2019 Supreme(Mad) 1936

IN THE HIGH COURT OF JUDICATURE AT MADRAS
Senthilkumar Ramamoorthy, J.
The Secretary to Government, Government of Tamil Nadu, Rep. by the Superintending Engineer(H), Thanjavur - Appellant
Versus
SPL Infrastructure Private Limited (formerly S.P. Lakshmanan), Chennai & Others - Respondent
O.P. No. 431 of 2010
Decided On : 17-10-2019

Important Points

An arbitral award may be set aside wholly or in part by applying the principle of severance, as held in R.S.Jiwani v. Ircon International Ltd. 2010 (112) Bom LR 491(FB) and other judgments, and there are compelling reasons to sever the Award, in this case, including in respect of amounts awarded in respect of individual bridges. If severance is not applied, the parties would be back to the starting block after being involved in a protracted dispute resolution process till date.

Subject

Arbitration Law - SETTING ASIDE OF ARBITRAL AWARD

Act Referred

ARBITRATION AND CONCILIATION ACT : S.34, S.31(7)(b)
CONTRACT ACT : S.55

Headnote

The Arbitration Act- Section 31(7)(b)- section 34 -The Award in respect of the claim for overheads is not liable to be set aside under section 34 of the Arbitration Act- The Award in respect of post-Award interest at 12% per annum is reasonable in the context of Section 31(7)(b) of the Arbitration Act, as applicable to this case, and, therefore, does not warrant interference.

Statement of facts:

The respondent in the Arbitration Proceeding is the Petitioner before this Court. The Petitioner awarded a contract to the first Respondent herein for the design and construction/re-construction of five bridges in the Pudukottai District on turnkey basis under package number X through the Superintending Engineer, TNADP Circle, Trichy, under Letter of Acceptance dated 23.02.1999.

Finding of the court:

It is not possible to re-work the amounts due to the first Respondent for several reasons, including the non-availability of the documents that were filed/exhibited in the arbitration proceeding. Nonetheless, as a corollary to the conclusion in the preceding paragraph, the first Respondent is granted leave to re-work the amounts due and payable as per the Award, on the above basis, in respect of the First, Second and Third Bridges and in respect of post-Award interest on the revised aggregate amount and make an aggregate claim on the Petitioner. In the event of non-payment, the first Respondent is granted leave to initiate execution proceedings or other appropriate proceedings for the limited purpose of crystallising and recovering amounts due and payable, as per the Award read with this order, in respect of the First, Second and Third Bridges or the post-Award interest claim on the aggregate amount

Result: Award is partially set aside

Advocates Appeared:
For the Petitioner: Sricharan Rangarajan, Special Government Pleader.
For the Respondents: D. Balaraman, Adv.

JUDGMENT :

Prayer: Original Petition is filed under Section 34 of the Arbitration and Conciliation Act, 1996 to set aside the Arbitral Award dated 20.12.2008 passed by the Arbitral Tribunal.

1. The respondent in the Arbitration Proceeding is the Petitioner before this Court. The Petitioner awarded a contract to the first Respondent herein for the design and construction/re-construction of five bridges in the Pudukottai District on turnkey basis under package number X through the Superintending Engineer, TNADP Circle, Trichy, under Letter of Acceptance dated 23.02.1999. Pursuant thereto, an Agreement was executed on 15.03.1999 (the Contract) for a total contract value of Rs.8,18,60,000/-. During the execution of the Contract, certain differences and disputes arose between the Petitioner and the first Respondent herein and the said disputes were referred to arbitration under the arbitration clause in the General Conditions of Contract. The first Respondent herein made claims in respect of each of the bridges. These claims were modified during the course of the Arbitration Proceeding. After modification, the first Respondent herein made aggregate claims of Rs.18,29,437/- in respect of the bridge at km 30/10 of Pudupatti Nedungadi Road (the First Bridge); Rs.28,85,648/- in respect of the bridge at km 135/8 of Perambalur Manamadurai Road (the Second Bridge); Rs.18,01,595/- in respect of the bridge at km25/8 of Arantangi Kattumavadi Road (the Third Bridge); Rs.68,60,546/- in respect of the bridge at km 112/2 of Peramabalur Manamadurai Road (the Fourth Bridge); and Rs.15,69,024/- in respect of the bridge at km 4/10 of Pudukkottai Embal Road (the Fifth Bridge). These claims were in respect of escalation in cost of materials and labour, overhead charges and loss of profits for all bridges, and in respect of refund of liquidated damages, additional expenses towards preparation of design, earth work and widening of the approach at the curve in some bridges. Upon consideration of the pleadings, documents, oral and written arguments, the Arbitral Tribunal pronounced Arbitral Award dated 20.12.2008 (the Award). By the said Award, the Petitioner herein was directed to pay the first Respondent herein an aggregate sum of Rs.84,48,156/- in respect of all five bridges with interest thereon from the date of Award till the date of payment at 12% per annum. The said Award is impugned in this Petition.

2. I heard the learned Special Government Pleader (CS) (the SGP), Mr.Sricharan Rangarajan, on behalf of the Petitioner and the learned counsel for the first Respondent, Mr.D.Balaraman.

3. The learned SGP opened his oral submissions by raising three contentions on the apportionment of delay in respect of the submission of and approval of designs and drawings by the Arbitral Tribunal. Although these contentions were raised in the overall context of the challenge to the Award, they would be significant in the context of the First and Second Bridges and relevant though not significant in the context of the Third Bridge and not relevant in the factual context of the Fourth and Fifth Bridges, where the claims were not made on the basis of alleged delay in approval of detailed designs and drawings. His first contention, in this regard, was that the Arbitral Tribunal failed to appreciate the fact that the initial delay was admittedly on the part of the first Respondent herein with regard to the submission of designs and drawings. In specific, he submitted that the Contract specified that detailed designs and drawings should be submitted within 60 days whereas the first Respondent admittedly submitted such detailed designs and drawings in respect of the First Bridge on 10.06.1999, instead of 15.05.1999, after a delay of about 25 days. According to the learned SGP, this had a cascading effect on subsequent work. In order to fortify this submission, he relied upon the judgment of the Division Bench of the Hon’ble Delhi High Court in NTPC Ltd. v. Deconar Services Ltd

1
2
3
4
5
6
7
8
9
10
11