and other works;

(d) repair, alter or remove the same; and

(e) do all other acts necessary for the due supply of energy.

(2) Nothing contained in sub-section (1) shall be deemed to authorise or empower a licensee, without the consent of the local authority or of the (owner or occupier) concerned, as the case may be, lay down or place any electric supply-line, or other work in, through or against any building, or on, over or under any land not dedicated to public use whereon, wherever or whereunder any electric supply-line or work has not already been lawfully laid down or placed by such licensee:

Provided that any support of an (overhead line) or any stay or strut required for the sole purpose or securing in position any support of an (overhead line) may be fixed on any building or land or, having been so fixed, may be altered, notwithstanding the objection of the owner or occupier of such building or land, if the District Magistrate or, in a Presidency-town, the Commissioner of Police by order in writing so directs:

Provided also, that, if at any time the owner or occupier of any building or land on which any such support, stay or strut has been fixed shows sufficient cause, the District Magistrate or, in a Presidency-town, the Commissioner of Police






































Click Here to Read the rest of this document

1
2
3
4
5
6
7
8
9
10
11
Judicial Analysis

AI

SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top