2011 Supreme(Mad) 4679
High Court Of Madras
V.Ramasubramanian J.
Amk And Co. Rep. By Its Proprietor K.S. Mohamed Bariq - Appellant
Versus
Deputy Chief Materials Manager Golden Rock – Respondent
Writ Petition (MD) No.8856 of 2010 and M.P.(MD) Nos.1, 3 and 5 of 2010
Decided On : Dec 08,2011
Act Referred
CONTRACT ACT : S.74
SALE OF GOODS ACT : S.24, S.25(1), S.19, S.26
Headnote
GROUND RENT - Auction Sale Dispute - Conditions of lots: Lots are sold on as is where is basis and no guarantee is for size, measurement, quantity, etc. - Sale advice contained a stipulation that any ground rent likely to accrue as a result of the delay in taking delivery will be the responsibility of the purchaser - The stipulation for payment of ground rent was found to be unenforceable as it was in the nature of a penalty and the property in the goods had already passed to the buyer - The respondents were directed to permit the petitioner to cut and remove the girders and other material purchased in the auction without any obstruction
Fact of the Case:
The petitioner challenged a demand made by the first respondent for payment of ground rent and sought extension of time to take delivery of material purchased in an auction held by the respondents. The petitioner participated in the auction, became the successful bidder, and was issued a sale advice calling for remittance of the balance amount. The respondents issued delivery orders, but the petitioner faced delays in taking delivery and requested extensions without payment of ground rent. The respondents demanded ground rent, leading to the petitioner filing a writ petition challenging the demand.
Finding of the Court:
The stipulation for payment of ground rent was found to be unenforceable as it was in the nature of a penalty and the property in the goods had already passed to the buyer. The respondents were directed to permit the petitioner to cut and remove the girders and other material purchased in the auction without any obstruction.
Issues: The issues considered by the court included the enforceability of the stipulation for payment of ground rent, the passing of title to the petitioner, and the rights of the parties in relation to the material purchased in the auction.
Ratio Decidendi: The stipulation for payment of ground rent was found to be unenforceable as it was in the nature of a penalty and the property in the goods had already passed to the buyer. The respondents were directed to permit the petitioner to cut and remove the girders and other material purchased in the auction without any obstruction.
Final Decision: The writ petition was allowed, and the respondents were directed to permit the petitioner to cut and remove the girders and other material purchased in the auction without any obstruction.
C.K.Rajan, V.Radhakrishnan, S.Manohar
( 1. ) THE petitioner has come up with the above writ petition challenging a demand made by the first respondent herein for payment of ground rent, for allowing extension of time to them to take delivery of the material purchased by them in an auction held by the respondents.
( 2. ) I have heard Mr.C.K.Rajan, learned counsel for the petitioner and Mr.V.Radhakrishnan, learned senior counsel for the respondents.
The first respondent herein published an auction catalogue in their website for a public auction to be held on 19.01.2010 at the Combined Scrap Stores Depot, Golden Rock. The catalogue contained 72 items proposed to be auctioned. Each of those items was described seriatim, such as GAJ1, GAJ2, etc., upto GAJ-72.
( 3. ) LOT No.64 indicated by code word "GAJ64" was described in the catalogue as follows:
Auction LOT No. PL No. LOT Qty Sale unit No. Description -------- ------------------------------- --------- ---------- GAJ64 058300909 98032252 4.000 NUMBER LOC. AT BRIDGE NO.633 @ KM 237/6-7 IN MV-VM SECTION DESC: RELD. GIRDER THROUGH TYPE 45.720 MTRS WITH BED PLATE 16 NOS. SPAN - 4 NOS/ 448.080 MTS. LOT BASIS. NFS-1) PHOSPER BRONZE STRIP 2'.10" x 4" x 1/2" - 32 NOS (2) GI CABLE BOXES WITH HOLDING BRACKETS, (3) TELEPHONE POSTS WITH C.I. BASE. CUS: SE/BR/E/TPJ @ GOC DS-8 NO. 792138 DT, 04-10-2007. CUTTING PERMITTED TO LOADABLE SIZES.
( 4. ) THE catalogue was also available to be downloaded from the website of the first respondent and the catalogue was accompanied by "Terms and Conditions for R.M. Auction Sale". THE acronym "R.M." stood for "Released Materials". Condition No.1 of the "Terms and Conditions" stipulated that the inspection of the material was permitted prior to auction sale. Condition No.2 stipulated that the lots are sold on as is where is basis and that there was no guarantee for size, measurement, quantity, etc. Condition No.2 may be of relevance for the case on hand. THErefore, it is extracted as follows:
2. Conditions of lots: Lots are sold on as is where is basis and no guarantee is for size, measurement, quantity, etc. THE sale is strictly on the assumption that bidders have inspected the item. No complaint / claim by the purchaser will be entertained in this regard. Railway reserves rights to reduce / increase the quantity.
Condition No.9 of the "Terms and Conditions" contained the prescription relating to payment of balance sale value and delivery of lots. The relevant portion of condition No.9 presented in a tabular form, reads as follows:
SL NO SALE VALUE FREE TIME ALLOWED OTHER THAN ROLLINGFOR ROLLING STOCK NUMBER OF INSTALMENTS OF LOTS ?FOR PAYMENT OF STOCK FREE TIME FREE TIME ALLOWED PERMISSIBLE FOR AUCTION DATE BALANCE SALE ALLOWED FOR DELIVERY FOR DELIVERY RECKONED PAYMENT 11 / 01 / 2010 RECKONED FROM RECKONED FROM THE DATE FROM THE DATE OF GAH LOTS THE DATE OF AUCTION OF AUCTION INCLUDING FREE AUCTION INCLUDING TIME FOR PAYMENT OF BSV FREE TIME FOR PAYMENT OF BSV 1 Upto and including 10 days 25 days40 days 1 Rs.1,00,000/- 28 / 01 / 10 12 / 02 / 10 27 / 02 / 2010 2 Exceeding 20 days 35 days 50 days 1 Rs.1,00,000/- and 07 / 02 / 10 22 /02 / 1009 / 03 / 2010 upto Rs.2,00,000/- 3 Exceeding 20 days 50 days65 days 2 Rs.2,00,000/- 07 / 02 / 10 09 / 03 /2010 24 / 03 / 2010 4 Maximum permissible 90 days 105 days Ground rent period for taking 18 /04 / 2010 03 / 05 / 2010 0.5% per day delivery of sold lots
( 5. ) CONDITION No.12 prescribed the maximum period of delivery as 90 days from the date of auction and it also stipulated that upon failure, the EMD will be forfeited. The other clauses may not be of relevance for our present purpose. Therefore, I am not dealing with the same. But, one aspect needs to be taken note of, namely, that all the 72 items put up for auction on 19.01.2010 were described under the category of "GAJ". However, condition No.9 extracted above gave an impression as though it applied only to GAH Lots.
( 6. ) THE petitioner herein participated in the auction held on 19.01.2010 and