2015 Supreme(Mad) 576

HIGH COURT OF JUDICATURE AT MADRAS
P.R. SHIVAKUMAR, J.
P. Kalimuthu - Appellant
Versus
P. Karthikeyan - Respondent
C.R.P.(PD).No. 3489 of 2011 & M.P. No. 1 of 2011
Decided On : 30-01-2015

Important Points

The court has the discretion to exclude a counter-claim from proceedings if it is unrelated to the main suit and trying it separately would avoid confusion and unwieldy proceedings.

Subject

Civil Law - Civil Procedure

Act Referred

CIVIL PROCEDURE CODE : O.8 R.6(c), S.151
CONSTITUTION OF INDIA : Art.227

Headnote

Counter-claim - Exclusion from Proceedings - Order VIII Rule 6(c) - Code of Civil Procedure

Fact of the Case:

The plaintiff filed a suit for injunction against the defendant. The defendant filed a counter-claim unrelated to the plaintiff's properties. The plaintiff sought exclusion of the counter-claim from the proceedings.

Finding of the Court:

The court found that the counter-claim was unrelated to the plaintiff's properties and should be tried separately. The trial court's decision to allow the counter-claim was set aside.

Issues: Exclusion of counter-claim from proceedings under Order VIII Rule 6(c) of the Code of Civil Procedure.

Ratio Decidendi: The court has the discretion to exclude a counter-claim from proceedings if it is unrelated to the main suit and trying it separately would avoid confusion and unwieldy proceedings.

Final Decision: The revision succeeded, and the trial court's decision to allow the counter-claim was set aside. The counter-claim was directed to be numbered as a separate suit and tried separately.

Advocates Appeared:
For the Petitioner:A. Shivaji, Advocate.
For the Respondent:T. Murugamanickam, Advocate.

Judgment

1. Heard Mr. A.Shivaji, learned counsel for the revision petitioner and Mr. T.Murugamanickam, learned counsel for the respondent. The materials produced in the form of typed set of papers are also perused.

2. The plaintiff in the original suit is the petitioner in the revision. The sole defendant in the original suit is the respondent in the revision. The revision petitioner/plaintiff filed the suit O.S.No.727/2010 on the file of the Court of District Munsif, Pollachi for injunction restraining the respondent herein/defendant from interfering with the use of underground pipeline described in plaint 'B' schedule for taking water from the well in S.No.619/2B of Setthumadai Village to irrigate his land comprised in S.No.613/1A having an extent of 3.63 acres in Vettaikaranpudur village more fully described in plaint 'A' schedule.

3. The respondent herein/defendant filed a written statement resisting the prayer made by the revision petitioner/plaintiff for injunction and also making a counter-claim to the effect that the revision petitioner/plaintiff should be restrained from interfering with the right of the respondent/defendant to irrigate his land comprised in S.Nos.613/1A3, 613/4 and 614/1B2 of Vettaikaranpudur Village using the underground pipeline passing through the Government poramboke land comprised in S.No.613/1A2 and the land comprised in S.No.613/1B.

4. It is obvious that none of the above said survey numbers through which the underground pipeline of the respondent/defendant allegedly passes belongs to the revision petitioner/plaintiff. The pipeline in respect of which the respondent/defendant has made the counter-claim does not have any link or connection with the pipeline described in plaint 'B' schedule, no part of the pipeline of the respondent/defendant is stated to be passing through any of the survey fields owned by the revision petitioner/plaintiff. Under the said circumstances, the revision petitioner/plaintiff filed an application under Order VIII Rule 6(c) and Section 151 of the Code of Civil Procedure as I.A.No.741/2011 praying for the exclusion of the counter-claim made by the respondent herein/defendant.

5. The learned trial Judge, after hearing both sides, dismissed the petition holding that allowing the respondent herein to pursue the counter-claim shall avoid multiplicity of proceedings. The legality and sustainability of the said order are questioned in the present revision filed under Article 227 of the Constitution of India.

6. It is the contention of the learned counsel for the petitioner that the counter-claim has become infructuous because the licence granted by the Public Works Department, which was referred to as the basis of the claim of the respondent in the counter claim, came to be cancelled by the Public Works Department and the respondent has chosen to challenge the same before the High Court by filing a Writ Petition. The correctness of the above said fact brought to the notice of this court by the learned counsel for the petitioner is not disputed. It is the further contention of the learned counsel for the petitioner that only in order to cause confusion and make the proceedings unwieldy with the ultimate aim of preventing the petitioner from getting an early verdict in the suit, the respondent has chosen to make the counter claim in respect of an entirely different set of facts and also in respect of properties, which have no connection with the properties concerned in the suit filed by the revision petitioner.

7. On perusal of the schedules provided in the plaint and the schedules provided in the counter-claim, this Court is able to find that the respondent/defendant has not made any claim of easement or licence in respect of any of the properties of the revision petitioner/plaintiff. Still, by projecting a cause of action as if the revision petitioner/plaintiff was trying to prevent the use of the pipe line meant for irrigating his properties in S.No.613/1A3, 613/4 and 614/1B2 of V





1