2019 Supreme(Mad) 2551

IN THE HIGH COURT OF JUDICATURE AT MADRAS
N. Sathish Kumar, J.
Tuticorin Port Trust (V.O.Chidambaranar Port Trust), Tuticorin - Petitioner
Versus
M/s. Jan De Nul Dredging India Pvt. Ltd., Chennai & Others - Respondent
O.P. No. 152 of 2015
Decided On : 10-09-2019

Advocates Appeared:
For the Petitioner:Yashodvardhan, S. Yashwanth, Advocates.
For the Respondents:Jose John for M/s. Kindgs & Patridge, Advocates.

The main legal point established in the judgment is that the interpretation of contractual clauses and the application of contract terms play a crucial role in determining the entitlement to claims and interest payments in arbitration disputes.

Headnote:

Arbitration and Conciliation Act - Tuticorin Port Trust - Section 34 of the Arbitration and Conciliation Act, 1996 - Summary of Acts and Sections: The court discussed the Major Port Trust Act 1963, Indian Companies Act 1956, and various clauses of the contract including Clause 10, Clause 14.1, Clause 44, and Clause 57.1. The court also referred to Clause 38 of Section 3 of the contract. The court analyzed the legal provisions related to reimbursement of charges, soil conditions, customs duties, reclassification of works, equipment idling, and interest payment.

Fact of the Case:

The Tuticorin Port Trust filed a petition under Section 34 of the Arbitration and Conciliation Act, 1996 to set aside an arbitral award. The dispute arose from a contract for deepening the channel and basin at Tuticorin Port. The claimant raised multiple claims, some of which were allowed by the arbitrators. The petitioner challenged the award, primarily focusing on the claim related to equipment idling due to the respondent's failure to provide possession and access to the site.

Finding of the Court:

The court found that the contract did not restrict the use of more than one dredger, and the choice of technology and equipment was left to the contractor. The court upheld the arbitrators' decision to allow the claim for equipment idling, as it was in accordance with the contract and the evidence presented. The court also rejected the petitioner's request to reduce the interest awarded by the arbitrators.

Issues: The issues included the entitlement to various claims, such as reimbursement of charges, soil conditions, customs duties, reclassification of works, equipment idling, and interest payment. The court also considered the applicability of specific clauses in the contract and the defense raised by the respondent.

Ratio Decidendi: The court's decision was based on the interpretation of the contract, specifically the clauses related to equipment deployment, work conditions, and payment terms. The court upheld the arbitrators' findings and rejected the petitioner's contentions, emphasizing that the award was in line with the contractual provisions and the evidence presented.

Final Decision: The Original Petition filed by Tuticorin Port Trust was dismissed by the court, and no costs were awarded.

JUDGMENT :

Prayer: Petition filed under Section 34 of the Arbitration and Conciliation Act, 1996 praying to set aside the Award dated 18.10.2014 insofar as it allows the claim No.3,4,5,6,7,9 and 10 vide “Part L” of the award amounting to Rs.426,883,388/- passed by the Respondents 2 to 4 along with costs.

1. Challenging the Three Members Arbitral Award, the present Original Petition has been filed.

2. The brief facts leading to file this Original Petition is as follows:

2.(a) The Petitioner viz., Tuticorin Port Trust is a Board of Trustees constituted under Section 3 of Major Port Trust Act 1963. Claimant company registered under the Indian Companies Act 1956. The Petitioner’s Port invited tenders consisting of technical/commercial bid with respect to work - ‘Deepening of the Channel and Basin to Cater to 12.80 M Draught Vessel at Tuticorin Port’. The claimant was one of the bidders and work order was issued on 28.10.2010. Formal contract was executed on 27.12.2010. The material events which have taken place before the Tribunal are set out in the following table:

DATES AND EVENTS

S.No.

Date

Description

1

15/07/2009

Notice inviting tender issued

2

20/08/2009

Pre-bid meeting with tenderers

3

26/08/2009

Port’s clarifications to the pre-bid queries received

4

07/09/09

Originally scheduled date of submission of bid and opening of tender

5

30/09/2009

Amended last date for submission of tender (1st extension)

6

15.10.2009

Amended last date for submission of tender (2nd extension)

7

30.10.2009

Amended last date for submission of tender (3rd extension)

8

09/11/09

Amended last date for submission of tender (4th extension)

9

28.10.2010

Issue of Work order

10

27.12.2010

Formal Contract executed

11

28.12.2010

Commencement of dredging works

12

01/01/11

Monthly Running Account Statement 001Running Account Bill Mobilisation No.JDN-001

13

17.03.2011 to 03.09.2011

Soil investigation by Fugro Geotech

14

31.08.2011

Dredging Works completed

15

030911

BHD Jerommeke demobilized and dispatched via M/v Sky Oceanus

16

26.08.2011 to 03.09.2011

Join gt Post dredge survey along with independent third party surveyor

17

06.09.11

Post dredge survey details including draft final statement along with bill of quantities submitted to the Respondent.

18

06.09.11

Final Account statement - 009 (including idle time)Running Account bill dredging works - final statement no.JDN 018 (excluding idle time)

Demobilisation bill No.JDN-019

Running account bill - fuel escalation final statement JDN-020

19

08/09/11

Post dredge survey charts certified by third party submitted to the Respondent.

20

20/09/2011

CSD Zheng He demobilized

21

30/09/2011

site cleared by Claimant

22

19/11/2011

Post Commissioned at New Depth of 14.10 m CD in basin and 14.70 m CD in approach channel

23

02/04/12

Taking over certificate and Defect Liability Period Certificate received from the Respondent indicating the conclusion of all Works under the contract.

24

29.05.2012

claimant submits final statement

25

25.07.2012

Respondent bill of quantities received

26

06/08/12

Notice issued to Respondent on final payments

27

24.08.2012

Retention money received

28

20.09.2012

Reference to Arbitration

29

19.11.2012

Rs.95,23,861 - Part release of recovered money in running bills.

2(b) The claimant has raised the following claims:

BoQ

BoQ payments overdue as per Respondent’s final Quantities dated 25.07.2012

199,632,249

Claim No.1

Reimbursement of Wharfage Charges

14,065,411

Claim No.2

Soil Conditions in the Approach Channel

1,27,72,15,471

Claim No.3

Reimbursement of Customs Du






      Click Here to Read the rest of this document
      1
      2
      3
      4
      5
      6
      7
      8
      9
      10
      11
      SupremeToday Portrait Ad
      supreme today icon
      logo-black

      An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

      Please visit our Training & Support
      Center or Contact Us for assistance

      qr

      Scan Me!

      India’s Legal research and Law Firm App, Download now!

      For Daily Legal Updates, Join us on :

      whatsapp-icon Back to top