SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2013 Supreme(Mad) 1260

High Court of Judicature at Madras
V. RAMASUBRAMANIAN, J.
SEPCO III Electric Power Construction Corporation Represented by its Power Agent Chen Jianjun
Versus
Sterlite Energy Limited
C.P.No. 285 of 2012 & Company Application Nos. 909 of 2012 & 56 of 2013
Decided On : 07-03-2013

Advocates Appeared:
For the Petitioner: C.S. Vaidyanathan, Senior Counsel.
For the Respondent: P.S. Raman, Senior Counsel.

The main legal point established is that in a petition for winding up, the court will not order winding up if the debt is bona fide disputed and the defence is substantial, as per the test established in Madhusudan Gordhandas & Co. vs. Madhu Woollen Industries Pvt. Ltd.

Headnote:

Winding Up - Companies Act - Section 433, 434

Fact of the Case:

The petitioner sought winding up of the respondent-Company and appointment of the Official Liquidator due to non-payment of outstanding dues despite fulfilling all contractual obligations. The respondent disputed the outstanding payments and raised objections based on performance issues and arbitration clauses.

Finding of the Court:

The court found that the disputes raised by the respondent were bona fide and had substance, as they existed prior to the meeting held on 10.7.2012. The court emphasized that the refusal to pay was based on genuine disputes and the debt equity ratio was not a decisive factor in the winding up decision.

Issues: The main issues were whether the respondent had an unequivocal undeniable liability to make payment and whether the disputes raised were bona fide and had substance.

Ratio Decidendi: The court applied the test of whether the disputes were raised in good faith and had substance, as established in Madhusudan Gordhandas & Co. vs. Madhu Woollen Industries Pvt. Ltd. The court also considered the existence of disputes prior to the meeting on 10.7.2012 and the non-decisive nature of the debt equity ratio.

Final Decision: The court dismissed the Company Petition for winding up, ruling that the disputes raised by the respondent were genuine and had substance, and the debt equity ratio was not a decisive factor in the decision.

Judgment :-

1. This is a petition filed under Section 433 (e) and (f) read with Section 434 of the Companies Act, praying for the winding up of the respondent-Company and for the appointment of the Official Liquidator.

2. I have heard Mr. C.S. Vaidyanathan, learned Senior Counsel for the petitioner and Mr. P.S.Raman, learned Senior Counsel for the respondent.

3. The brief facts, as pleaded in the petition, leading to the institution of the above proceedings are as follows:-

(i) that the respondent, which was originally incorporated as a Private Limited Company under a different name and which later became a closely held Public Limited Company and a wholly owned subsidiary of a listed Company, entered into 4 separate contracts, all on the same date viz., 10.5.2006 with the petitioner herein;

(ii) that all the 4 contracts were towards the project of setting up a coal based power plant of 3,600 MW Capacity;

(iii) that the total contract price of all the 4 contracts dated 10.5.2006 was fixed at USD 943,978,215.00 and INR 15,602,886,878.00;

(iv) that as per the terms and conditions of the contracts, the petitioner not only started executing works, but also issued Performance Bank Guarantees to the total tune of USD 123,599,998.10, all of which are valid and subsisting till 31.10.2013;

(v) that the petitioner completed all its obligations under all the 4 contracts and all the 4 Units (4 x 600 MW), were set up except that the Reliability Run and Performance Guarantee Test for Unit No.4 was pending;

(vi) that all the 4 Units are complete in all respects and are already operating commercially and generating revenue, with the respondent selling power from all the 4 Units to various Government and Non-Governmental Agencies;

(vii) that despite the petitioner fulfilling and performing all their obligations, the respondent delayed payment of even the admitted milestone payments, especially after 2010;

(viii) that in several letters, the respondent duly admitted its default as well as the delay in the release of the outstanding payments;

(ix) that when a staggering amount of USD 115.03 million and INR 140.95 crores was omitted to be paid by the respondent, the petitioner issued a notice of suspension of work on 18.4.2012;

(x) that immediately the respondent sent a reply, giving a payment schedule, thereby admitting the liability;

(xi) that even by a subsequent mail dated 20.4.2012, the respondent's Director admitted and acknowledged the liability to the tune of USD 107 million and INR 140 crores;

(xii) that even while admitting and acknowledging liability under the letter dated 20.4.2012, the respondent simultaneously issued notices on the same date, viz., 20.4.2012 to the Bankers to invoke the Performance Bank Guarantees;

(xiii) that therefore, the petitioner was constrained to move applications in Arbitration Petition Nos.590-593 of 2012 on the file of the High Court of Judicature at Bombay under Section 9 of the Arbitration and Conciliation Act, 1996, challenging the invocation of the Performance Bank Guarantees;

(xiv) that the prayer of the petitioner in those applications for the grant of an ex parte order of interim injunction was rejected by a single Judge of the Bombay High Court on 23.4.2012;

(xv) that the petitioner then moved appeals before the Division Bench and obtained interim prohibitory orders restraining the Banks from making payment to the respondent in pursuance of the invocation of Guarantee;

(xvi) that immediately thereafter, the respondent issued a letter dated 24.4.2012, revoking the letter invoking Bank Guarantees;

(xvii) that consequently, the parties reached a settlement, leading to the disposal of the appeals by the Division Bench, in terms of the consent between the parties;

(xviii) that thereafter the petitioner as well as the respondent nominated the Arbitrators to resolve the disputes;

(xix) that after the parties nominated the Arbitrators, but before the Arbitrators could choose an umpire, the parties resolved t



































































































Click Here to Read the rest of this document

1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top