IN THE HIGH COURT OF JUDICATURE AT MADRAS
N. Sathish Kumar, J.
Tuticorin Port Trust (V.O.Chidambaranar Port Trust), Tuticorin - Petitioner
Versus
M/s. Jan De Nul Dredging India Pvt. Ltd., Chennai & Others - Respondent
O.P. No. 152 of 2015
Decided On : 10-09-2019
Arbitration and Conciliation Act - Tuticorin Port Trust - Section 34 of the Arbitration and Conciliation Act, 1996 - Summary of Acts and Sections: The court discussed the Major Port Trust Act 1963, Indian Companies Act 1956, and various clauses of the contract including Clause 10, Clause 14.1, Clause 44, and Clause 57.1. The court also referred to Clause 38 of Section 3 of the contract. The court analyzed the legal provisions related to reimbursement of charges, soil conditions, customs duties, reclassification of works, equipment idling, and interest payment.
Fact of the Case:
The Tuticorin Port Trust filed a petition under Section 34 of the Arbitration and Conciliation Act, 1996 to set aside an arbitral award. The dispute arose from a contract for deepening the channel and basin at Tuticorin Port. The claimant raised multiple claims, some of which were allowed by the arbitrators. The petitioner challenged the award, primarily focusing on the claim related to equipment idling due to the respondent's failure to provide possession and access to the site.
Finding of the Court:
The court found that the contract did not restrict the use of more than one dredger, and the choice of technology and equipment was left to the contractor. The court upheld the arbitrators' decision to allow the claim for equipment idling, as it was in accordance with the contract and the evidence presented. The court also rejected the petitioner's request to reduce the interest awarded by the arbitrators.
Issues: The issues included the entitlement to various claims, such as reimbursement of charges, soil conditions, customs duties, reclassification of works, equipment idling, and interest payment. The court also considered the applicability of specific clauses in the contract and the defense raised by the respondent.
Ratio Decidendi: The court's decision was based on the interpretation of the contract, specifically the clauses related to equipment deployment, work conditions, and payment terms. The court upheld the arbitrators' findings and rejected the petitioner's contentions, emphasizing that the award was in line with the contractual provisions and the evidence presented.
Final Decision: The Original Petition filed by Tuticorin Port Trust was dismissed by the court, and no costs were awarded.
JUDGMENT :
Prayer: Petition filed under Section 34 of the Arbitration and Conciliation Act, 1996 praying to set aside the Award dated 18.10.2014 insofar as it allows the claim No.3,4,5,6,7,9 and 10 vide “Part L” of the award amounting to Rs.426,883,388/- passed by the Respondents 2 to 4 along with costs.
1. Challenging the Three Members Arbitral Award, the present Original Petition has been filed.
2. The brief facts leading to file this Original Petition is as follows:
2.(a) The Petitioner viz., Tuticorin Port Trust is a Board of Trustees constituted under Section 3 of Major Port Trust Act 1963. Claimant company registered under the Indian Companies Act 1956. The Petitioner’s Port invited tenders consisting of technical/commercial bid with respect to work - ‘Deepening of the Channel and Basin to Cater to 12.80 M Draught Vessel at Tuticorin Port’. The claimant was one of the bidders and work order was issued on 28.10.2010. Formal contract was executed on 27.12.2010. The material events which have taken place before the Tribunal are set out in the following table:
DATES AND EVENTS
| S.No. | Date | Description |
| 1 | 15/07/2009 | Notice inviting tender issued |
| 2 | 20/08/2009 | Pre-bid meeting with tenderers |
| 3 | 26/08/2009 | Port’s clarifications to the pre-bid queries received |
| 4 | 07/09/09 | Originally scheduled date of submission of bid and opening of tender |
| 5 | 30/09/2009 | Amended last date for submission of tender (1st extension) |
| 6 | 15.10.2009 | Amended last date for submission of tender (2nd extension) |
| 7 | 30.10.2009 | Amended last date for submission of tender (3rd extension) |
| 8 | 09/11/09 | Amended last date for submission of tender (4th extension) |
| 9 | 28.10.2010 | Issue of Work order |
| 10 | 27.12.2010 | Formal Contract executed |
| 11 | 28.12.2010 | Commencement of dredging works |
| 12 | 01/01/11 | Monthly Running Account Statement 001Running Account Bill Mobilisation No.JDN-001 |
| 13 | 17.03.2011 to 03.09.2011 | Soil investigation by Fugro Geotech |
| 14 | 31.08.2011 | Dredging Works completed |
| 15 | 030911 | BHD Jerommeke demobilized and dispatched via M/v Sky Oceanus |
| 16 | 26.08.2011 to 03.09.2011 | Join gt Post dredge survey along with independent third party surveyor |
| 17 | 06.09.11 | Post dredge survey details including draft final statement along with bill of quantities submitted to the Respondent. |
| 18 | 06.09.11 | Final Account statement - 009 (including idle time)Running Account bill dredging works - final statement no.JDN 018 (excluding idle time) Demobilisation bill No.JDN-019 Running account bill - fuel escalation final statement JDN-020 |
| 19 | 08/09/11 | Post dredge survey charts certified by third party submitted to the Respondent. |
| 20 | 20/09/2011 | CSD Zheng He demobilized |
| 21 | 30/09/2011 | site cleared by Claimant |
| 22 | 19/11/2011 | Post Commissioned at New Depth of 14.10 m CD in basin and 14.70 m CD in approach channel |
| 23 | 02/04/12 | Taking over certificate and Defect Liability Period Certificate received from the Respondent indicating the conclusion of all Works under the contract. |
| 24 | 29.05.2012 | claimant submits final statement |
| 25 | 25.07.2012 | Respondent bill of quantities received |
| 26 | 06/08/12 | Notice issued to Respondent on final payments |
| 27 | 24.08.2012 | Retention money received |
| 28 | 20.09.2012 | Reference to Arbitration |
| 29 | 19.11.2012 | Rs.95,23,861 - Part release of recovered money in running bills. |
2(b) The claimant has raised the following claims:
| BoQ | BoQ payments overdue as per Respondent’s final Quantities dated 25.07.2012 | 199,632,249 |
| Claim No.1 | Reimbursement of Wharfage Charges | 14,065,411 |
| Claim No.2 | Soil Conditions in the Approach Channel | 1,27,72,15,471 |
| Claim No.3 | Reimbursement of Customs Du | |
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.