SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2013 Supreme(Mad) 360

High Court of Judicature at Madras
VINOD K. SHARMA, J.
Arkay Energy Ltd.
Versus
Tidel Park Ltd.
Appln.No.4804 of 2011 in C.S.No.389 of 2011
Decided on : 17-01-2013

The mandatory duty of the court to refer disputes to arbitration when an arbitration clause exists.

Headnote:

Arbitration - Power Supply Agreement - Arbitration and Conciliation Act, 1996, Section 8

Fact of the Case:

The plaintiff filed an application to refer a dispute under the Power Supply Agreement to arbitration. The defendant argued that the dispute should be referred to arbitration as per the arbitration clause in the Power Supply Agreement.

Finding of the Court:

The court found that the dispute raised by the plaintiff fell within the scope of the arbitration clause in the Power Supply Agreement and therefore should be referred to arbitration.

Issues: The main issue was whether the dispute should be referred to arbitration as per the arbitration clause in the Power Supply Agreement.

Ratio Decidendi: The court held that when an arbitration clause exists, the court has a mandatory duty to refer the dispute to arbitration, and the civil court has no jurisdiction to continue with the suit.

Final Decision: The court allowed the application and ordered the proceedings in the suit against the defendant to be stayed, referring the dispute to arbitration.

Judgment :

VINOD K..SHARMA, J.

1. The plaintiff/defendant No.1 has filed this application under Order XIV, Rule 8 of the O.S. Rules read with section 8 of Arbitration and Conciliation Act, 1996, to refer the dispute raised by the respondent No.1/plaintiff under the Power Supply Agreement, dt.10.11.2005 for adjudication by arbitration under Article 10 of the Power Supply Agreement, dated 10.11.2005.

2. M/s. Tidel Park Limited, company registered under the Companies Act, has filed the suit for declaration that M/s.Arkay Energy (Rameswaram) Limited has defaulted in the supply of contracted demand of power and is liable to pay a sum of Rs.4,85,32,773/-(Rupees four crores eighty five lakhs thirty two thousand seven hundred and seventy three only) for the quantity of power not supplied under the Power Supply Agreement, dt.10.11.2005.

3. The plaintiff/non applicant also prayed for recovery of interest on this amount. The plaintiff/non applicant has also prayed for interest @ 16% p.a. on the investment of Rs.90,00,000/- (Rupees ninety lakhs only) from 5.12.2005 with consequential direction for payment of Rs.77,79,945/- (Rupees seventy seven lakhs seventy nine thousand nine hundred and forty five only) as interest payable till 29.4.2011.

4. The plaintiff/non applicant has further prayed for Preliminary decree, that the second defendant is liable to purchase the whole of the shares of the first defendant company, i.e. applicant herein, held by the plaintiff/non applicant in terms of the Shareholders' Agreement, dated 10.11.2005.

5. It is submitted that the plaintiff/non applicant has filed the suit based on the claims falling under two separate agreements, both dt.10.11.2005 i.e. Power Supply Agreement entered into between the applicant/defendant No.1 and the plaintiff/non applicant and Tripartite Shareholders Agreement entered into between the plaintiff and the defendants.

6. It is submitted that in the Power Supply Agreement, there are only two parties, i.e. Plaintiff and the defendant No.1, whereas Shareholders' Agreement is tripartite Agreement.

7. It is also the case of the applicant/defendant No.1 that rights and obligations of the parties under these agreements are distinct and separate.

8. It is also the submission that as per the Power Supply Agreement, dated 10.11.2005, any dispute or differences arisen between the parties, is agreed to be resolved through arbitration i.e. to say that there is an arbitration clause, whereas there is no arbitration clause in the tripartite Shareholders' agreement.

9. It is submitted that under Order II Rule 3 of the Code of Civil Procedure, joinder of cause of action is permissible only if the lis between a plaintiff against the same defendant or same defendants jointly, which is not the case here.

10. That dispute under Power Supply Agreement is covered by Power Supply Agreement, dated 10.11.2005 which provides for settlement of dispute by arbitration, therefore parties should settle the dispute in accordance with the said article through arbitration.

11. On the pleading referred to above, it is prayed that the dispute raised by the plaintiff/non applicant under the Power Supply Agreement, dated 10.11.2005 be referred to arbitration in terms of Article 10 of Power Supply Agreement, dated 10.11.2005.

12. This application is opposed by the plaintiff/non applicant by pleading that M/s. Kanumuri Holdings Private Limited, defendant No.2 had requested the plaintiff to participate as one of the captive consumers in the Power plant of the applicant/defendant No.1, accordingly, the non applicant along with the applicant and the second respondent executed a Shareholders Agreement, dated 10.11.2005, thereby plaintiff has become a captive power consumer of the applicant.

13. In the Shareholders' Agreement, the defendant No.2 was described as Promoter Company and the defendant No.1 as the Implementing Company. At the relevant time, the second respondent held more than 74% of the shares in the applica

















































Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top