2016 Supreme(Mad) 3838
MADRAS HIGH COURT
M.V. Muralidaran, J.
N. Kanagaraj - Petitioner
Versus
Udavdoss Company, by its Proprietors, Shyam Sundar Sapriya S/o Udavadass and Another - Respondents
C.R.P. (NPD) No. 2406 of 2008 and M.P. No. 1 of 2008
Decided On : 08-12-2016
Subject
Civil Law - Execution of Decree
Act Referred
Headnote
Recovery of amount - Suit was decreed - Petitioner/judgment debtor is that the respondent/plaintiff has filed the suit in O.S. on the file of the Sub-Judge, Salem for recovery of amount and the suit was decreed directing this petitioner/judgment debtor to pay a sum of Rs. 25,000/- with interest – Held, Court for interference in the order passed in R.E.P. in O.S. on the file of the Additional Sub-Judge, Salem. In the interest of justice, it is just and necessary, this Court ought to have set aside the order in R.E.A. in R.E.P.in O.S. passed by the Additional Sub Court, Salem - Civil Revision Petition is allowed
For the Petitioner:P. Jagadeesan, Advocate.
For the Respondents:R. Margabandhu, Advocate.
M.V. Muralidaran, J.
This Civil Revision Petition has been filed by the petitioner/ Judgment debtor/defendant in R.E.A. No. 448 of 2007 in R.E.P. No. 73 of 2005 in O.S. No. 417 of 1995, dated 18.06.2008, on the file of the Additional Sub Judge, Salem.
2. The case of the petitioner/judgment debtor is that the respondent/plaintiff has filed the suit in O.S. No. 417 of 1995, on the file of the Sub-Judge, Salem for recovery of amount and the suit was decreed on 07.10.2002 directing this petitioner/judgment debtor to pay a sum of Rs. 25,000/- with interest.
3. Pursuant to the decree, the respondent/plaintiff has filed R.E.P. No. 73 of 2005 before the Additional Sub-Judge, Salem for executing the decree dated 07.10.2002 obtained by him for a sum of Rs. 44,450/-. Notice was sent to this petitioner/judgment debtor, but he was not appeared in the Court. Hence, the Additional Sub Judge, has brought the property for auction sale. Accordingly, the second respondent has bid the property for a sum of Rs. 2,52,000/- on 13.06.2007.
4. On knowing about the auction sale dated 13.06.2007, this petitioner/judgment debtor has filed an application in R.E.A. No. 448 of 2007 by depositing the amount for a sum of Rs. 66,458/- towards the sale warrant and commission, poundage, interest and expenses for set aside the auction sale dated 13.06.2007. On receipt of the notice, counter affidavit has been filed by the first respondent stating that it is true that the properties were sold in the execution proceedings initiated by the first respondent and the second respondent bid the auction held on 13.06.2007 for a sum of Rs. 2,52,000/-. The respondent also admitted that the petitioner has deposited Rs. 66,458/- towards sale warrant and commission, poundage, interest and expenses. But, the calculation made by the petitioner/judgment debtor is not correct.
5. The first respondent also states that mere deposit of the above amount will not entitle the petitioner to set aside the auction held on 13.06.2007. This respondent also held that the petitioner/judgment debtor borrowed more money for the business from the first respondent and the petitioner/judgment debtor has failed to repay the due to the first respondent. Therefore, the first respondent has filed a suit in O.S. No. 1935 of 2004, on the file of the Principal District Munsif, Salem and obtained a decree with costs for a sum of Rs. 1,25,771.50/-. Thereafter, the first respondent has also filed another suit for recovery of amount in O.S. No. 779 of 1995, on the file of the Additional Sub-Judge, Salem and suit was decreed as prayed for a sum of Rs. 2,67,549/- with cost. Subsequently, the first respondent has filed another three suits in O.S. No. 403 of 1994, O.S. No. 417 of 1995 and O.S. No. 410 of 1995, on the file of the Sub-Court, Salem, all the suits were decreed as prayed for and a sum of Rs. 79.797.95/-, Rs. 53,822/- and Rs. 1,80,492.20/- respectively, which was due by the petitioner/ judgment debtor. Therefore, the first respondent has claimed the amount that the plaintiff as a decree holder stating that as on date, this petitioner/judgment debtor has to pay a sum of Rs. 7,30,142/- with subsequent interest after the above said decree. For that, the first respondent/decree holder also filed four execution petitions before the Additional Sub-Court, Salem and the same is pending. While pendency of the above execution petitions, this petitioner/judgment debtor had encumbered the properties to the third parties in order to deprive the lawful claim of this first respondent/decree holder and also stating that the petitioner and his daughters were colluded together and created a decree to deprive the first respondent from recovering the fruits of the decree. Therefore, the compromise decree in I.A. No. 582 of 2006 in O.S. No. 66 of 2005 is not proved and will not binding on the first respondent.
6. Thou