2016 Supreme(Mad) 57

IN THE HIGH COURT OF MADRAS MADURAI BENCH
V. Ramasubramanian & N. Kirubakaran, JJ.
S. Ramesh – Appellant
Vs.
Cethar Ltd. and Others – Respondents
Writ Appeal (MD) No. 1122 of 2015 and M.P. (MD) Nos. 1 and 2 of 2015
Decided On : 12-1-2016

Subject

Labour Law - Industrial Disputes

Act Referred

COMPANIES ACT : S.529(a)
CONSTITUTION OF INDIA : Art.226

Headnote

Payment of Wages Act - Companies Act, 1956 - Section 529-A - Constitution of India, 1950 - Article 226 – Employment and Service matter – Workmen - Lockout - Seeking police protection for removal of goods from their factory premises - Management of a Company - Nonpayment of salary - Appellant is General Secretary of Trade Union of Workers, employed in first respondent Company - First respondent filed an application with Government for permission to layoff - But, by G.O. Ms request for layoff was turned down by Government - Thereafter, management failed to pay salary to workers from January, 2015 - Hence, workers started staging a protest inside factory premises - However, salary for January, 2015 alone was paid - Thereafter, management declared a lockout - Appellant union raised an Industrial Dispute, claiming that lockout was illegal - Held, Admittedly, this represents salary payable by management to workers for months of February and March, 2015 - Lockout was declared only therefore, this amount now lying in fixed deposit is an undisputed amount, payable without any valid objection to workers - Payment of this amount would not even depend upon outcome of industrial dispute, as same represents wages for period prior to lockout - As a matter of fact, management is liable for prosecution under provisions of Payment of Wages Act, for nonpayment of salary for February and March, 2015 - Management cannot any more lay a claim for an amount now lying in fixed deposit, as it represents not only salary payable to workers for undisputed period but also represents value of goods removed, pursuant to interim orders passed by Single Judge - It is needless to point out that a person who enjoyed benefit of an interim order, is liable to compensate other party, when main case is decided against him - Writ appeal is disposed of

Advocates:
Advocate Appeared:
For Appellant: V. Prakash, Senior Counsel for Lakshi Gopinathan.
For Respondent: K. Govindarajan for T. Antony Arul Raj.

JUDGMENT :

V. Ramasubramanian, J.

1. The writ appeal arises out of an order passed by a learned Single Judge in a writ petition filed by the Management of a Company, seeking a mandamus to provide police protection for the removal of the goods from their factory premises, which is under lockout.

2. We have heard Mr. V. Prakash, learned senior counsel appearing on behalf of Mrs. Lakshmi Gopinathan, learned counsel for the appellant and Mr. K. Govindarajan, learned counsel appearing for the first respondent and Mr. N. Manoharan, learned Special Government Pleader appearing for respondents 2 to 4.

3. The appellant is the General Secretary of the Trade Union of Workers, employed in the first respondent Company. The first respondent filed an application with the Government for permission to layoff. But, by G.O. Ms. No. 85 dated 04.08.2014, the request for layoff was turned down by the Government.

4. Thereafter, the management failed to pay salary to the workers from January, 2015. Hence, the workers started staging a protest inside the factory premises.

5. In a peace committee meeting held on 17.03.2015, the management agreed to pay salary to the workers. However, the salary for January, 2015 alone was paid.

6. Thereafter, the management declared a lockout on 4.04.2015. The appellant union raised an Industrial Dispute on 06.04.2015, claiming that the lockout was illegal. The Deputy Commissioner of Labour, Trichy, initiated conciliation proceedings, but the same ended in failure.

7. Thereafter, the first respondent management gave a representation on 17.06.2015, seeking police protection for the removal of the goods on the ground that the goods belonged to their customers. Within a week of giving such a representation, the management came up with a writ petition in W.P. (MD) No. 10685 of 2015 seeking the issue of a writ of mandamus to direct the police to provide protection to enable them to remove the materials.

8. Unfortunately, the management did not implead the trade union as a party to the writ petition, though the grant of the relief prayed for in the writ petition would have been to the detriment of the workers. But, fortunately, the General Secretaries of two trade unions filed applications in M.P. (MD) No. 1 of 2015 and got impleaded as respondents 4 and 5. Thereafter, one of the customers of the first respondent management also got impleaded as the 6th respondent to the writ petition.

9. On 21.07.2015, a learned Judge of this Court passed an interim order appointing an Advocate Commissioner to take an inventory of the raw materials and to hand-over the raw materials to the suppliers of the first respondent management. But, this order was passed on the basis of an undertaking that arrears of salary would be paid.

10. However, the Advocate commissioner filed a Report on 07.08.2015 indicating that out of the four customers of the first respondent management, only one was present during the inspection and that even the said customer did not bring the amount payable to the first respondent company. There was also a dispute as to whether the material lying in the premises were raw materials or not. But, the company, which was impleaded as the 6th respondent to the writ petition came up with a demand draft for a sum of Rs. 14,25,027/- as the value of their goods, which they wanted to remove.

11. On the basis of the said Report, another interim order was passed on 03.09.2015, directing the Advocate Commissioner to assess the value of the materials found in the factory premises of the first respondent company, with the help of experts from BHEL. A further direction was issued to the Advocate Commissioner to deposit the demand drafts collected from the suppliers with this Court. The Registry was directed to deposit the same in fixed deposit.

12. Thereafter, the Advocate Commissioner deposited four demand drafts of the total value of Rs. 61,82,321.00, with the Indian Bank, High Court Branch. He also made an attempt to make a second inspection. Bu

















1
2
3
4
5
6
7
8
9
10