2018 Supreme(Mad) 2619
IN THE HIGH COURT OF JUDICATURE AT MADRAS
M.V. MURALIDARAN, J.
Krishnasamy Chettiar & Ors. - Petitioners
Versus
Velu Odayar (died) & Ors. - Respondents
C.R.P.(NPD) No.397 of 2005
Decided On : 06-06-2018
Subject
Execution of Decree - Delivery of Property
Act Referred
Headnote
Code of Civil Procedure, 1908 - Section 47 and 115 - Possession Of Suit Property - Petitioners 1 and 2 are defendants and suit has been filed by plaintiff for delivery of vacant possession of suit property by defendants after dismantling superstructure put up by them and payment of arrears of rent and also damages for use and occupation till surrendering possession of suit property - By judgment suit was decreed and for execution of decree respondents herein have filed - Refuting defendants have filed counter stating that property described in decree was not available for execution as it lacks precision by non-mentioning of survey number and correct boundary - Therefore due to lack of clarity and identity of property decree is not executable - It is stated that decree in was injuncted from execution wherein a decree was passed and decree passed was still valid binding and became final as there was no appeal or revision filed - execution of decree - It is also stated that filed by respondents was barred by limitation – Held, I find that there is no error in ordering delivery of property by Executing Court and there is also no stay obtained from higher court for execution of decree - Therefore in absence of any stay order from higher court executing court was right in ordering delivery of property mentioned - There is no justification for this court in interfering with order of executing court - Exercise of revisional powers is purely discretionary - High court will not take a technical view and necessarily interfere in every case where an order is wrong and even improper if such interference will produce hardship or injustice - Revisional jurisdiction of court is intended to secure and sub-serve ends of justice and not to deny or defect it - If interference in a particular case will result in hardship or injustice to a party high court will be justified in refusing to interfere in exercise of its revisional jurisdiction even if order is found to be one without jurisdiction - Petition is dismissed
For the Petitioners: Mr. R. Natarajan.
For the Respondents: Mr. T.P. Manoharan Senior Counsel for M/s. K.P. Jotheeswaran.
1. This Civil Revision Petition has been originally filed by the petitioners 1 and 2 challenging the order passed in E.P.No.26 of 2004 in O.S.No.7 of 1977 on the file of the Principal District Munsif Court, Karaikal dated 22.07.2004, whereby the Executing Court ordered delivery of the property.
2. The petitioners 1 and 2 are defendants in O.S.No.7 of 1977 and the suit has been filed by the plaintiff Velu Odayar for delivery of vacant possession of the suit property by the defendants after dismantling the superstructure put up by them and payment of arrears of rent and also damages for the use and occupation till surrendering possession of the suit property. By the judgment dated 29.11.1979, the suit was decreed and for execution of the decree, the respondents herein have filed E.P.No.26 of 2004.
3. Refuting E.P.No.26 of 2004, the defendants have filed counter stating that the property described in the decree was not available for execution, as it lacks precision by non-mentioning of the survey number and correct boundary. Therefore, due to lack of clarity and identity of the property, the decree is not executable. It is stated that the decree in O.S.No.7 of 1977 was injuncted from execution in O.S.No.112 of 1992 (filed by the defendants in O.S.No.7 of 1977), wherein a decree was passed on 21.07.1995 and the decree passed in O.S.No.112 of 1992 was still valid, binding and became final, as there was no appeal or revision filed. The execution of the decree in O.S.No.112 of 1992 is pending in E.P.No.37 of 2003. It is also stated that E.P.No.26 of 2004 filed by the respondents was barred by limitation.
4. Pending E.P.No.26 of 2004, the defendants have filed E.A.No.309 of 2004 under Section 47 of the Code of Civil Procedure, 1908 alleging that the property mentioned in the Execution Petition is not a private property and it is a poramboke property, which necessitated the filing of the suit being O.S.No.112 of 1992 with its specific identification and survey numbers seeking that the decree in O.S.No.7 of 1977 is not valid and cannot be executed. According to the defendants, the property described in O.S.No.7 of 1977 and O.S.No.112 of 1992 are one and the same.
5. Upon consideration of the rival submissions, the Executing Court ordered delivery of the property in E.P.No.26 of 2004. Challenging the same, the defendants have filed the present Civil Revision Petition. Pending Civil Revision Petition, the second defendant, who is the second petitioner died and his legal heirs were impleaded as petitioners 3 to 11 in this Civil Revision Petition.
6. I heard Mr. R. Natarajan, learned counsel for the petitioners and Mr. T.P. Manoharan, learned Senior Counsel for M/s. K.P. Jotheeswaran, learned counsel for the respondents 2, 3, 4 and 5 and also perused the materials available on record.
7. The learned counsel for the petitioners submitted that the impugned order dated 22.07.2004 passed in E.P.No.26 of 2004 by ignoring the decree that was passed in O.S.No.112 of 1992, dated 21.07.1995 which restrained by an order of permanent injunction the execution of the decree passed in O.S.No.7 of 1977, is against the law, legality, contrary to public policy and without jurisdiction. He submitted that the Executing Court ought not to have entertained E.P.No.26 of 2004 for enforcement of the decree in as much as the life of the decree that was passed on 29.11.1979 stood eclipsed and became inoperative by reason of the decree passed in O.S.No.112 of 1992. He argued that the impugned order of the Executing Court is perverse and without jurisdiction. In support of his submissions, the learned counsel relied upon the following decisions:
(i)State of W.B. v. Hemant Kumar Bhattacharjee and others, reported in AIR 1966 SC 1061.
(ii)State of Punjab v. Bhag Singh, reported in (2004) 1 SCC 547.
8. Per contra, the learned Senior Counsel appearing for the respondents argued that after a hot contest only the suit in O.S.No.7 of 1977 was decreed by the trial Court. Aggrie