C.S. KARNAN, J.
P. Rajesh & Another
Versus
Chairman, Tamil Nadu Electricity Generation & Distribution Corporation & Others
W.P. No. 15810 of 2014 & M.P. No. 1 of 2014
Decided On : 17-12-2014

Advocates Appeared:
For the Petitioners:K. Sasindran for M/s. Achari & Antoni Associates, Advocates.
For the Respondents:R1 to R4, P. Gunaraj, R5, A. Kumar, Advocates.

The main legal point established in the judgment is that the insistence on a completion certificate for providing electricity service connection was unwarranted under the Electricity Act.

Headnote:

Electricity Connection - Property Dispute - Electricity Act, Town and Country Planning Act - [Electricity Act, Town and Country Planning Act]

Fact of the Case:

The petitioners sought electricity connection for a building they constructed, but the authorities insisted on a completion certificate from the planning authorities. The petitioners argued that the insistence on the completion certificate was unwarranted under the Electricity Act.

Finding of the Court:

The court found that the petitioners had obtained necessary building plans and that electricity service connection was a basic amenity for occupying the building. The court also noted that a similar case had been granted relief without insisting on the production of a No Objection Certificate.

Issues: The main issue was whether the authorities were justified in insisting on a completion certificate for providing electricity service connection.

Ratio Decidendi: The court held that the insistence on a completion certificate was unwarranted under the Electricity Act and directed the authorities to provide electricity service connection without insisting on the completion certificate.

Final Decision: The court allowed the writ petition and directed the authorities to provide electricity service connection to the building without insisting on a completion certificate.

JUDGMENT

C.S. KARNAN, J.


1. The short facts of the case are as follows:-

The petitioners submit that they are the absolute owners of the property bearing Plot No. 111, Shanti Nagar, Chrompet and comprised in Old Survey No. 453, Patta Survey No. 453/2A1A1B situated in Zamin Pallavaram Village, Alandur Taluk, Kancheepuram District, measuring an extent of 5175 sq. feet as per registered sale deed dated 14.12.2011 executed by Mohammed Sikkander and M.N. Sultan Alaudeen and registered as Document No. 8101 of 2011 on the file of Sub-Registrar, Pallavaram.

2. The first petitioner further stated that he obtained the planning permission from the Chennai Metropolitan Development Authority and obtained approved plan for putting up construction of stilt + 3 floors of residential building on 15.04.2013. Similarly, the petitioners have obtained planning permission from the local body viz. Pallavaram Municipality on 07.06.2013. Accordingly, he has completed the construction as per the approved plan. After completion of the construction, he applied for Electricity Connection to the fourth respondent in the month of December 2013 and also paid the necessary charge on 20.12.2013. However, the fourth respondent is insisting upon the production of Completion Certificate/No Objection Certificate from the planning authorities namely CMDA, the fifth respondent herein.

3. He further submits that in response to the demand of 3rd and 4th respondents for effecting service connection to the building put up, the production of completion certificate no doubt is unwarranted under the Electricity Act, he approached the fifth respondent herein along with a request for issuance of completion certificate. It is relevant to state here that there are no major violations or usage violations and floor violations with regard to the building put up. The construction put up is almost in accordance with the planning permission. However, the fifth respondent replied that they will not issue no objection without any orders from this Court. He submits that without any option the petitioners herein is seeking direction in this writ petition for considering and effecting electricity service connection for the building put up at the above said address. The entire construction for the building was over as per the approved plan and there is no deviation and there is no floor violation. The petitioner is suffering without grant of service connection as the third respondent insist upon the production of Completion Certificate/No Objection Certificate from the planning authorities namely CMDA the fifth respondent herein.

4. He submits that while considering the various orders passed by this Court in similar circumstances, the deviations are minimal and for that reason the fifth respondent should not reject the request for completion certificate. Anyhow under the provisions of Electricity Act, nowhere it is contemplated that the application for service connection should be accompanied by a completion certificate issued by the planning authority. Such being the case the insistence of the completion certificate by the respondents 1 to 4 for effecting service connection is against the principles of law and violative of provisions of the Act. The fifth respondent is always entitled to initiate any action with regard to deviations if so, as provided under the Town and Country Planning Act. He submits that the insistence of completion certificate by the respondents 1 to 4 through some resolution passed by the authorities in August 2012 on the basis of Judgment of this Court in the regularization scheme Batch is not legally valid and the same is against the provisions of Electricity Act. Even in the G.O. issued in the year 2004, the Government instructed the Electricity Board to provide Service Connection if they otherwise satisfy the Electricity Board to provide Service Connection and if they otherwise satisfy all the Rules and Regulations without insisting upon completion certificate


































































































































Click Here to Read the rest of this document

1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top